ARDOT contract A00085 bid tabulation
THE PURPOSE OF THIS PROJECT IS TO OVERLAY AND PERFORM FULL DEPTH RECLAMATION PROCESSES ON APPROXIMATELY 5.866 MILES OF HIGHWAY 328 IN RANDOLPH COUNTY. THIS PROJECT CONSISTS OF REMOVAL AND DISPOSAL ITEM, AGGREGATE BASE COURSE, FULL DEPTH RECLAMATION OF BASE COURSE, ACHM SURFACE COURSE, COLD MILLING ASPHALT PAVEMENT, ACHM PATCHING OF EXISTING ROADWAY, APPROACH GUTTERS, MAINTENANCE OF TRAFFIC, GUARDRAIL, RUMBLE STRIPES, PAVEMENT MARKING, AND MISC. ITEMS. Let by Arkansas DOT on February 26, 2025, Randolph. 3 bids received; low bid $3,807,984 by Atlas Asphalt, Inc..
- Owner
- Arkansas DOT
- Letting
- 26 FEB 2025
- Pay items
- 26
- Data through
- 04 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Atlas Asphalt, Inc. | $3,807,984 | Low |
| 2 | Delta Asphalt of Arkansas, Inc. | $4,353,357 | +14% |
| 3 | Rogers Group, Inc. | $7,037,439 | +85% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Atlas Asphalt, Inc. | 2. Delta Asphalt of Arkansas, Inc. | 3. Rogers Group, Inc. |
|---|---|---|---|---|---|---|
| 0001 | Removal and disposal of guardrail (202132) | LF | 600 | $21.55 | $21.55 | $22.00 |
| 0002 | Aggregate base course (class 7) (303117) | TON | 1,167 | $26.84 | $25.83 | $65.00 |
| 0003 | Processing full depth reclaimed base course (307213) | SY | 80,738 | $8.48 | $7.39 | $19.00 |
| 0004 | Cement in full depth reclaimed base course (307400) | TON | 3,589 | $233.91 | $257.74 | $340.00 |
| 0005 | Soil aggregate in full depth reclaimed base course (307503) | TON | 292 | $33.39 | $139.87 | $64.00 |
| 0006 | Tack coat (401011) | GAL | 15,711 | $0.01 | $0.01 | $1.00 |
| 0007 | Mineral aggregate in achm surface course (1/2") (407162) | TON | 17,951 | $79.82 | $98.56 | $130.00 |
| 0008 | Asphalt binder (PG 64-22) in achm surface course (1/2") (minimum bid $120.00) (407432) | TON | 1,005 | $120.00 | $120.00 | $700.00 |
| 0009 | Cold milling asphalt pavement (412002) | SY | 7,110 | $2.62 | $6.55 | $5.00 |
| 0010 | Asphalt concrete patching for maintenance of traffic (414011) | TON | 147 | $150.00 | $255.81 | $350.00 |
| 0011 | Achm patching of existing roadway (415011) | TON | 20 | $150.00 | $286.48 | $250.00 |
| 0012 | Approach gutters (504264) | CY | 97.56 | $2,319.05 | $2,319.05 | $2,500.00 |
| 0013 | Maintenance of traffic (603010) | LS | 1 | $56,197 | $135,000 | $230,000 |
| 0014 | Signs (604003) | SF | 808 | $5.00 | $8.00 | $8.50 |
| 0015 | Construction pavement markings (604041) | LF | 123,890 | $0.16 | $0.16 | $0.20 |
| 0016 | Vertical panels (604083) | EACH | 220 | $22.00 | $30.00 | $31.00 |
| 0017 | Guardrail (type A) (617005) | LF | 1,350 | $28.00 | $28.00 | $29.00 |
| 0018 | Guardrail terminal (type 2) (617312) | EACH | 12 | $2,700.00 | $2,700.00 | $2,800.00 |
| 0019 | Thrie beam guardrail terminal (617332) | EACH | 12 | $2,200.00 | $2,200.00 | $2,300.00 |
| 0020 | Rumble stripes in asphalt shoulders (642011) | LF | 30,967 | $0.08 | $0.23 | $0.10 |
| 0021 | Portable traffic signal system - actuated (701603) | WEEK | 30 | $1,708.80 | $895.00 | $900.00 |
| 0022 | Reflectorized paint pavement marking white (6") (718002) | LF | 61,945 | $0.24 | $0.24 | $0.25 |
| 0023 | Reflectorized paint pavement marking yellow (6") (718102) | LF | 61,945 | $0.10 | $0.10 | $0.10 |
| 0024 | Raised pavement markers (type II) (721002) | EACH | 388 | $4.00 | $4.00 | $4.00 |
| 0025 | Reinforcing steel-roadway (grade 60) (804003) | LB | 10,176 | $3.00 | $3.00 | $3.00 |
| 0026 | Mobilization (unit bid amount may not exceed 5% of subtotal) (601001) | LS | 1 | $117,908 | $190,000 | $334,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ARDOT's tabulation for this contract. ARDOT monthly bid tab PDFs (morning and afternoon sessions), January 2022 to November 2026. Base bids are printed in whole dollars; on A+B and A+C jobs the base bid is kept, and the published rank follows the award amount.
Every contract let that day: ARDOT letting of February 26, 2025. Compiled by Mirage Metrics.