ARDOT contract 061915 bid tabulation
THE PURPOSE OF THIS PROJECT IS TO PLACE GUARDRAIL IMPROVEMENTS ON I-57 IN PULASKI AND LONOKE COUNTIES. THIS PROJECT CONSISTS OF REMOVAL AND DISPOSAL ITEMS, TRENCHING AND SHOULDER PREPARATION, AGGREGATE BASE COURSE, ACHM SURFACE COURSE, APPROACH GUTTERS, MAINTENANCE OF TRAFFIC, GUARDRAIL, AND MISC. ITEMS. Let by Arkansas DOT on September 17, 2025, Lonoke, Pulaski. 1 bid received; low bid $2,763,348 by Creative Design Concepts, Inc..
- Owner
- Arkansas DOT
- Letting
- 17 SEP 2025
- Pay items
- 26
- Data through
- 04 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Creative Design Concepts, Inc. | $2,763,348 | Low |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Creative Design Concepts, Inc. |
|---|---|---|---|---|
| 0001 | Removal and disposal of approach gutters (202052) | EACH | 8 | $3,971.54 |
| 0002 | Removal and disposal of guardrail (202132) | LF | 2,050 | $15.00 |
| 0003 | Trenching and shoulder preparation (215011) | STA | 36 | $600.00 |
| 0004 | Aggregate base course (class 7) (303117) | TON | 1,531 | $122.50 |
| 0005 | Mineral aggregate in achm surface course (1/2") (407162) | TON | 216 | $478.50 |
| 0006 | Asphalt binder (PG 76-22) in achm surface course (1/2") (minimum bid $120.00) (407452) | TON | 13 | $925.00 |
| 0007 | Achm patching of existing roadway (415011) | TON | 50 | $315.00 |
| 0008 | Approach gutters (504264) | CY | 154.40 | $3,200.00 |
| 0009 | Portland cement concrete pavement patching (12" uniform thickness) (507232) | SY | 500 | $899.75 |
| 0010 | Mobilization (unit bid amount may not exceed 5% of subtotal) (601001) | LS | 1 | $131,588 |
| 0011 | Maintenance of traffic (603010) | LS | 1 | $322,000 |
| 0012 | Signs (604003) | SF | 2,342 | $14.00 |
| 0013 | Traffic drums (604023) | EACH | 2,213 | $54.00 |
| 0014 | Furnishing and installing precast concrete barrier (604031) | LF | 3,704 | $76.00 |
| 0015 | Relocating precast concrete barrier (max. bid 25% of item number ) (604036) | LF | 2,804 | $19.00 |
| 0016 | Advance warning arrow panel (604071) | DAY | 120 | $21.00 |
| 0017 | Portable changeable message sign (604078) | WEEK | 24 | $351.00 |
| 0018 | Mobile speed notification system (special) (604160) | EACH | 4 | $13,551 |
| 0019 | Guardrail (type A) (617005) | LF | 2,100 | $42.00 |
| 0020 | Guardrail terminal (type 2) (617312) | EACH | 14 | $4,300.00 |
| 0021 | Thrie beam guardrail terminal (617332) | EACH | 14 | $3,100.00 |
| 0022 | Wattle (20") (621173) | LF | 4,200 | $15.00 |
| 0023 | Temporary impact attenuation barrier (731061) | EACH | 6 | $12,000 |
| 0024 | Temporary impact attenuation barrier (repair) (731062) | EACH | 4 | $1,600.00 |
| 0025 | Temporary impact attenuation barrier (relocation) (731065) | EACH | 8 | $4,100.00 |
| 0026 | Reinforcing steel-roadway (grade 60) (804003) | LB | 12,796 | $3.50 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ARDOT's tabulation for this contract. ARDOT monthly bid tab PDFs (morning and afternoon sessions), January 2022 to November 2026. Base bids are printed in whole dollars; on A+B and A+C jobs the base bid is kept, and the published rank follows the award amount.
Every contract let that day: ARDOT letting of September 17, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.