ARDOT contract SA2549 bid tabulation
THE PURPOSE OF THIS PROJECT IS TO LEVEL AND RESEAL APPROXIMATELY 5.10 MILES OF VARIOUS COUNTY ROADS IN FULTON COUNTY. THIS PROJECT CONSISTS OF AGGREGATE BASE COURSE, FOG SEAL, ACHM SURFACE COURSE, ASPHALT SURFACE TREATMENT, ACHM PATCHING OF EXISTING ROADWAY, MAINTENANCE OF TRAFFIC, PAVEMENT MARKING, AND MISC. ITEMS. Let by Arkansas DOT on February 26, 2025, Fulton. 2 bids received; low bid $417,738 by Atlas Asphalt, Inc..
- Owner
- Arkansas DOT
- Letting
- 26 FEB 2025
- Pay items
- 12
- Data through
- 04 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Atlas Asphalt, Inc. | $417,738 | Low |
| 2 | Apac-Central, Inc. | $487,564 | +17% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Atlas Asphalt, Inc. | 2. Apac-Central, Inc. |
|---|---|---|---|---|---|
| 0001 | Aggregate base course (class 7) (303107) | TON | 71 | $44.22 | $70.00 |
| 0002 | Fog seal (type 2) (401005) | GAL | 6,113 | $4.65 | $5.25 |
| 0003 | Tack coat (401011) | GAL | 1,650 | $3.50 | $3.75 |
| 0004 | Mineral aggregate in asphalt surface treatment (class 2) (402102) | TON | 1,070 | $62.01 | $40.00 |
| 0005 | Polymer modified cationic emulsified asphalt (CRS-2P) (solid polymer) (402204) | GAL | 24,452 | $5.46 | $5.25 |
| 0006 | Mineral aggregate in achm surface course (3/8") (407161) | TON | 1,034 | $108.70 | $165.00 |
| 0007 | Asphalt binder (PG 64-22) in achm surface course (3/8") (minimum bid $120.00) (407431) | TON | 66 | $120.00 | $120.00 |
| 0008 | Achm patching of existing roadway (415011) | TON | 180 | $175.00 | $225.00 |
| 0009 | Maintenance of traffic (603009) | LS | 1 | $6,000.00 | $17,500 |
| 0010 | Signs (604003) | SF | 408 | $5.00 | $11.86 |
| 0011 | Reflectorized paint pavement marking yellow (4") (718101) | LF | 53,856 | $0.12 | $0.20 |
| 0012 | Mobilization (unit bid amount may not exceed 5% of subtotal) (601001) | LS | 1 | $14,221 | $21,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ARDOT's tabulation for this contract. ARDOT monthly bid tab PDFs (morning and afternoon sessions), January 2022 to November 2026. Base bids are printed in whole dollars; on A+B and A+C jobs the base bid is kept, and the published rank follows the award amount.
Every contract let that day: ARDOT letting of February 26, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.