ARDOT contract A20034 bid tabulation
THE PURPOSE OF THIS PROJECT IS TO MILL AND OVERLAY APPROXIMATELY 8.321 MILES OF HIGHWAY 425 IN JEFFERSON COUNTY. THIS PROJECT CONSISTS OF A REMOVAL AND DISPOSAL ITEM, AGGREGATE BASE COURSE, ACHM SURFACE COURSE, COLD MILLING ASPHALT PAVEMENT, ACHM PATCHING OF EXISTING ROADWAY, APPROACH GUTTERS, MAINTENANCE OF TRAFFIC, GUARDRAIL, RUMBLE STRIPS AND STRIPES, LOOP WIRING, PAVEMENT MARKING, AND MISC. ITEMS. Let by Arkansas DOT on April 9, 2025, Jefferson. 2 bids received; low bid $4,263,892 by Redstone Construction Group, Inc..
- Owner
- Arkansas DOT
- Letting
- 09 APR 2025
- Pay items
- 31
- Data through
- 04 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Redstone Construction Group, Inc. | $4,263,892 | Low |
| 2 | Pine Bluff Sand & Gravel Co. | $5,630,960 | +32% |
Bid tabulation
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ARDOT's tabulation for this contract. ARDOT monthly bid tab PDFs (morning and afternoon sessions), January 2022 to November 2026. Base bids are printed in whole dollars; on A+B and A+C jobs the base bid is kept, and the published rank follows the award amount.
Every contract let that day: ARDOT letting of April 9, 2025. Compiled by Mirage Metrics.