ARDOT contract A10046 bid tabulation
THE PURPOSE OF THIS PROJECT IS TO MILL AND OVERLAY APPROXIMATELY 13.087 MILES OF HIGHWAY 79 IN LEE AND ST. FRANCIS COUNTIES. THIS PROJECT CONSISTS OF REMOVAL AND DISPOSAL ITEMS, TRENCHING AND SHOULDER PREPARATION, AGGREGATE BASE COURSE, ACHM SURFACE COURSE, COLD MILLING ASPHALT PAVEMENT, ACHM PATCHING OF EXISTING ROADWAY, APPROACH GUTTERS, MAINTENANCE OF TRAFFIC, GUARDRAIL, RUMBLE STRIPES, PAVEMENT MARKING, AND MISC. ITEMS. Let by Arkansas DOT on February 26, 2025, Lee, St. Francis. 2 bids received; low bid $4,469,411 by Apac-Tennessee, Inc..
- Owner
- Arkansas DOT
- Letting
- 26 FEB 2025
- Pay items
- 26
- Data through
- 04 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Apac-Tennessee, Inc. | $4,469,411 | Low |
| 2 | Atlas Asphalt, Inc. | $4,651,002 | +4.0% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Apac-Tennessee, Inc. | 2. Atlas Asphalt, Inc. |
|---|---|---|---|---|---|
| 0001 | Removal and disposal of approach gutters (202052) | EACH | 12 | $2,283.75 | $3,707.95 |
| 0002 | Removal and disposal of guardrail (202132) | LF | 1,350 | $9.27 | $12.00 |
| 0003 | Trenching and shoulder preparation (215011) | STA | 11 | $404.00 | $2,885.99 |
| 0004 | Aggregate base course (class 5) (303115) | TON | 4,544 | $60.44 | $70.58 |
| 0005 | Tack coat (401011) | GAL | 47,055 | $0.01 | $0.01 |
| 0006 | Mineral aggregate in achm surface course (1/2") (407162) | TON | 28,836 | $96.36 | $97.57 |
| 0007 | Asphalt binder (PG 64-22) in achm surface course (1/2") (minimum bid $120.00) (407432) | TON | 1,711 | $120.00 | $120.00 |
| 0008 | Cold milling asphalt pavement (412002) | SY | 276,793 | $1.04 | $1.36 |
| 0009 | Achm patching of existing roadway (415011) | TON | 500 | $232.33 | $150.00 |
| 0010 | Approach gutters (504264) | CY | 97.56 | $1,689.98 | $2,403.85 |
| 0011 | Maintenance of traffic (603009) | LS | 1 | $98,000 | $106,177 |
| 0012 | Signs (604003) | SF | 982 | $5.15 | $4.50 |
| 0013 | Traffic drums (604023) | EACH | 16 | $25.75 | $25.00 |
| 0014 | Construction pavement markings (604041) | LF | 180,932 | $0.17 | $0.16 |
| 0015 | Guardrail (type A) (617005) | LF | 825 | $31.93 | $31.00 |
| 0016 | Guardrail terminal (type 2) (617312) | EACH | 10 | $2,987.00 | $3,300.00 |
| 0017 | Thrie beam guardrail terminal (617332) | EACH | 10 | $2,060.00 | $2,300.00 |
| 0018 | Silt fence (621021) | LF | 1,100 | $0.25 | $0.05 |
| 0019 | Rumble stripes in asphalt shoulders (642011) | LF | 141,831 | $0.12 | $0.05 |
| 0020 | Centerline rumble stripes in asphalt roadways (642102) | LF | 70,916 | $0.12 | $0.05 |
| 0021 | Thermoplastic pavement marking white (6") (719002) | LF | 141,821 | $0.64 | $0.63 |
| 0022 | Thermoplastic pavement marking yellow (6") (719102) | LF | 39,112 | $0.64 | $0.63 |
| 0023 | Raised pavement markers (type II) (721002) | EACH | 886 | $4.04 | $4.00 |
| 0024 | Bridge end terminal (734011) | EACH | 2 | $31,280 | $32,000 |
| 0025 | Reinforcing steel-roadway (grade 60) (804003) | LB | 10,536 | $3.35 | $3.00 |
| 0026 | Mobilization (unit bid amount may not exceed 5% of subtotal) (601001) | LS | 1 | $143,000 | $87,216 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ARDOT's tabulation for this contract. ARDOT monthly bid tab PDFs (morning and afternoon sessions), January 2022 to November 2026. Base bids are printed in whole dollars; on A+B and A+C jobs the base bid is kept, and the published rank follows the award amount.
Every contract let that day: ARDOT letting of February 26, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.