THE PURPOSE OF THIS PROJECT IS TO REPLACE ONE STRUCTURE ON HIGHWAY 67 IN CLARK COUNTY. THIS PROJECT CONSISTS OF CLEARING AND GRUBBING, REMOVAL AND DISPOSAL ITEMS, EARTHWORK, AGGREGATE BASE COURSE, ACHM BASE, BINDER, AND SURFACE COURSES, COLD MILLING ASPHALT PAVEMENT, ACHM PATCHING OF EXISTING ROADWAY, APPROACH SLABS, PORTLAND CEMENT CONCRETE DRIVEWAY, MAINTENANCE OF TRAFFIC, CONCRETE DITCH PAVING, MINOR DRAINAGE, EROSION CONTROL, CONCRETE ISLAND AND WALKS, HAND RAILING, CONCRETE CURB AND GUTTER, WHEELCHAIR RAMPS, PAVEMENT MARKING, CONSTRUCT ONE COMPOSITE PRESTRESSED CONCRETE GIRDER UNIT (1137.17') AND MISC. ITEMS. Let by Arkansas DOT on September 17, 2025, Clark. 6 bids received; low bid $19,194,938 by Robertson Contractors, Inc..
- Owner
- Arkansas DOT
- Letting
- 17 SEP 2025
- Pay items
- 122
- Data through
- 04 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Robertson Contractors, Inc. | $19,194,938 | Low |
| 2 | Mobley Contractors, Inc. | $19,873,131 | +4.0% |
| 3 | Manhattan Road & Bridge Co. | $21,139,041 | +10% |
| 4 | Capital Paving & Construction, LLC | $22,258,833 | +16% |
| 5 | McMillen, Inc. | $23,587,816 | +23% |
| 6 | Kiewit Infrastructure South Co. | $26,215,111 | +37% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Robertson Contractors, Inc. | 2. Mobley Contractors, Inc. | 3. Manhattan Road & Bridge Co. | 4. Capital Paving & Construction, LLC | 5. McMillen, Inc. | 6. Kiewit Infrastructure South Co. |
|---|---|---|---|---|---|---|---|---|---|
| 0001 | Clearing (201011) | STA | 14 | $2,330.79 | $2,447.33 | $7,500.00 | $11,025 | $9,000.00 | $15,444 |
| 0002 | Grubbing (201111) | STA | 14 | $1,624.49 | $1,705.71 | $7,500.00 | $6,026.33 | $9,000.00 | $2,000.00 |
| 0003 | Removal and disposal of curb (202001) | LF | 109 | $28.25 | $29.66 | $30.00 | $56.34 | $25.00 | $35.86 |
| 0004 | Removal and disposal of curb and gutter (202003) | LF | 40 | $28.25 | $29.66 | $30.00 | $51.18 | $47.00 | $83.95 |
| 0005 | Removal and disposal of fence (202011) | LF | 386 | $4.24 | $4.45 | $4.50 | $7.80 | $6.00 | $12.38 |
| 0006 | Removal and disposal of gates (202017) | EACH | 2 | $353.15 | $370.81 | $366.00 | $804.87 | $750.00 | $1,045.63 |
| 0007 | Removal and disposal of asphalt islands (202048) | SY | 30 | $28.25 | $29.66 | $30.00 | $162.11 | $80.00 | $108.34 |
| 0008 | Removal and disposal of concrete driveways (202062) | SY | 80 | $49.44 | $51.91 | $51.00 | $65.60 | $51.46 | $70.21 |
| 0009 | Removal and disposal of walks (202072) | SY | 32 | $49.44 | $51.91 | $51.00 | $110.22 | $44.00 | $88.50 |
| 0010 | Removal and disposal of junction boxes (202092) | EACH | 1 | $1,412.60 | $1,483.23 | $1,500.00 | $4,094.31 | $3,900.00 | $2,009.51 |
| 0011 | Removal and disposal of pipe culverts (202096) | EACH | 7 | $7,769.30 | $8,157.77 | $5,150.00 | $1,547.40 | $2,175.00 | $1,587.99 |
| 0012 | Removal and disposal of guardrail (202132) | LF | 174 | $7.06 | $7.41 | $11.00 | $13.25 | $16.33 | $13.75 |
| 0013 | Removal and disposal of cattle guard (202190) | EACH | 1 | $353.15 | $370.81 | $367.00 | $1,540.18 | $1,330.00 | $3,806.39 |
| 0014 | Removal and disposal of signs (202191) | EACH | 24 | $500.00 | $525.00 | $520.00 | $256.70 | $350.00 | $235.01 |
| 0015 | Removal and disposal of handrail (202909) | LF | 17 | $28.25 | $29.66 | $30.00 | $103.74 | $155.00 | $116.72 |
| 0016 | Removal of existing bridge structure (site no. 1) (205011) | LS | 1 | $480,000 | $725,040 | $500,000 | $270,565 | $300,000 | $950,000 |
| 0017 | Unclassified excavation (210213) | CY | 2,533 | $16.13 | $16.94 | $17.50 | $36.47 | $35.00 | $49.00 |
| 0018 | Compacted embankment (210611) | CY | 32,661 | $18.91 | $19.86 | $20.00 | $32.86 | $40.00 | $28.63 |
| 0019 | Soil stabilization (210702) | TON | 400 | $200.00 | $367.50 | $325.00 | $525.38 | $355.00 | $385.00 |
| 0020 | Aggregate base course (class 7) (303117) | TON | 1,797 | $43.10 | $45.26 | $48.00 | $74.13 | $75.00 | $55.00 |
| 0021 | Tack coat (401011) | GAL | 2,202 | $4.63 | $4.86 | $4.75 | $6.14 | $4.63 | $5.10 |
| 0022 | Mineral aggregate in achm base course (1 1/2") (405161) | TON | 2,142 | $175.35 | $184.12 | $180.00 | $232.45 | $175.35 | $193.50 |
| 0023 | Asphalt binder (PG 64-22) in achm base course (1 1/2") (minimum bid $120.00) (405402) | TON | 89 | $120.00 | $126.00 | $150.00 | $159.08 | $120.00 | $132.41 |
| 0024 | Mineral aggregate in achm binder course (1") (406161) | TON | 812 | $193.65 | $203.33 | $200.00 | $256.72 | $193.65 | $213.69 |
| 0025 | Asphalt binder (PG 64-22) in achm binder course (1") (minimum bid $120.00) (406402) | TON | 37 | $120.00 | $126.00 | $150.00 | $159.08 | $120.00 | $131.76 |
| 0026 | Mineral aggregate in achm surface course (1/2") (407162) | TON | 2,105 | $194.23 | $203.94 | $200.00 | $257.49 | $194.23 | $222.52 |
| 0027 | Asphalt binder (PG 64-22) in achm surface course (1/2") (minimum bid $120.00) (407432) | TON | 14 | $120.00 | $126.00 | $150.00 | $159.08 | $120.00 | $132.42 |
| 0028 | Asphalt binder (PG 76-22) in achm surface course (1/2") (minimum bid $120.00) (407452) | TON | 118 | $120.00 | $126.00 | $150.00 | $159.08 | $120.00 | $132.42 |
| 0029 | Cold milling asphalt pavement (412002) | SY | 991 | $19.91 | $20.91 | $24.00 | $26.39 | $20.35 | $22.80 |
| 0030 | Asphalt concrete patching for maintenance of traffic (414011) | TON | 13 | $200.00 | $525.00 | $520.00 | $384.27 | $300.00 | $286.41 |
| 0031 | Achm patching of existing roadway (415011) | TON | 10 | $200.00 | $525.00 | $520.00 | $452.63 | $300.00 | $286.41 |
| 0032 | Approach slabs (504031) | CY | 218.16 | $945.00 | $866.88 | $875.00 | $711.08 | $1,800.00 | $962.07 |
| 0033 | Portland cement concrete driveway (505011) | SY | 731.22 | $140.00 | $157.50 | $150.00 | $185.19 | $195.00 | $206.26 |
| 0034 | Mobilization (unit bid amount may not exceed 5% of subtotal) (601001) | LS | 1 | $880,000 | $670,248 | $963,000 | $437,000 | $1,100,000 | $1,239,761 |
| 0035 | Furnishing field office (602011) | EACH | 1 | $25,000 | $69,239 | $89,000 | $182,396 | $25,000 | $30,000 |
| 0036 | Maintenance of traffic (603010) | LS | 1 | $250,000 | $1,043,618 | $87,500 | $752,982 | $200,000 | $351,168 |
| 0037 | 12" temporary culvert (603013) | LF | 26 | $105.22 | $110.48 | $109.00 | $447.39 | $600.00 | $632.34 |
| 0038 | Signs (604003) | SF | 518 | $10.00 | $10.50 | $10.25 | $13.25 | $15.00 | $17.18 |
| 0039 | Construction project information sign update (604010) | EACH | 4 | $75.00 | $78.75 | $78.00 | $99.43 | $100.00 | $114.57 |
| 0040 | Barricades (604013) | LF | 64 | $20.00 | $21.00 | $21.00 | $26.51 | $30.00 | $34.37 |
| 0041 | Traffic drums (604023) | EACH | 88 | $51.00 | $53.55 | $53.00 | $67.61 | $65.00 | $74.47 |
| 0042 | Construction pavement markings (604041) | LF | 19,587 | $0.60 | $0.63 | $0.65 | $0.80 | $1.00 | $0.69 |
| 0043 | Removal of permanent pavement markings (604061) | LF | 4,205 | $0.80 | $0.84 | $0.85 | $1.06 | $1.00 | $1.26 |
| 0044 | Vertical panels (604083) | EACH | 29 | $65.00 | $68.25 | $67.50 | $86.17 | $75.00 | $85.92 |
| 0045 | Concrete ditch paving (type B) (605012) | SY | 37 | $185.00 | $341.25 | $90.00 | $300.14 | $160.00 | $166.17 |
| 0046 | 18" reinforced concrete pipe culverts (class III) (605601) | LF | 418 | $86.18 | $90.49 | $90.00 | $210.96 | $112.00 | $153.57 |
| 0047 | 24" reinforced concrete pipe culverts (class V) (605609) | LF | 56 | $1,150.55 | $1,208.08 | $1,275.00 | $208.78 | $560.00 | $1,910.05 |
| 0048 | 42" reinforced concrete pipe culverts (class III) (605621) | LF | 22 | $222.82 | $233.96 | $235.00 | $540.48 | $345.00 | $269.60 |
| 0049 | 18" flared end sections for reinforced concrete pipe culverts (605856) | EACH | 12 | $2,083.77 | $2,187.96 | $2,200.00 | $2,760.92 | $3,000.00 | $3,411.99 |
| 0050 | 42" flared end sections for reinforced concrete pipe culverts (605864) | EACH | 1 | $6,653.09 | $6,985.74 | $7,500.00 | $7,492.33 | $5,000.00 | $8,696.65 |
| 0051 | Selected pipe bedding (606994) | CY | 210 | $89.38 | $93.85 | $93.00 | $64.69 | $59.00 | $58.00 |
| 0052 | Drop inlets (type C) (609013) | EACH | 21 | $8,700.00 | $9,385.97 | $8,500.00 | $16,571 | $15,000 | $16,554 |
| 0053 | Drop inlets (type MO) (609134) | EACH | 3 | $8,500.00 | $8,842.97 | $8,250.00 | $13,919 | $14,000 | $13,102 |
| 0054 | Junction boxes (type E) (609215) | EACH | 8 | $7,800.00 | $6,061.91 | $6,000.00 | $9,942.47 | $16,000 | $18,919 |
| 0055 | Drop inlet extensions (4') (609311) | EACH | 5 | $2,850.00 | $4,137.44 | $2,300.00 | $3,314.15 | $8,000.00 | $2,721.77 |
| 0056 | 4" pipe underdrains (611008) | LF | 1,000 | $27.58 | $28.96 | $30.00 | $22.80 | $20.00 | $18.48 |
| 0057 | Underdrain outlet protectors (611013) | EACH | 10 | $700.62 | $735.65 | $725.00 | $1,738.67 | $500.00 | $1,310.00 |
| 0058 | Lime (620001) | TON | 17 | $45.00 | $47.25 | $47.00 | $132.56 | $100.00 | $100.00 |
| 0059 | Seeding (620011) | ACRE | 8.36 | $1,237.64 | $1,299.52 | $1,285.00 | $1,789.64 | $1,350.00 | $1,398.00 |
| 0060 | Mulch cover (620022) | ACRE | 16.72 | $897.29 | $942.15 | $930.00 | $1,325.67 | $1,000.00 | $924.00 |
| 0061 | Water (620030) | MGAL | 1,043.80 | $5.00 | $5.25 | $5.25 | $6.63 | $5.00 | $5.08 |
| 0062 | Temporary seeding (621001) | ACRE | 8.36 | $738.64 | $775.57 | $765.00 | $994.25 | $750.00 | $776.00 |
| 0063 | Silt fence (621021) | LF | 5,565 | $3.41 | $3.58 | $3.50 | $4.64 | $3.50 | $3.98 |
| 0064 | Sand bag ditch checks (621031) | BAG | 352 | $10.86 | $11.40 | $11.25 | $13.25 | $10.00 | $14.00 |
| 0065 | Sediment basin (621071) | CY | 200 | $14.13 | $14.84 | $14.75 | $23.64 | $10.00 | $179.00 |
| 0066 | Obliteration of sediment basin (621101) | CY | 200 | $14.13 | $14.84 | $14.75 | $23.64 | $10.00 | $42.42 |
| 0067 | Sediment removal and disposal (621111) | CY | 457 | $19.78 | $20.77 | $20.50 | $25.99 | $20.00 | $38.00 |
| 0068 | Pipe for slope drains (621131) | LF | 40 | $75.60 | $79.38 | $80.00 | $146.08 | $145.00 | $5.73 |
| 0069 | Rock ditch checks (621151) | CY | 78 | $111.99 | $117.59 | $115.00 | $111.64 | $75.00 | $178.16 |
| 0070 | Filter sock (12") (621168) | LF | 704 | $7.83 | $8.22 | $8.25 | $12.59 | $9.50 | $11.92 |
| 0071 | Wattle (20") (621173) | LF | 90 | $11.49 | $12.06 | $12.00 | $19.88 | $15.00 | $16.55 |
| 0072 | Second seeding application (623001) | ACRE | 8.36 | $375.00 | $393.75 | $390.00 | $397.70 | $300.00 | $310.00 |
| 0073 | Solid sodding (624001) | SY | 1,638 | $4.28 | $4.49 | $4.50 | $7.62 | $5.75 | $5.94 |
| 0074 | Erosion control matting (class 3) (626003) | SY | 885 | $5.95 | $6.25 | $6.25 | $7.95 | $6.00 | $6.62 |
| 0075 | Concrete island (632011) | SY | 207 | $140.00 | $210.00 | $165.00 | $198.85 | $180.00 | $186.00 |
| 0076 | Concrete walks (633011) | SY | 3,570 | $105.00 | $105.00 | $120.00 | $149.14 | $126.00 | $181.00 |
| 0077 | Concrete combination curb and gutter (type A) (1' 6") (634201) | LF | 3,652 | $42.00 | $47.25 | $38.00 | $38.45 | $70.00 | $38.00 |
| 0078 | Roadway construction control (635001) | LS | 1 | $75,000 | $77,274 | $75,000 | $157,893 | $100,000 | $105,000 |
| 0079 | Bridge construction control (636001) | LS | 1 | $180,000 | $72,966 | $375,000 | $172,938 | $170,000 | $194,368 |
| 0080 | Mailboxes (637001) | EACH | 4 | $45.00 | $47.25 | $47.50 | $59.65 | $50.00 | $55.00 |
| 0081 | Mailbox supports (single) (637017) | EACH | 4 | $200.00 | $210.00 | $210.00 | $265.14 | $250.00 | $270.00 |
| 0082 | Wheelchair ramps (type 3) (641020) | SY | 36 | $385.00 | $525.00 | $600.00 | $563.41 | $288.00 | $689.72 |
| 0083 | Galvanized steel conduit (1") (709001) | LF | 100 | $112.50 | $47.25 | $120.00 | $149.14 | $10.00 | $71.00 |
| 0084 | Non-metallic conduit (2") (710004) | LF | 2,500 | $15.00 | $52.50 | $17.50 | $19.88 | $8.00 | $5.85 |
| 0085 | Concrete pull box (type 3 HD) (711106) | EACH | 4 | $2,750.00 | $3,675.00 | $3,000.00 | $3,645.57 | $700.00 | $1,065.00 |
| 0086 | Thermoplastic pavement marking white (6") (719002) | LF | 7,957 | $1.00 | $1.05 | $1.05 | $1.33 | $1.50 | $0.97 |
| 0087 | Thermoplastic pavement marking white (12") (719005) | LF | 302 | $10.00 | $10.50 | $10.50 | $13.25 | $15.00 | $11.55 |
| 0088 | Thermoplastic pavement marking yellow (6") (719102) | LF | 9,030 | $1.00 | $1.05 | $1.05 | $1.33 | $1.50 | $0.96 |
| 0089 | Thermoplastic pavement marking yellow (8") (719103) | LF | 362 | $3.00 | $3.15 | $3.15 | $3.98 | $3.00 | $6.10 |
| 0090 | Thermoplastic pavement marking (words) (719201) | EACH | 2 | $300.00 | $315.00 | $315.00 | $397.70 | $500.00 | $350.00 |
| 0091 | Thermoplastic pavement marking (arrows) (719202) | EACH | 4 | $300.00 | $315.00 | $315.00 | $397.70 | $450.00 | $330.00 |
| 0092 | Raised pavement markers (type II) (721002) | EACH | 62 | $10.00 | $10.50 | $10.50 | $13.25 | $20.00 | $8.80 |
| 0093 | Unclassified excavation for structures-bridge (801001) | CY | 48 | $185.00 | $110.08 | $60.00 | $196.23 | $6,500.00 | $688.97 |
| 0094 | Class S concrete-bridge (802112) | CY | 555.60 | $1,580.00 | $1,417.70 | $2,000.00 | $1,986.87 | $1,500.00 | $2,888.32 |
| 0095 | Class S(AE) concrete-bridge (802122) | CY | 2,167.50 | $1,610.00 | $1,328.94 | $1,750.00 | $1,504.62 | $1,750.00 | $2,176.20 |
| 0096 | Architectural finish (802229) | SF | 4,655 | $25.00 | $16.80 | $6.00 | $53.10 | $10.00 | $16.74 |
| 0097 | Prestressed concrete girders (type IV) (802681) | LF | 4,563 | $345.00 | $396.83 | $470.00 | $471.47 | $560.00 | $423.82 |
| 0098 | Textured coating finish (802951) | SY | 2,890 | $32.50 | $17.64 | $15.00 | $46.40 | $20.00 | $49.32 |
| 0099 | Class 2 protective surface treatment (803004) | SY | 6,127.60 | $8.00 | $7.35 | $6.50 | $13.29 | $4.00 | $8.10 |
| 0100 | Reinforcing steel-roadway (grade 60) (804003) | LB | 27,062 | $2.25 | $2.11 | $1.80 | $1.92 | $1.60 | $1.80 |
| 0101 | Reinforcing steel-bridge (grade 60) (804013) | LB | 116,500 | $2.10 | $1.90 | $1.90 | $1.56 | $1.60 | $1.81 |
| 0102 | Epoxy coated reinforcing steel (grade 60) (804023) | LB | 533,350 | $2.15 | $2.08 | $1.95 | $1.73 | $1.80 | $2.05 |
| 0103 | Steel shell piling (18" diameter) (805124) | LF | 855 | $220.00 | $213.26 | $210.00 | $329.89 | $450.00 | $462.93 |
| 0104 | Steel shell piling (24" diameter) (805127) | LF | 3,255 | $330.00 | $275.97 | $280.00 | $347.90 | $550.00 | $517.94 |
| 0105 | Steel shell piling (30" diameter) (805128) | LF | 910 | $525.00 | $566.94 | $485.00 | $559.27 | $750.00 | $662.85 |
| 0106 | Preboring (805504) | LF | 1,526 | $340.00 | $367.76 | $115.00 | $260.46 | $175.00 | $400.93 |
| 0107 | Pile encasement (805513) | LF | 875 | $195.00 | $311.45 | $350.00 | $327.82 | $190.00 | $466.58 |
| 0108 | Metal bridge railing (type H4) (806013) | LF | 1,170 | $365.00 | $261.35 | $325.00 | $256.20 | $333.00 | $388.81 |
| 0109 | Metal bridge railing (type H2) (806021) | LF | 1,129 | $140.00 | $127.31 | $150.00 | $103.53 | $78.00 | $151.71 |
| 0110 | Metal bridge railing (type H3) (806022) | LF | 1,125 | $160.00 | $171.13 | $190.00 | $151.87 | $58.00 | $168.93 |
| 0111 | Transitional approach railing (806217) | EACH | 4 | $7,800.00 | $9,897.88 | $25,000 | $7,524.22 | $10,500 | $12,703 |
| 0112 | Structural steel in plate girder spans (A709, GR. 50W) (807234) | LB | 642,330 | $3.35 | $3.73 | $4.70 | $3.32 | $4.25 | $4.46 |
| 0113 | Painting structural steel (807301) | TON | 58.20 | $650.00 | $1,010.63 | $5,000.00 | $3,963.73 | $3,725.00 | $1,062.95 |
| 0114 | Elastomeric bearings (808002) | CUIN | 67,306 | $4.80 | $5.13 | $1.55 | $5.54 | $4.50 | $4.91 |
| 0115 | Silicone joint sealant (809015) | LF | 260 | $105.00 | $103.71 | $135.00 | $970.78 | $49.00 | $70.43 |
| 0116 | Bridge name plate (type D) (812004) | EACH | 1 | $2,500.00 | $934.35 | $1,250.00 | $4,607.47 | $1,800.00 | $441.74 |
| 0117 | Filter blanket (816003) | SY | 1,311 | $5.39 | $6.60 | $10.00 | $10.59 | $53.00 | $11.52 |
| 0118 | Dumped riprap (816111) | CY | 609 | $112.72 | $138.08 | $155.00 | $239.02 | $175.00 | $162.89 |
| 0119 | 18" reinforced concrete pipe culverts (class III) (605601) | LF | 947 | $83.14 | $90.49 | $86.22 | $247.79 | $145.00 | $153.57 |
| 0122 | 24" reinforced concrete pipe culverts (class III) (605606) | LF | 308 | $107.45 | $112.82 | $115.00 | $267.55 | $160.00 | $169.02 |
| 0125 | 36" reinforced concrete pipe culverts (class III) (605616) | LF | 470 | $173.39 | $182.06 | $180.00 | $344.50 | $240.00 | $319.97 |
| 0128 | 42" reinforced concrete pipe culverts (class III) (605621) | LF | 247 | $236.95 | $233.96 | $250.00 | $406.51 | $265.00 | $268.10 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ARDOT's tabulation for this contract. ARDOT monthly bid tab PDFs (morning and afternoon sessions), January 2022 to November 2026. Base bids are printed in whole dollars; on A+B and A+C jobs the base bid is kept, and the published rank follows the award amount.
Every contract let that day: ARDOT letting of September 17, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.