ARDOT contract 061708 bid tabulation
THE PURPOSE OF THIS PROJECT IS TO CONSTRUCT A NEW WESTBOUND RAMP AT CONGO ROAD, CONVERSTION OF EXISTING WESTBOUND ENTRANCE AT CONGO ROAD TO EXIT RAMP AND WIDEN EXISTING FRONTAGE ROAD ON INTERSTATE 30 AND HIGHWAY 5 IN SALINE COUNTY. THIS PROJECT CONSISTS OF CLEARING AND GRUBBING, REMOVAL AND DISPOSAL ITEMS, FLOWABLE SELECT MATERIAL, EARTHWORK, AGGREGATE BASE COURSE, PORTLAND CEMENT CONCRETE BASE, ACHM BINDER AND SURFACE COURSES, ULTRATHIN BONDED WEARING COURSE, COLD MILLING ASPHALT PAVEMENT, ACHM PATCHING OF EXISTING ROADWAY, PORTLAND CEMENT CONCRETE PAVEMENT, PORTLAND CEMENT CONCRETE DRIVEWAY, JOINT REHABILITATION, SCARIFYING CONCRETE PAVEMENT, MAINTENANCE OF TRAFFIC, CONCRETE DITCH PAVING, MINOR DRAINAGE, GUARDRAIL, EROSION CONTROL, CONCRETE ISLAND AND WALKS, CONCRETE CURB AND GUTTER, WHEELCHAIR RAMPS, RUMBLE STRIPS, LIGHTING ITEMS, PAVEMENT MARKINGS, SIGN ITEMS, AND MISC. ITEMS. Let by Arkansas DOT on February 26, 2025, Saline. 3 bids received; low bid $23,119,608 by Redstone Construction Group, Inc..
- Owner
- Arkansas DOT
- Letting
- 26 FEB 2025
- Pay items
- 171
- Data through
- 04 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Redstone Construction Group, Inc. | $23,119,608 | Low |
| 2 | Kiewit Infrastructure South Co. | $27,197,307 | +18% |
| 3 | Weaver-Bailey Contrs., Inc. | $28,622,819 | +24% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Redstone Construction Group, Inc. | 2. Kiewit Infrastructure South Co. | 3. Weaver-Bailey Contrs., Inc. |
|---|---|---|---|---|---|---|
| 0001 | Clearing (201011) | STA | 2 | $4,424.08 | $7,500.00 | $8,186.83 |
| 0002 | Grubbing (201111) | STA | 2 | $4,424.08 | $7,500.00 | $6,922.99 |
| 0003 | Removal and disposal of curb and gutter (202003) | LF | 1,036 | $21.13 | $28.00 | $17.89 |
| 0004 | Removal and disposal of fence (202011) | LF | 210 | $17.44 | $18.79 | $16.02 |
| 0005 | Removal and disposal of gates (202017) | EACH | 2 | $1,236.26 | $1,200.00 | $673.73 |
| 0006 | Removal and disposal of barrier wall (202037) | LF | 1,661 | $207.04 | $140.00 | $106.32 |
| 0007 | Removal and disposal of concrete pavement (202042) | SY | 7,593 | $52.31 | $53.00 | $41.92 |
| 0008 | Removal and disposal of concrete islands (202047) | SY | 696 | $33.45 | $50.00 | $40.41 |
| 0009 | Removal and disposal of concrete driveways (202062) | SY | 720 | $48.65 | $40.00 | $58.55 |
| 0010 | Removal and disposal of drop inlets (202093) | EACH | 10 | $1,719.51 | $4,000.00 | $2,453.76 |
| 0011 | Removal and disposal of pipe culverts (202096) | EACH | 18 | $1,587.16 | $474.90 | $4,798.40 |
| 0012 | Removal and disposal of headwalls (202099) | EACH | 2 | $3,263.79 | $4,000.00 | $2,332.12 |
| 0013 | Removal and disposal of concrete riprap (202111) | SY | 62 | $118.55 | $175.00 | $193.10 |
| 0014 | Removal and disposal of concrete ditch paving (202125) | SY | 2,155 | $23.96 | $31.00 | $28.30 |
| 0015 | Removal and disposal of guardrail (202132) | LF | 2,159 | $4.20 | $4.38 | $14.73 |
| 0016 | Removal and disposal of signs (202191) | EACH | 1 | $2,819.26 | $450.00 | $1,469.23 |
| 0017 | Removal and disposal of mailboxes (202200) | EACH | 2 | $251.59 | $600.00 | $1,100.94 |
| 0018 | Removal and disposal of luminaire pole and foundation (202280) | EACH | 12 | $1,609.49 | $5,000.00 | $2,810.57 |
| 0019 | Flowable select material (206021) | CY | 29 | $695.32 | $800.00 | $488.57 |
| 0020 | Unclassified excavation (210213) | CY | 11,102 | $54.19 | $72.00 | $62.55 |
| 0021 | Compacted embankment (210611) | CY | 16,232 | $55.92 | $80.00 | $93.00 |
| 0022 | Soil stabilization (210702) | TON | 100 | $637.48 | $445.00 | $717.61 |
| 0023 | Aggregate base course (class 7) (303117) | TON | 23,121 | $46.70 | $36.15 | $71.14 |
| 0024 | Aggregate in cement stabilized crushed stone base course (308021) | TON | 862 | $143.81 | $120.50 | $32.66 |
| 0025 | Cement in cement stabilized crushed stone base course (308203) | TON | 55 | $143.94 | $307.70 | $301.69 |
| 0026 | Processing cement stabilized crushed stone base course (308204) | SY | 2,621 | $2.75 | $22.00 | $45.99 |
| 0027 | Portland cement concrete base (7" uniform thickness) (309507) | SY | 806 | $158.27 | $171.60 | $222.84 |
| 0028 | Portland cement concrete base (11" uniform thickness) (309511) | SY | 2,350 | $169.32 | $237.34 | $222.76 |
| 0029 | Tack coat (401011) | GAL | 13,647 | $0.01 | $0.01 | $0.01 |
| 0030 | Mineral aggregate in achm binder course (1") (406161) | TON | 3,247 | $130.00 | $200.73 | $201.58 |
| 0031 | Asphalt binder (PG 76-22) in achm binder course (1") (minimum bid $120.00) (406422) | TON | 139 | $600.00 | $131.44 | $132.00 |
| 0032 | Mineral aggregate in achm surface course (3/8") (407161) | TON | 135 | $302.03 | $387.60 | $389.24 |
| 0033 | Mineral aggregate in achm surface course (1/2") (407162) | TON | 14,379 | $184.50 | $191.49 | $192.30 |
| 0034 | Asphalt binder (PG 64-22) in achm surface course (3/8") (minimum bid $120.00) (407431) | TON | 9 | $120.00 | $131.44 | $132.00 |
| 0035 | Asphalt binder (PG 64-22) in achm surface course (1/2") (minimum bid $120.00) (407432) | TON | 7 | $120.00 | $131.44 | $132.00 |
| 0036 | Asphalt binder (PG 76-22) in achm surface course (1/2") (minimum bid $120.00) (407452) | TON | 846 | $120.00 | $131.44 | $132.00 |
| 0037 | Ultrathin bonded wearing course (5/8"-type B) (407905) | TON | 1,870 | $350.00 | $327.14 | $328.53 |
| 0038 | Cold milling asphalt pavement (412002) | SY | 993 | $40.00 | $20.68 | $20.77 |
| 0039 | Asphalt concrete patching for maintenance of traffic (414011) | TON | 92 | $1,250.00 | $750.81 | $963.64 |
| 0040 | Achm patching of existing roadway (415011) | TON | 200 | $550.00 | $383.38 | $822.35 |
| 0041 | Portland cement concrete pavement (9" uniform thickness) (501209) | SY | 5,819 | $120.00 | $167.75 | $178.74 |
| 0042 | Portland cement concrete pavement (14" uniform thickness) (501222) | SY | 2,217 | $165.00 | $200.00 | $272.13 |
| 0043 | Portland cement concrete driveway (505011) | SY | 1,633.33 | $160.00 | $180.00 | $194.31 |
| 0044 | Removal and disposal of concrete pavement for patching (507002) | SY | 721 | $475.00 | $315.91 | $565.61 |
| 0045 | Portland cement concrete pavement patching (14" uniform thickness) (507234) | SY | 721 | $785.00 | $474.49 | $709.99 |
| 0046 | Joint rehabilitation (type A) (509001) | LF | 3,240 | $12.60 | $6.60 | $37.93 |
| 0047 | Scarifying concrete pavement (510012) | SY | 167 | $120.00 | $69.05 | $69.34 |
| 0048 | Mobilization (unit bid amount may not exceed 5% of subtotal) (601001) | LS | 1 | $1,000,500 | $1,291,596 | $1,361,650 |
| 0049 | Furnishing field office (602011) | EACH | 1 | $319,588 | $30,000 | $229,007 |
| 0050 | Maintenance of traffic (603010) | LS | 1 | $1,955,000 | $740,000 | $945,324 |
| 0051 | Signs (604003) | SF | 2,833 | $3.50 | $3.83 | $7.70 |
| 0052 | Construction project information sign update (604010) | EACH | 4 | $80.00 | $87.63 | $55.00 |
| 0053 | Barricades (604013) | LF | 16 | $17.00 | $18.62 | $24.20 |
| 0054 | Traffic drums (604023) | EACH | 611 | $20.00 | $21.91 | $33.00 |
| 0055 | Furnishing and installing precast concrete barrier (604031) | LF | 2,526 | $21.80 | $22.73 | $46.51 |
| 0056 | Relocating precast concrete barrier (max. bid 25% of item number ) (604036) | LF | 4,964 | $5.45 | $5.68 | $9.12 |
| 0057 | Construction pavement markings (604041) | LF | 32,298 | $0.25 | $0.27 | $0.42 |
| 0058 | Removable construction pavement markings (604051) | LF | 21,990 | $1.75 | $1.92 | $1.76 |
| 0059 | Removal of construction pavement markings (604055) | LF | 2,336 | $0.85 | $0.93 | $0.99 |
| 0060 | Removal of permanent pavement markings (604061) | LF | 18,492 | $0.85 | $0.93 | $0.99 |
| 0061 | Advance warning arrow panel (604071) | DAY | 1,650 | $10.00 | $10.95 | $11.00 |
| 0062 | Portable changeable message sign (604078) | WEEK | 312 | $100.00 | $109.54 | $165.00 |
| 0063 | Mobile speed notification system (special) (604160) | EACH | 2 | $4,000.00 | $4,381.48 | $9,350.00 |
| 0064 | Concrete ditch paving (type B) (605012) | SY | 460 | $116.28 | $185.24 | $169.94 |
| 0065 | 18" reinforced concrete pipe culverts (class III) (605601) | LF | 2,324 | $104.67 | $220.00 | $223.48 |
| 0066 | 18" reinforced concrete pipe culverts (class IV) (605603) | LF | 265 | $85.07 | $255.00 | $216.46 |
| 0067 | 24" reinforced concrete pipe culverts (class III) (605606) | LF | 133 | $245.33 | $440.00 | $320.04 |
| 0068 | 30" reinforced concrete pipe culverts (class III) (605611) | LF | 128 | $533.14 | $550.00 | $342.46 |
| 0069 | 36" reinforced concrete pipe culverts (class III) (605616) | LF | 96 | $491.03 | $605.00 | $449.19 |
| 0070 | 42" reinforced concrete pipe culverts (class III) (605621) | LF | 10 | $507.70 | $386.10 | $2,209.67 |
| 0071 | 48" reinforced concrete pipe culverts (class III) (605626) | LF | 40 | $1,596.99 | $636.00 | $2,554.86 |
| 0072 | 18" flared end sections for reinforced concrete pipe culverts (605856) | EACH | 3 | $4,905.50 | $5,000.00 | $3,946.10 |
| 0073 | 24" flared end sections for reinforced concrete pipe culverts (605858) | EACH | 1 | $4,183.28 | $6,000.00 | $3,482.23 |
| 0074 | Selected pipe bedding (606994) | CY | 100 | $121.55 | $62.09 | $101.76 |
| 0075 | Drop inlets (type C) (609013) | EACH | 11 | $16,515 | $20,000 | $15,227 |
| 0076 | Drop inlets (type E) (609015) | EACH | 4 | $10,500 | $16,000 | $9,434.03 |
| 0077 | Drop inlets (type MO) (609134) | EACH | 48 | $9,136.96 | $17,000 | $13,123 |
| 0078 | Drop inlets (type RM) (609136) | EACH | 26 | $8,345.82 | $20,000 | $8,026.80 |
| 0079 | Drop inlets (type ST) (609138) | EACH | 17 | $12,306 | $17,000 | $10,039 |
| 0080 | Drop inlets (type special) (609144) | EACH | 1 | $9,606.06 | $15,000 | $12,619 |
| 0081 | Junction boxes (type E) (609215) | EACH | 7 | $8,192.72 | $15,000 | $7,320.64 |
| 0082 | Drop inlet extensions (4') (609311) | EACH | 44 | $2,131.60 | $3,800.00 | $2,471.15 |
| 0083 | Drop inlet extensions (8') (609312) | EACH | 8 | $3,222.78 | $5,400.00 | $3,891.30 |
| 0084 | Drop inlets adjusted to grade (610002) | EACH | 1 | $6,398.46 | $8,000.00 | $12,764 |
| 0085 | Junction boxes adjusted to grade (610003) | EACH | 1 | $2,436.78 | $9,000.00 | $14,024 |
| 0086 | 4" pipe underdrains (611008) | LF | 500 | $25.39 | $15.04 | $30.61 |
| 0087 | Underdrain outlet protectors (611013) | EACH | 4 | $729.90 | $1,291.83 | $2,479.49 |
| 0088 | Pavement repair over culverts (concrete) (615020) | CY | 59 | $1,200.00 | $2,200.00 | $1,055.54 |
| 0089 | Guardrail (type A) (617005) | LF | 875 | $32.00 | $35.05 | $35.20 |
| 0090 | Terminal anchor posts (type 1) (617105) | EACH | 3 | $2,200.00 | $2,409.81 | $2,365.00 |
| 0091 | Guardrail terminal (type 2) (617312) | EACH | 4 | $2,000.00 | $2,190.74 | $3,300.00 |
| 0092 | Thrie beam guardrail terminal (617332) | EACH | 1 | $2,000.00 | $2,190.74 | $2,970.00 |
| 0093 | Lime (620001) | TON | 10 | $100.00 | $109.54 | $110.00 |
| 0094 | Seeding (620011) | ACRE | 4.87 | $1,400.00 | $1,533.52 | $1,540.00 |
| 0095 | Mulch cover (620022) | ACRE | 9.74 | $1,000.00 | $1,095.37 | $1,100.00 |
| 0096 | Water (620030) | MGAL | 603.30 | $10.00 | $10.00 | $10.00 |
| 0097 | Temporary seeding (621001) | ACRE | 4.87 | $700.00 | $766.76 | $770.00 |
| 0098 | Silt fence (621021) | LF | 1,154 | $3.25 | $3.56 | $3.58 |
| 0099 | Sand bag ditch checks (621031) | BAG | 1,364 | $9.50 | $10.41 | $10.45 |
| 0100 | Drop inlet silt fence (621051) | LF | 100 | $15.00 | $16.43 | $16.50 |
| 0101 | Sediment basin (621071) | CY | 100 | $35.89 | $52.50 | $37.62 |
| 0102 | Obliteration of sediment basin (621101) | CY | 100 | $22.67 | $52.50 | $21.62 |
| 0103 | Sediment removal and disposal (621111) | CY | 270 | $29.97 | $64.60 | $206.78 |
| 0104 | Rock ditch checks (621151) | CY | 735 | $94.14 | $114.90 | $196.99 |
| 0105 | Filter sock (18") (621169) | LF | 2,170 | $12.00 | $13.14 | $13.20 |
| 0106 | Wattle (20") (621173) | LF | 400 | $10.00 | $10.95 | $11.00 |
| 0107 | Second seeding application (623001) | ACRE | 4.87 | $350.00 | $383.38 | $385.00 |
| 0108 | Solid sodding (624001) | SY | 582 | $5.50 | $6.02 | $6.05 |
| 0109 | Erosion control matting (class 3) (626003) | SY | 3,921 | $6.00 | $6.57 | $6.60 |
| 0110 | Concrete barrier wall (median type A) (631036) | LF | 150 | $1,132.94 | $1,200.00 | $1,419.45 |
| 0111 | Concrete barrier wall (median type C) (631040) | LF | 1,015 | $1,132.94 | $1,700.00 | $1,487.03 |
| 0112 | Concrete barrier wall (median type SP-1) (631042) | LF | 75 | $722.64 | $1,100.00 | $1,318.44 |
| 0113 | Concrete barrier wall (side type E) (631177) | LF | 993 | $1,098.18 | $1,650.00 | $1,661.34 |
| 0114 | Concrete island (632011) | SY | 1,475 | $141.25 | $184.00 | $134.44 |
| 0115 | Concrete walks (633011) | SY | 1,690 | $104.64 | $196.00 | $221.08 |
| 0116 | Concrete walks (type special) (633017) | SY | 522 | $905.31 | $1,525.00 | $1,971.05 |
| 0117 | Hand railing (633201) | LF | 1,132 | $128.68 | $160.00 | $101.43 |
| 0118 | Integral curb (type special) (634009) | LF | 2,262 | $28.53 | $13.14 | $23.75 |
| 0119 | Concrete combination curb and gutter (type A) (1' 6") (634201) | LF | 13,656 | $34.00 | $31.00 | $49.79 |
| 0120 | Roadway construction control (635001) | LS | 1 | $347,493 | $500,000 | $479,898 |
| 0121 | Mailboxes (637001) | EACH | 2 | $50.00 | $54.77 | $71.50 |
| 0122 | Mailbox supports (single) (637017) | EACH | 2 | $75.00 | $82.15 | $203.50 |
| 0123 | Modifying drop inlets (640021) | EACH | 3 | $4,323.22 | $10,000 | $5,956.92 |
| 0124 | Modifying junction boxes (640022) | EACH | 1 | $6,398.46 | $8,500.00 | $7,897.79 |
| 0125 | Wheelchair ramps (type 3) (641020) | SY | 110 | $375.00 | $700.00 | $1,024.18 |
| 0126 | Rumble strips in asphalt shoulders (642001) | LF | 17,243 | $0.97 | $0.22 | $0.42 |
| 0127 | Electrical conductors-in-conduit, copper (2C/10 A.W.G., E.G.C.) (708252) | LF | 2,550 | $3.76 | $3.51 | $4.14 |
| 0128 | Electrical conductors-in-conduit, copper (2C/8 A.W.G., E.G.C.) (708398) | LF | 800 | $4.74 | $5.59 | $5.21 |
| 0129 | Electrical conductors for luminaires (708451) | LF | 780 | $1.75 | $3.78 | $1.93 |
| 0130 | Non-metallic conduit (2") (710004) | LF | 3,800 | $17.50 | $39.43 | $19.25 |
| 0131 | Concrete pull box (type 2 HD) (711117) | EACH | 21 | $1,950.00 | $2,393.38 | $2,145.00 |
| 0132 | LED luminaire assembly (714724) | EACH | 4 | $1,000.00 | $1,355.52 | $1,100.00 |
| 0133 | LED roadway illumination pole (12,520 lumens, T-base, 40’, 8’ arm) (714898) | EACH | 3 | $11,773 | $13,350 | $12,950 |
| 0134 | LED roadway illumination pole (12,520 lumens, shoe-base, 40’, 8’ arm) (714899) | EACH | 10 | $11,773 | $10,959 | $12,950 |
| 0135 | Pedestal type service point (100 amp) (715109) | EACH | 1 | $9,850.00 | $17,523 | $10,835 |
| 0136 | Reflectorized paint pavement marking white (10") (718004) | LF | 791 | $2.25 | $2.46 | $2.37 |
| 0137 | Reflectorized paint pavement marking yellow (10") (718104) | LF | 891 | $2.25 | $2.46 | $2.20 |
| 0138 | Thermoplastic pavement marking white (6") (719002) | LF | 3,539 | $0.70 | $0.77 | $1.01 |
| 0139 | Thermoplastic pavement marking white (8") (719003) | LF | 826 | $1.75 | $1.92 | $4.18 |
| 0140 | Thermoplastic pavement marking white (12") (719005) | LF | 480 | $7.00 | $7.67 | $8.25 |
| 0141 | Thermoplastic pavement marking yellow (6") (719102) | LF | 3,137 | $0.70 | $0.77 | $0.99 |
| 0142 | Thermoplastic pavement marking yellow (8") (719103) | LF | 93 | $1.75 | $1.92 | $3.96 |
| 0143 | Thermoplastic pavement marking (words) (719201) | EACH | 4 | $285.00 | $312.18 | $275.00 |
| 0144 | Thermoplastic pavement marking (arrows) (719202) | EACH | 8 | $265.00 | $290.27 | $247.50 |
| 0145 | Enhanced thermoplastic pavement marking white (6") (719502) | LF | 18,406 | $0.85 | $0.93 | $1.08 |
| 0146 | Enhanced thermoplastic pavement marking white (12") (719505) | LF | 2,068 | $6.00 | $6.57 | $9.02 |
| 0147 | Enhanced thermoplastic pavement marking yellow (6") (719602) | LF | 12,836 | $0.85 | $0.93 | $1.06 |
| 0148 | Raised pavement markers (type II) (721002) | EACH | 844 | $3.00 | $3.29 | $6.16 |
| 0149 | Steel overhead sign structure (________________) (724022) | EACH | 1 | $164,100 | $179,750 | $184,120 |
| 0150 | Steel overhead sign structure (________________) (724023) | EACH | 1 | $165,100 | $180,846 | $185,242 |
| 0151 | Steel overhead sign structure (________________) (724024) | EACH | 1 | $166,100 | $181,941 | $186,364 |
| 0152 | Steel bridge mounted sign structure (______________) (724126) | EACH | 1 | $32,000 | $35,052 | $35,904 |
| 0153 | Steel cantilever sign structure (_____________) (724227) | EACH | 1 | $139,000 | $152,256 | $155,958 |
| 0154 | Modification of existing cantilever sign structure (724510) | EACH | 1 | $84,500 | $92,559 | $94,809 |
| 0155 | Guide sign-roadside mounted (demountable legend) (725003) | SF | 833 | $43.20 | $47.32 | $48.47 |
| 0156 | Guide sign-overhead mounted (demountable legend) (725103) | SF | 1,017 | $43.80 | $47.98 | $49.14 |
| 0157 | Standard sign (726002) | SF | 544 | $35.00 | $38.34 | $39.27 |
| 0158 | Exit number panel (type A) (727004) | SF | 95 | $45.50 | $49.84 | $51.05 |
| 0159 | Breakaway sign support (type G-2) (730202) | LB | 5,339 | $12.60 | $13.80 | $14.14 |
| 0160 | Omni-directional breakaway sign supports (type G-1) (730499) | EACH | 40 | $3,150.00 | $3,450.42 | $3,534.30 |
| 0161 | Omni-directional breakaway sign supports (type G2-1) (730502) | EACH | 7 | $3,850.00 | $4,217.17 | $4,319.70 |
| 0162 | Omni-directional breakaway sign supports (type G2-2) (730503) | EACH | 1 | $3,900.00 | $4,271.94 | $4,375.80 |
| 0163 | Omni-directional breakaway sign supports (type G2-4) (730505) | EACH | 1 | $4,000.00 | $4,381.48 | $4,488.00 |
| 0164 | Temporary impact attenuation barrier (731071) | EACH | 2 | $9,670.68 | $2,738.43 | $4,125.00 |
| 0165 | Temporary impact attenuation barrier (repair) (731072) | EACH | 2 | $5,973.12 | $766.76 | $550.00 |
| 0166 | Crash cushion (732011) | EACH | 2 | $23,000 | $25,194 | $31,350 |
| 0167 | 18" reinforced concrete pipe culverts (class III) (605601) | LF | 3,013 | $95.35 | $220.00 | $223.42 |
| 0170 | 24" reinforced concrete pipe culverts (class III) (605606) | LF | 801 | $139.90 | $440.00 | $320.02 |
| 0173 | 30" reinforced concrete pipe culverts (class III) (605611) | LF | 1,111 | $171.14 | $550.00 | $342.44 |
| 0176 | 36" reinforced concrete pipe culverts (class III) (605616) | LF | 294 | $262.35 | $605.00 | $449.38 |
| 0179 | 48" reinforced concrete pipe culverts (class III) (605626) | LF | 8 | $1,561.20 | $636.00 | $2,555.94 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ARDOT's tabulation for this contract. ARDOT monthly bid tab PDFs (morning and afternoon sessions), January 2022 to November 2026. Base bids are printed in whole dollars; on A+B and A+C jobs the base bid is kept, and the published rank follows the award amount.
Every contract let that day: ARDOT letting of February 26, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.