ALDOT contract 20250926015 bid tabulation
INTERCHANGE LIGHTING ON I-65 AT THE CR-222 (EXIT 305) INTERCHANGE IN GOOD HOPE. Let by Alabama DOT on September 26, 2025, Cullman, 0104. 4 bids received; low bid $688,407 by Temple J Electric, LLC.
- Owner
- Alabama DOT
- Letting
- 26 SEP 2025
- Pay items
- 22
- Data through
- 28 AUG 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Temple J Electric, LLC | $688,407 | Low |
| 2 | Stone Electric Company, Inc. | $781,095 | +13% |
| 3 | Stone & Sons Electrical Contractors, Inc. | $808,080 | +17% |
| 4 | J. Ranck Electric, Inc. | $827,784 | +20% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Temple J Electric, LLC | 2. Stone Electric Company, Inc. | 3. Stone & Sons Electrical Contractors, Inc. | 4. J. Ranck Electric, Inc. |
|---|---|---|---|---|---|---|---|
| 0010 | Mobilization (600A000) | LS | 1 | $26,800 | $72,455 | $98,191 | $99,000 |
| 0020 | Filter blanket, geotextile (610D003) | SY | 500 | $4.79 | $4.50 | $6.50 | $5.00 |
| 0030 | Seeding (652A100) | ACRE | 1 | $1,750.00 | $1,850.00 | $2,380.00 | $1,750.00 |
| 0040 | Temporary mulching (665B001) | TON | 3 | $1,450.00 | $1,650.00 | $1,972.00 | $1,450.00 |
| 0050 | Sand bags (665G000) | EACH | 450 | $7.75 | $8.25 | $10.55 | $7.75 |
| 0060 | Wattle (665Q002) | LF | 1,500 | $10.75 | $10.75 | $14.60 | $10.75 |
| 0070 | Geometric controls (680A001) | LS | 1 | $15,000 | $6,500.00 | $5,437.00 | $15,000 |
| 0080 | Construction fuel (maximum bid limited to $ 22,750.00) (698A000) | LS | 1 | $10,000 | $100.00 | $19,000 | $22,750 |
| 0090 | Construction signs (740B000) | SF | 1,289 | $7.00 | $6.79 | $10.00 | $3.00 |
| 0100 | Special construction signs (740C000) | SF | 18 | $7.00 | $8.23 | $10.00 | $3.00 |
| 0110 | Channelizing drums (740D000) | EACH | 50 | $55.00 | $36.20 | $162.00 | $5.00 |
| 0120 | Portable sequential arrow and chevron sign unit (741C010) | EACH | 1 | $1,000.00 | $1,000.00 | $1,750.00 | $250.00 |
| 0130 | Portable changeable message sign, type 2 (742A001) | EACH | 2 | $15,000 | $1,500.00 | $3,750.00 | $3,500.00 |
| 0140 | Roadway luminaire assembly with one, LED, 250 watt equivalent luminaire (750B601) | EACH | 28 | $7,500.00 | $8,539.27 | $6,905.00 | $7,000.00 |
| 0150 | Pole foundation,roadway (750C010) | EACH | 28 | $4,000.00 | $5,547.70 | $3,950.00 | $5,000.00 |
| 0160 | Electrical junction box,type 1 (750D200) | EACH | 13 | $650.00 | $1,211.28 | $1,100.00 | $1,500.00 |
| 0170 | Conduit, 2 inch, rigid metallic (750E127) | LF | 150 | $12.00 | $24.34 | $21.00 | $30.00 |
| 0180 | Conductor, #2 AWG (750F026) | LF | 600 | $10.00 | $3.25 | $4.95 | $6.50 |
| 0190 | Combined duct and cable,2 #6 AWG/ 1 #6 AWG GND (750G010) | LF | 10,000 | $11.00 | $12.15 | $15.10 | $15.00 |
| 0200 | Service pole (750H005) | EACH | 2 | $3,000.00 | $3,877.68 | $3,391.00 | $6,250.00 |
| 0210 | Lighting control center (750I015) | EACH | 2 | $31,000 | $30,980 | $36,152 | $37,825 |
| 0220 | 6" electrical conduit, 1 line, type 5 installation (756A028) | LF | 705 | $70.00 | $72.97 | $88.50 | $70.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ALDOT's tabulation for this contract. ALDOT bid tabulation PDFs, one per letting, January 2022 to August 2026, with bidder names and totals from each letting's vendor ranking. Every bid matched its published total.
Every contract let that day: ALDOT letting of September 26, 2025. Compiled by Mirage Metrics.