Kiewit Infrastructure South Co.: ARDOT bid record
Kiewit Infrastructure South Co. submitted 13 bids on Arkansas DOT contracts in the data, from 12 JAN 2022 to 17 SEP 2025, and was the low bidder on 5 of them (38%). When it was not low, its total sat a median +17% above the low bid.
- Owner
- Arkansas DOT
- Low bid volume
- $86,145,923
- Latest bid
- 17 SEP 2025
- Data through
- 04 NOV 2026
By year
| Year | Bids | Low bids | Win rate |
|---|---|---|---|
| 2022 | 4 | 1 | 25% |
| 2023 | 3 | 2 | 67% |
| 2024 | 3 | 1 | 33% |
| 2025 | 3 | 1 | 33% |
By county
| County | Bids | Low bids | Win rate |
|---|---|---|---|
| Jefferson | 3 | 0 | 0% |
| Clark | 2 | 1 | 50% |
| Saline | 2 | 1 | 50% |
| Crittenden | 1 | 0 | 0% |
| Pulaski | 1 | 0 | 0% |
| Lonoke | 1 | 1 | 100% |
| Prairie | 1 | 0 | 0% |
| Hot Spring | 1 | 1 | 100% |
| Various | 1 | 1 | 100% |
Pay items where it is most often lowest
| Pay item | Code | Unit | Lines bid | Lowest on the line | Its median price | All bidders' median |
|---|---|---|---|---|---|---|
| Aggregate base course (class 7) | 303117 | TON | 10 | 9 (90%) | $41.80 | $52.19 |
| Furnishing field office | 602011 | EACH | 11 | 8 (73%) | $30,000 | $38,533 |
| Soil stabilization | 210702 | TON | 11 | 8 (73%) | $355.88 | $350.00 |
| Selected pipe bedding | 606994 | CY | 9 | 8 (89%) | $47.71 | $59.75 |
| Thermoplastic pavement marking (arrows) | 719202 | EACH | 10 | 7 (70%) | $268.18 | $290.00 |
| Removal and disposal of pipe culverts | 202096 | EACH | 10 | 6 (60%) | $2,006.19 | $1,100.00 |
| Raised pavement markers (type II) | 721002 | EACH | 11 | 5 (45%) | $6.57 | $6.50 |
| Sediment removal and disposal | 621111 | CY | 11 | 5 (45%) | $32.82 | $18.14 |
| Asphalt concrete patching for maintenance of traffic | 414011 | TON | 10 | 5 (50%) | $329.16 | $262.50 |
| Grubbing | 201111 | STA | 10 | 5 (50%) | $2,250.00 | $1,700.00 |
| 4" pipe underdrains | 611008 | LF | 10 | 5 (50%) | $18.66 | $19.95 |
| Thermoplastic pavement marking white (6") | 719002 | LF | 9 | 5 (56%) | $0.99 | $0.90 |
A line counts when the firm priced it and at least one other bidder did too; the lowest unit price on the line counts whoever won the contract. Token prices and bids over three times the low bid are left out.
Who it meets most
| Firm | Contracts in common | That firm ranked ahead |
|---|---|---|
| Mobley Contractors, Inc. | 6 | 2 of 6 |
| Weaver-Bailey Contrs., Inc. | 4 | 2 of 4 |
| McMillen, Inc. | 3 | 1 of 3 |
| McGeorge Contracting Co., Inc. | 2 | 1 of 2 |
| Capital Paving & Construction, LLC | 2 | 2 of 2 |
| Diamond Surface, Inc. | 1 | 1 of 1 |
| Emery Sapp & Sons, Inc. | 1 | 1 of 1 |
| Webber, LLC | 1 | 1 of 1 |
| Redstone Const. Group, Inc. | 1 | 1 of 1 |
| WL Bass Construction, Inc. | 1 | 1 of 1 |
Latest bids
| Let | Contract | County | Project | Rank | Its bid | Against the low bid |
|---|---|---|---|---|---|---|
| 17 SEP 2025 | 070509 | Clark | THE PURPOSE OF THIS PROJECT IS TO REPLACE ONE STRUCTURE ON HIGHWAY 67 IN CLARK COUNTY. THIS PROJECT CONSISTS OF CLEARING AND GRUBBING, REMOV | 6 of 6 | $26,215,111 | +37% |
| 26 FEB 2025 | 061708 | Saline | THE PURPOSE OF THIS PROJECT IS TO CONSTRUCT A NEW WESTBOUND RAMP AT CONGO ROAD, CONVERSTION OF EXISTING WESTBOUND ENTRANCE AT CONGO ROAD TO | 2 of 3 | $27,197,307 | +18% |
| 15 JAN 2025 | 012494 | Various | THE PURPOSE OF THIS PROJECT IS TO REPAIR SCOUR DAMAGE ON SIX BRIDGES ON VARIOUS ROUTES IN VARIOUS COUNTIES. THIS PROJECT CONSISTS OF UNCLASS | 1 of 3 | $12,116,793 | Low, 2.0% under the second |
| 18 SEP 2024 | 061741 | Hot Spring | THE PURPOSE OF THIS PROJECT IS TO REPLACE ONE BRIDGE ON HIGHWAY 283 OVER INTERSTATE 30 IN HOT SPRING COUNTY. THIS PROJECT CONSISTS OF CLEARI | 1 of 2 | $8,829,982 | Low, 16% under the second |
| 22 MAY 2024 | 020784 | Jefferson | THE PURPOSE OF THIS PROJECT IS TO REPLACE ONE STRUCTURE ON HIGHWAY 88 AND ONE STRUCTURE ON WRAPE ROAD IN JEFFERSON COUNTY. THIS PROJECT CONS | 2 of 3 | $9,906,738 | +12% |
| 10 APR 2024 | 061614 | Prairie | THE PURPOSE OF THIS PROJECT IS TO REPLACE TWO STRUCTURES ON HIGHWAY 86 IN PRAIRIE COUNTY. THIS PROJECT CONSISTS OF CLEARING AND GRUBBING, RE | 3 of 4 | $10,052,441 | +7.0% |
| 01 NOV 2023 | 061508 | Saline | THE PURPOSE OF THIS PROJECT IS TO WIDEN WITH BIKE LANES ON APPROXIMATELY 1.192 MILES OF HIGHWAY 5 IN SALINE COUNTY. THIS PROJECT CONSISTS OF | 1 of 2 | $20,721,856 | Low, -5.0% under the second |
| 20 SEP 2023 | 061613 | Lonoke | THE PURPOSE OF THIS PROJECT IS TO REPLACE TWO STRUCTURES ON HIGHWAYS 13 AND 31 OVER INTERSTATE 40 IN LONOKE COUNTY. THIS PROJECT CONSISTS OF | 1 of 2 | $33,534,358 | Low, -3.0% under the second |
| 16 AUG 2023 | 020626 | Jefferson | THE PURPOSE OF THIS PROJECT IS TO WIDEN APPROXIMATELY 4.759 MILES OF HIGHWAYS 270 AND 365S IN JEFFERSON COUNTY. THIS PROJECT CONSISTS OF CLE | 3 of 3 | $70,583,946 | +56% |
| 09 NOV 2022 | 070513 | Clark | THE PURPOSE OF THIS PROJECT IS TO REPLACE ONE STRUCTURE ON HIGHWAY 51 IN CLARK COUNTY. THIS PROJECT CONSISTS OF CLEARING AND GRUBBING, REMOV | 1 of 2 | $10,942,934 | Low, -10% under the second |
| 21 SEP 2022 | CA0604 | Pulaski | THE PURPOSE OF THIS PROJECT IS TO WIDEN TO SIX LANES, MAKE INTERCHANGE IMPROVEMENTS, AND REPLACE THREE STRUCTURES ON HIGHWAY 67, IN JACKSONV | 3 of 3 | $207,420,952 | +13% |
| 12 JAN 2022 | 110800 | Crittenden | THE PURPOSE OF THIS PROJECT IS TO EXPAND TRUCK PARKING. THIS PROJECT CONSISTS OF CLEARING AND GRUBBING, REMOVAL AND DISPOSAL ITEMS, EARTHWOR | 2 of 2 | $7,094,394 | +16% |
| 12 JAN 2022 | 020702 | Jefferson | THE PURPOSE OF THIS PROJECT IS TO GRIND, PATCH, AND REHABILITATE APPROXIMATELY 9.438 MILES OF HIGHWAYS 63 AND 65B IN JEFFERSON COUNTY. THIS | 3 of 4 | $13,261,633 | +30% |
How this record was read
ARDOT monthly bid tab PDFs (morning and afternoon sessions), January 2022 to November 2026. Base bids are printed in whole dollars; on A+B and A+C jobs the base bid is kept, and the published rank follows the award amount.
- Every bid counted here matched its published total to within one dollar; ARDOT's rank decides who was low.
- The gap to the low bid is the firm's total over the low total, minus one, on contracts it did not win, leaving out bids over three times the low bid.
- A record covers the lettings in the data, not every contract the firm ever bid. Coverage by year is on the state page.
A name split in two, or a figure that does not match the owner's tabulation? Write to mehdi@miragemetrics.com and we correct it.