ARDOT contract A40041 bid tabulation

THE PURPOSE OF THIS PROJECT IS TO MILL AND OVERLAY APPROXIMATELY 12.468 MILES OF HIGHWAY 62 IN WASHINGTON COUNTY. THIS PROJECT CONSISTS OF REMOVAL AND DISPOSAL ITEM, AGGREGATE BASE COURSE, ACHM SURFACE COURSE, COLD MILLING ASPHALT PAVEMENT, ACHM PATCHING OF EXISTING ROADWAY, APPROACH GUTTERS, MAINTENANCE OF TRAFFIC, GUARDRAIL, MUMBLE STRIPS AND STRIPES, PAVEMENT MARKING, AND MISC. ITEMS. Let by Arkansas DOT on February 26, 2025, Washington. 4 bids received; low bid $4,987,983 by Robinson Construction, LLC.

Owner
Arkansas DOT
Letting
26 FEB 2025
Pay items
22
Data through
04 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Robinson Construction, LLC$4,987,983Low
2Emery Sapp & Sons, Inc.$5,180,369+4.0%
3Grant Garrett Excavating, Inc.$5,465,913+10%
4Apac-Central, Inc.$5,692,828+14%
ARDOT contract A40041: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Robinson Construction, LLC2. Emery Sapp & Sons, Inc.3. Grant Garrett Excavating, Inc.4. Apac-Central, Inc.
0001Removal and disposal of guardrail (202132)LF1,808$4.00$4.57$4.69$18.00
0002Aggregate base course (class 7) (303117)TON1,834$40.00$36.05$37.92$70.00
0003Tack coat (401011)GAL49,580$3.85$3.15$3.00$3.50
0004Mineral aggregate in achm surface course (1/2") (407162)TON30,213$105.45$118.06$115.50$117.00
0005Asphalt binder (PG 70-22) in achm surface course (1/2") (minimum bid $120.00) (407442)TON1,860$120.00$120.00$120.00$120.00
0006Cold milling asphalt pavement (412002)SY254,463$2.50$1.92$3.09$3.10
0007Achm patching of existing roadway (415011)TON500$135.00$156.72$182.07$250.00
0008Approach gutters (504264)CY25.68$385.00$319.79$800.78$2,765.00
0009Maintenance of traffic (603010)LS1$65,000$69,039$93,500$80,000
0010Signs (604003)SF1,364$7.05$6.85$7.04$6.60
0011Construction pavement markings (604041)LF234,579$0.28$0.29$0.29$0.30
0012Guardrail (type A) (617005)LF3,045$31.20$34.26$35.21$32.95
0013Guardrail terminal (type 2) (617312)EACH16$3,100.00$3,312.11$3,404.03$3,185.00
0014Mumble strips in asphalt shoulders (642301)LF76,782$0.43$0.08$0.47$0.25
0015Centerline mumble stripes in asphalt roadways (642402)LF38,780$0.45$0.10$0.47$0.25
0016Thermoplastic pavement marking white (6") (719002)LF137,109$0.71$0.78$0.80$0.70
0017Thermoplastic pavement marking white (12") (719005)LF170$10.70$11.42$11.74$11.00
0018Thermoplastic pavement marking yellow (6") (719102)LF97,470$0.70$0.78$0.80$0.70
0019Thermoplastic pavement marking (words) (719201)EACH4$295.00$325.50$334.53$330.00
0020Raised pavement markers (type II) (721002)EACH894$3.05$3.43$3.52$7.70
0021Reinforcing steel-roadway (grade 60) (804003)LB1,992$3.58$5.88$1.35$3.30
0022Mobilization (unit bid amount may not exceed 5% of subtotal) (601001)LS1$80,000$69,785$44,500$95,000
ARDOT contract A40041: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from ARDOT's tabulation for this contract. ARDOT monthly bid tab PDFs (morning and afternoon sessions), January 2022 to November 2026. Base bids are printed in whole dollars; on A+B and A+C jobs the base bid is kept, and the published rank follows the award amount.

Every contract let that day: ARDOT letting of February 26, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy