ARDOT contract 061744 bid tabulation
THE PURPOSE OF THIS PROJECT IS TO REPLACE A STRUCTURE WITH ONE R.C. BOX CULVERT ON HIGHWAY 86 IN PRAIRIE COUNTY. THIS PROJECT CONSISTS OF CLEARING AND GRUBBING, EARTHWORK, AGGREGATE BASE COURSE, ACHM BINDER AND SURFACE COURSES, COLD MILLING ASPHALT PAVEMENT, ACHM PATCHING OF EXISTING ROADWAY, MAINTENANCE OF TRAFFIC, MINOR DRAINAGE, EROSION CONTROL, PAVEMENT MARKING, CONSTRUCT ONE QUINTUPLE BOX CULVERT (63.83 FT) AND MISC. ITEMS. Let by Arkansas DOT on February 26, 2025, Prairie. 3 bids received; low bid $1,527,197 by Mobley Contractors, Inc..
- Owner
- Arkansas DOT
- Letting
- 26 FEB 2025
- Pay items
- 48
- Data through
- 04 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Mobley Contractors, Inc. | $1,527,197 | Low |
| 2 | R.L. Persons Construction, Inc. | $2,389,999 | +56% |
| 3 | 1911 Construction Company, Inc. | $2,670,377 | +75% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Mobley Contractors, Inc. | 2. R.L. Persons Construction, Inc. | 3. 1911 Construction Company, Inc. |
|---|---|---|---|---|---|---|
| 0001 | Clearing (201011) | STA | 3 | $2,966.46 | $4,825.00 | $1,500.00 |
| 0002 | Grubbing (201111) | STA | 3 | $2,966.46 | $3,300.00 | $1,500.00 |
| 0003 | Removal and disposal of pipe culverts (202096) | EACH | 2 | $5,932.92 | $1,720.00 | $1,600.00 |
| 0004 | Removal and disposal of guardrail (202132) | LF | 127 | $5.93 | $65.00 | $15.00 |
| 0005 | Removal of existing bridge structure (site no. 1) (205011) | LS | 1 | $143,681 | $42,500 | $120,000 |
| 0006 | Unclassified excavation (210213) | CY | 4,369 | $22.02 | $50.05 | $25.00 |
| 0007 | Compacted embankment (210611) | CY | 2,009 | $28.38 | $78.50 | $30.00 |
| 0008 | Soil stabilization (210702) | TON | 50 | $70.63 | $725.00 | $350.00 |
| 0009 | Aggregate base course (class 7) (303117) | TON | 1,146 | $62.17 | $82.50 | $75.00 |
| 0010 | Tack coat (401011) | GAL | 415 | $1.05 | $6.00 | $5.00 |
| 0011 | Mineral aggregate in achm binder course (1") (406161) | TON | 99 | $126.00 | $260.00 | $500.00 |
| 0012 | Asphalt binder (PG 64-22) in achm binder course (1") (minimum bid $120.00) (406402) | TON | 4 | $1,260.00 | $175.00 | $500.00 |
| 0013 | Mineral aggregate in achm surface course (1/2") (407162) | TON | 521 | $147.00 | $260.00 | $510.00 |
| 0014 | Asphalt binder (PG 64-22) in achm surface course (1/2") (minimum bid $120.00) (407432) | TON | 27 | $1,260.00 | $175.00 | $510.00 |
| 0015 | Cold milling asphalt pavement (412002) | SY | 556 | $14.70 | $35.00 | $32.50 |
| 0016 | Achm patching of existing roadway (415011) | TON | 5 | $262.50 | $435.00 | $375.00 |
| 0017 | Maintenance of traffic (603010) | LS | 1 | $21,923 | $265,099 | $250,000 |
| 0018 | Signs (604003) | SF | 341 | $10.50 | $14.50 | $13.00 |
| 0019 | Barricades (604013) | LF | 32 | $21.00 | $29.00 | $35.00 |
| 0020 | Traffic drums (604023) | EACH | 12 | $31.50 | $475.00 | $50.00 |
| 0021 | 30" side drain (606705) | LF | 46 | $103.70 | $235.00 | $250.00 |
| 0022 | 42" side drain (606707) | LF | 40 | $115.32 | $300.00 | $275.00 |
| 0023 | Selected pipe bedding (606994) | CY | 10 | $67.01 | $195.00 | $110.00 |
| 0024 | 4" pipe underdrains (611008) | LF | 100 | $41.96 | $52.50 | $20.00 |
| 0025 | Underdrain outlet protectors (611013) | EACH | 2 | $881.99 | $1,170.00 | $500.00 |
| 0026 | Lime (620001) | TON | 4 | $125.00 | $65.00 | $170.00 |
| 0027 | Seeding (620011) | ACRE | 1.95 | $1,500.00 | $1,860.00 | $1,950.00 |
| 0028 | Mulch cover (620022) | ACRE | 4.88 | $1,000.00 | $1,685.00 | $1,300.00 |
| 0029 | Water (620030) | MGAL | 259.20 | $10.00 | $14.50 | $15.00 |
| 0030 | Temporary seeding (621001) | ACRE | 2.93 | $750.00 | $1,285.00 | $975.00 |
| 0031 | Sand bag ditch checks (621031) | BAG | 396 | $10.00 | $15.00 | $13.00 |
| 0032 | Sediment basin (621071) | CY | 100 | $11.30 | $96.50 | $12.00 |
| 0033 | Obliteration of sediment basin (621101) | CY | 100 | $11.30 | $96.50 | $12.00 |
| 0034 | Sediment removal and disposal (621111) | CY | 209 | $25.43 | $135.00 | $12.00 |
| 0035 | Rock ditch checks (621151) | CY | 48 | $129.28 | $140.00 | $120.00 |
| 0036 | Filter sock (18") (621169) | LF | 2,019 | $12.00 | $16.50 | $16.00 |
| 0037 | Second seeding application (623001) | ACRE | 1.95 | $500.00 | $690.00 | $650.00 |
| 0038 | Solid sodding (624001) | SY | 45 | $11.50 | $13.50 | $15.00 |
| 0039 | Roadway construction control (635001) | LS | 1 | $17,694 | $10,500 | $100,000 |
| 0040 | Reflectorized paint pavement marking white (6") (718002) | LF | 1,800 | $1.05 | $1.45 | $3.00 |
| 0041 | Reflectorized paint pavement marking yellow (6") (718102) | LF | 1,800 | $1.05 | $1.45 | $3.00 |
| 0042 | Raised pavement markers (type II) (721002) | EACH | 12 | $105.00 | $145.00 | $130.00 |
| 0043 | Unclassified excavation for structures-roadway (801101) | CY | 158 | $499.64 | $200.00 | $150.00 |
| 0044 | Class S concrete-roadway (802012) | CY | 417.31 | $1,324.76 | $2,260.00 | $2,500.00 |
| 0045 | Reinforcing steel-roadway (grade 60) (804003) | LB | 48,702 | $1.92 | $0.35 | $2.75 |
| 0046 | Filter blanket (816003) | SY | 971 | $7.09 | $7.35 | $25.00 |
| 0047 | Dumped riprap (816111) | CY | 487 | $147.00 | $150.00 | $200.00 |
| 0048 | Mobilization (unit bid amount may not exceed 5% of subtotal) (601001) | LS | 1 | $61,442 | $100,000 | $125,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ARDOT's tabulation for this contract. ARDOT monthly bid tab PDFs (morning and afternoon sessions), January 2022 to November 2026. Base bids are printed in whole dollars; on A+B and A+C jobs the base bid is kept, and the published rank follows the award amount.
Every contract let that day: ARDOT letting of February 26, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.