ARDOT contract A50040 bid tabulation
THE PURPOSE OF THIS PROJECT IS TO MICROSURFACE APPROXIMATELY 7.627 MILES OF HIGHWAY 106 IN INDEPENDENCE COUNTY. THIS PROJECT CONSISTS OF REMOVAL AND DISPOSAL ITEMS, MICROSURFACING, APPROACH GUTTERS, MAINTENANCE OF TRAFFIC, GUARDRAIL, PAVEMENT MARKING, AND MISC. ITEMS. Let by Arkansas DOT on February 26, 2025, Independence. 2 bids received; low bid $822,412 by Vance Brothers, Inc..
- Owner
- Arkansas DOT
- Letting
- 26 FEB 2025
- Pay items
- 17
- Data through
- 04 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Vance Brothers, Inc. | $822,412 | Low |
| 2 | Atlas Asphalt, Inc. | $1,134,348 | +38% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Vance Brothers, Inc. | 2. Atlas Asphalt, Inc. |
|---|---|---|---|---|---|
| 0001 | Removal and disposal of approach gutters (202052) | EACH | 4 | $3,967.51 | $3,707.95 |
| 0002 | Removal and disposal of guardrail (202132) | LF | 1,468 | $6.42 | $10.00 |
| 0003 | Microsurfacing (418301) | SY | 109,284 | $3.76 | $6.59 |
| 0004 | Approach gutters (504264) | CY | 39.04 | $2,064.81 | $1,929.73 |
| 0005 | Maintenance of traffic (603009) | LS | 1 | $22,882 | $38,581 |
| 0006 | Signs (604003) | SF | 633 | $6.42 | $5.00 |
| 0007 | Construction pavement markings (604041) | LF | 81,640 | $0.32 | $0.16 |
| 0008 | Guardrail (type A) (617005) | LF | 1,000 | $32.10 | $35.00 |
| 0009 | Guardrail terminal (type 2) (617312) | EACH | 7 | $3,103.00 | $3,300.00 |
| 0010 | Thrie beam guardrail terminal (617332) | EACH | 7 | $2,033.00 | $2,300.00 |
| 0011 | Thermoplastic pavement marking white (6") (719002) | LF | 82,040 | $0.75 | $0.65 |
| 0012 | Thermoplastic pavement marking white (12") (719005) | LF | 14 | $7.49 | $6.00 |
| 0013 | Thermoplastic pavement marking yellow (6") (719102) | LF | 81,740 | $0.75 | $0.65 |
| 0014 | Raised pavement markers (type II) (721002) | EACH | 510 | $3.75 | $4.00 |
| 0015 | Bridge end terminal (734011) | EACH | 1 | $28,890 | $32,000 |
| 0016 | Reinforcing steel-roadway (grade 60) (804003) | LB | 3,908 | $3.21 | $3.00 |
| 0017 | Mobilization (unit bid amount may not exceed 5% of subtotal) (601001) | LS | 1 | $18,190 | $28,005 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ARDOT's tabulation for this contract. ARDOT monthly bid tab PDFs (morning and afternoon sessions), January 2022 to November 2026. Base bids are printed in whole dollars; on A+B and A+C jobs the base bid is kept, and the published rank follows the award amount.
Every contract let that day: ARDOT letting of February 26, 2025. Compiled by Mirage Metrics.