ARDOT letting results, February 26, 2025

31 contracts let by Arkansas DOT on February 26, 2025, $93,642,745 in low bids, a median of 3 bidders per contract.

Owner
Arkansas DOT
Contracts
31
Low bids, total
$93,642,745
Data through
04 NOV 2026

Contracts let that day

ContractProjectCountyBidsLow bidderLow bidSecond bidGapSource
061708THE PURPOSE OF THIS PROJECT IS TO CONSTRUCT A NEW WESTBOUND RAMP AT CONGO ROAD, CONVERSTION OF EXISTING WESTBOUND ENTRANCE AT CONGO ROAD TO EXIT RAMP AND WIDEN Saline3Redstone Construction Group, Inc.$23,119,608$27,197,307+18%ARDOT
A70037THE PURPOSE OF THIS PROJECT IS TO MILL AND OVERLAY APPROXIMATELY 8.507 MILES OF HIGHWAY 79 IN CALHOUN COUNTY. THIS PROJECT CONSISTS OF REMOVAL AND DISPOSAL ITEMCalhoun1Jet Asphalt & Rock Co., Inc.$8,815,926ARDOT
A30041THE PURPOSE OF THIS PROJECT IS TO LEVEL AND OVERLAY APPROXIMATELY 13.318 MILES OF HIGHWAYS 29 AND 160 IN LAFAYETTE COUNTY. THIS PROJECT CONSISTS OF REMOVAL AND Lafayette4Jet Asphalt & Rock Co., Inc.$7,296,683$7,544,815+3.0%ARDOT
A40041THE PURPOSE OF THIS PROJECT IS TO MILL AND OVERLAY APPROXIMATELY 12.468 MILES OF HIGHWAY 62 IN WASHINGTON COUNTY. THIS PROJECT CONSISTS OF REMOVAL AND DISPOSAL Washington4Robinson Construction, LLC$4,987,983$5,180,369+4.0%ARDOT
A10045THE PURPOSE OF THIS PROJECT IS TO LEVEL AND OVERLAY APPROXIMATELY 14.379 MILES OF HIGHWAY 50 IN ST. FRANCIS COUNTY. THIS PROJECT CONSISTS OF REMOVAL AND DISPOSASt. Francis2Apac-Tennessee, Inc.$4,800,417$5,051,887+5.0%ARDOT
A10046THE PURPOSE OF THIS PROJECT IS TO MILL AND OVERLAY APPROXIMATELY 13.087 MILES OF HIGHWAY 79 IN LEE AND ST. FRANCIS COUNTIES. THIS PROJECT CONSISTS OF REMOVAL ANLee, St. Francis2Apac-Tennessee, Inc.$4,469,411$4,651,002+4.0%ARDOT
A90033THE PURPOSE OF THIS PROJECT IS TO MILL AND OVERLAY APPROXIMATELY 6.796 MILES OF HIGHWAYS 59 AND 59B IN BENTON COUNTY. THIS PROJECT CONSISTS OF REMOVAL AND DISPOBenton4Robinson Construction, LLC$3,895,792$4,027,149+3.0%ARDOT
A00085THE PURPOSE OF THIS PROJECT IS TO OVERLAY AND PERFORM FULL DEPTH RECLAMATION PROCESSES ON APPROXIMATELY 5.866 MILES OF HIGHWAY 328 IN RANDOLPH COUNTY. THIS PROJRandolph3Atlas Asphalt, Inc.$3,807,984$4,353,357+14%ARDOT
A40040THE PURPOSE OF THIS PROJECT IS TO MILL, OVERLAY, AND PLACE ULTRATHIN BONDED WEARING COURSE ON APPROXIMATELY 9.767 MILES OF HIGHWAYS 45 AND 271 IN SEBASTIAN COUNSebastian3Robinson Construction, LLC$3,745,972$3,944,618+5.0%ARDOT
A70034THE PURPOSE OF THIS PROJECT IS TO LEVEL AND OVERLAY APPROXIMATELY 5.443 MILES OF HIGHWAY 79 IN COLUMBIA COUNTY. THIS PROJECT CONSISTS OF REMOVAL AND DISPOSAL OFColumbia3Jet Asphalt & Rock Co., Inc.$3,472,528$3,940,326+13%ARDOT
A60049THE PURPOSE OF THIS PROJECT IS TO MILL AND OVERLAY APPROXIMATELY 4.341 MILES OF HIGHWAY 270 IN GARLAND COUNTY. THIS PROJECT CONSISTS OF AGGREGATE BASE COURSE, AGarland2Cranford Construction Co.$2,972,636$3,270,526+10%ARDOT
A00075THE PURPOSE OF THIS PROJECT IS TO MILL AND OVERLAY APPROXIMATELY 6.457 MILES OF HIGHWAYS 412 AND 412B IN LAWRENCE COUNTY. THIS PROJECT CONSISTS OF REMOVAL AND DLawrence3Atlas Asphalt, Inc.$2,937,871$3,624,503+23%ARDOT
A50038THE PURPOSE OF THIS PROJECT IS TO MILL AND OVERLAY APPROXIMATELY 5.972 MILES OF HIGHWAYS 69 AND 69B IN INDEPENDENCE COUNTY. THIS PROJECT CONSISTS OF REMOVAL ANDIndependence1Atlas Asphalt, Inc.$2,450,991ARDOT
A40042THE PURPOSE OF THIS PROJECT IS TO MILL AND OVERLAY APPROXIMATELY 3.505 MILES OF HIGHWAYS 64 AND 162 IN CRAWFORD COUNTY. THIS PROJECT CONSISTS OF ACHM SURFACE COCrawford3Robinson Construction, LLC$2,381,285$2,433,560+2.0%ARDOT
A60035THE PURPOSE OF THIS PROJECT IS TO RUT MILL AND OVERLAY APPROXIMATELY 5.331 MILES OF HIGHWAY 67 IN HOT SPRING COUNTY. THIS PROJECT CONSISTS OF REMOVAL AND DISPOSHot Spring2Cranford Construction Co.$2,124,354$2,182,836+3.0%ARDOT
A20032THE PURPOSE OF THIS PROJECT IS TO MILL, INLAY, AND OVERLAY APPROXIMATELY 5.207 MILES OF HIGHWAY 270 IN GRANT AND JEFFERSON COUNTIES. THIS PROJECT CONSISTS OF REGrant, Jefferson3Redstone Construction Group, Inc.$1,898,720$1,978,831+4.0%ARDOT
061744THE PURPOSE OF THIS PROJECT IS TO REPLACE A STRUCTURE WITH ONE R.C. BOX CULVERT ON HIGHWAY 86 IN PRAIRIE COUNTY. THIS PROJECT CONSISTS OF CLEARING AND GRUBBING,Prairie3Mobley Contractors, Inc.$1,527,197$2,389,999+56%ARDOT
A60048THE PURPOSE OF THIS PROJECT IS TO LEVEL AND OVERLAY APPROXIMATELY 4.073 MILES OF HIGHWAY 15 IN LONOKE COUNTY. THIS PROJECT CONSISTS OF AGGREGATE BASE COURSE, ACLonoke5CK Asphalt, LLC$1,399,172$1,445,843+3.0%ARDOT
040994THE PURPOSE OF THIS PROJECT IS TO REPLACE A STRUCTURE ON HIGHWAY 282 IN CRAWFORD COUNTY. THIS PROJECT CONSISTS OF CLEARING AND GRUBBING, REMOVAL AND DISPOSAL OFCrawford1Mobley Contractors, Inc.$1,267,441ARDOT
A80036THE PURPOSE OF THIS PROJECT IS TO PLACE ULTRATHIN BONDED WEARING COURSE ON APPROXIMATELY 2.665 MILES OF HIGHWAY 64 IN RUSSELLVILLE IN POPE COUNTY. THIS PROJECT Pope1Blackstone Construction, LLC$1,070,970ARDOT
A50040THE PURPOSE OF THIS PROJECT IS TO MICROSURFACE APPROXIMATELY 7.627 MILES OF HIGHWAY 106 IN INDEPENDENCE COUNTY. THIS PROJECT CONSISTS OF REMOVAL AND DISPOSAL ITIndependence2Vance Brothers, Inc.$822,412$1,134,348+38%ARDOT
SA3656THE PURPOSE OF THIS PROJECT IS TO SURFACE AND RESEAL APPROXIMATELY 12.68 MILES OF VARIOUS COUNTY ROADS IN JOHNSON COUNTY. THIS PROJECT CONSISTS OF RECONSTRUCTEDJohnson3Salt Creek Paving & Const. Co., Inc.$732,472$737,406+1.0%ARDOT
SA2251THE PURPOSE OF THIS PROJECT IS TO OVERLAY APPROXIMATELY 2.81 MILES OF COUNTY ROAD 15 IN DREW COUNTY. THIS PROJECT CONSISTS OF ACHM SURFACE COURSE, MAINTENANCE ODrew2Pine Bluff Sand & Gravel Co.$663,041$678,125+2.0%ARDOT
SA2456THE PURPOSE OF THIS PROJECT IS TO LEVEL AND SEAL APPROXIMATELY 9.70 MILES OF COUNTY ROADS 67 & 446 IN FRANKLIN COUNTY. THIS PROJECT CONSISTS OF FOG SEAL, ASPHALFranklin2Emery Sapp & Sons, Inc.$658,674$676,449+3.0%ARDOT
101234THE PURPOSE OF THE IS PROJECT IS TO CONSTRUCT FULL DEPTH SHOULDERS AND STRIPING TO INCLUDE A CENTER TURN LANE ON HIGHWAY 67 IN POCAHONTAS IN RANDOLPH COUNTY. THRandolph4Atlas Asphalt, Inc.$546,313$771,802+41%ARDOT
SA3943THE PURPOSE OF THIS PROJECT IS TO LEVEL AND RESEAL APPROXIMATELY 9.21 MILES OF VARIOUS COUNTY ROADS IN LEE COUNTY. THIS PROJECT CONSISTS OF ACHM SURFACE COURSE,Lee2Salt Creek Paving & Const. Co., Inc.$474,709$508,720+7.0%ARDOT
SA2549THE PURPOSE OF THIS PROJECT IS TO LEVEL AND RESEAL APPROXIMATELY 5.10 MILES OF VARIOUS COUNTY ROADS IN FULTON COUNTY. THIS PROJECT CONSISTS OF AGGREGATE BASE COFulton2Atlas Asphalt, Inc.$417,738$487,564+17%ARDOT
SA4283THE PURPOSE OF THIS PROJECT IS TO LEVEL AND RESEAL APPROXIMATELY 4.94 MILES OF COUNTY ROADS 33 AND 29 IN LOGAN COUNTY. THIS PROJECT CONSISTS OF ASPHALT SURFACE Logan3Salt Creek Paving & Const. Co., Inc.$329,336$330,5320.0%ARDOT
SA6145THE PURPOSE OF THIS PROJECT IS TO OVERLAY APPROXIMATELY 2.40 MILES OF COUNTY ROAD 275 IN RANDOLH COUNTY. THIS PROJECT CONSISTS OF AGGREGATE BASE COURSE, ACHM SURandolph5Atlas Asphalt, Inc.$313,054$351,079+12%ARDOT
SA5259THE PURPOSE OF THIS PROJECT IS TO RESEAL APPROXIMATELY 4.35 MILES OF COUNTY ROADS 2 AND 55 IN OUACHITA COUNTY. THIS PROJECT CONSISTS OF ASPHALT SURFACE TREATMENOuachita1Smackover Paving Co.$221,205ARDOT
SA3858THE PURPOSE OF THIS PROJECT IS TO INSTALL PAVEMENT MARKING ON APPROXIMATELY 15.78 MILES OF VARIOUS COUNTY ROADS IN LAWRENCE COUNTY. THIS PROJECT CONSISTS OF PAVLawrence4Traf-Mark Industries, L.L.C.$20,850$35,129+68%ARDOT
ARDOT contracts let on February 26, 2025, largest low bid first

Gap is the second bid over the low bid. Where a contract shows fewer bids than ARDOT received, the others did not match their published totals and are left out. Each contract number opens its full bid tabulation.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy