Rogers Group, Inc.: ARDOT bid record
Rogers Group, Inc. submitted 156 bids on Arkansas DOT contracts in the data, from 12 JAN 2022 to 04 NOV 2026, and was the low bidder on 51 of them (33%). When it was not low, its total sat a median +14% above the low bid.
- Owner
- Arkansas DOT
- Low bid volume
- $142,746,006
- Latest bid
- 04 NOV 2026
- Data through
- 04 NOV 2026
By year
| Year | Bids | Low bids | Win rate |
|---|---|---|---|
| 2022 | 29 | 14 | 48% |
| 2023 | 17 | 9 | 53% |
| 2024 | 31 | 10 | 32% |
| 2025 | 44 | 12 | 27% |
| 2026 | 35 | 6 | 17% |
By county
| County | Bids | Low bids | Win rate |
|---|---|---|---|
| White | 14 | 2 | 14% |
| Lonoke | 13 | 7 | 54% |
| Faulkner | 12 | 8 | 67% |
| Cleburne | 10 | 3 | 30% |
| Craighead | 10 | 2 | 20% |
| Conway | 9 | 3 | 33% |
| Perry | 8 | 3 | 38% |
| Van Buren | 7 | 4 | 57% |
| Prairie | 6 | 3 | 50% |
| Pulaski | 5 | 1 | 20% |
| Lonoke, Prairie | 4 | 2 | 50% |
| Monroe | 4 | 1 | 25% |
Pay items where it is most often lowest
| Pay item | Code | Unit | Lines bid | Lowest on the line | Its median price | All bidders' median |
|---|---|---|---|---|---|---|
| Tack coat | 401011 | GAL | 114 | 113 (99%) | $1.00 | $3.75 |
| Mineral aggregate in achm surface course (1/2") | 407162 | TON | 84 | 53 (63%) | $65.00 | $124.55 |
| Cold milling asphalt pavement | 412002 | SY | 88 | 44 (50%) | $3.88 | $8.00 |
| Mineral aggregate in achm surface course (3/8") | 407161 | TON | 63 | 41 (65%) | $75.00 | $124.22 |
| Signs | 604003 | SF | 151 | 39 (26%) | $8.00 | $8.40 |
| Construction pavement markings | 604041 | LF | 80 | 30 (38%) | $0.24 | $0.28 |
| Raised pavement markers (type II) | 721002 | EACH | 81 | 23 (28%) | $5.00 | $6.50 |
| Water | 620030 | MGAL | 31 | 23 (74%) | $10.00 | $10.00 |
| Thermoplastic pavement marking yellow (6") | 719102 | LF | 66 | 22 (33%) | $0.75 | $0.85 |
| Achm patching of existing roadway | 415011 | TON | 132 | 21 (16%) | $200.00 | $250.00 |
| Mineral aggregate in achm binder course (1") | 406161 | TON | 36 | 21 (58%) | $73.75 | $135.00 |
| Thermoplastic pavement marking white (6") | 719002 | LF | 66 | 20 (30%) | $0.75 | $0.90 |
A line counts when the firm priced it and at least one other bidder did too; the lowest unit price on the line counts whoever won the contract. Token prices and bids over three times the low bid are left out.
Who it meets most
| Firm | Contracts in common | That firm ranked ahead |
|---|---|---|
| CK Asphalt, LLC | 75 | 46 of 75 |
| Delta Asphalt of Arkansas, Inc. | 51 | 23 of 51 |
| Atlas Asphalt, Inc. | 49 | 42 of 49 |
| Blackstone Construction, LLC | 27 | 15 of 27 |
| Redstone Construction Group, Inc. | 21 | 7 of 21 |
| Delta Asphalt of Ark., Inc. | 16 | 3 of 16 |
| Cranford Construction Co. | 16 | 3 of 16 |
| Richard Baughn Construction, Inc. | 14 | 5 of 14 |
| Sugg Construction, Inc. | 14 | 6 of 14 |
| Apac-Tennessee, Inc. | 11 | 0 of 11 |
Latest bids
| Let | Contract | County | Project | Rank | Its bid | Against the low bid |
|---|---|---|---|---|---|---|
| 04 NOV 2026 | A20044 | Arkansas | THE PURPOSE OF THIS PROJECT IS TO OVERLAY APPROXIMATELY 23.707 MILES OF HIGHWAY 130 IN ARKANSAS COUNTY. THIS PROJECT CONSISTS OF REMOVAL AND | 3 of 4 | $9,665,352 | +11% |
| 04 NOV 2026 | A50033 | White | THE PURPOSE OF THIS PROJECT IS TO MILL AND OVERLAY AND PLACE ULTRATHIN BONDED WEARING COURSE ON APPROXIMATELY 5.952 MILES OF HIGHWAY 367 IN | 2 of 3 | $2,011,636 | +10% |
| 04 NOV 2026 | A80050 | Van Buren | THE PURPOSE OF THIS PROJECT IS TO MILL AND OVERLAY AND PLACE ULTRATHIN BONDED WEARING COURSE ON APPROXIMATELY 13.159 MILES OF HIGHWAY 65 IN | 2 of 3 | $5,169,623 | +5.0% |
| 04 NOV 2026 | A00103 | Craighead | THE PURPOSE OF THIS PROJECT IS TO PLACE ULTRATHIN BONDED WEARING COURSE ON APPROXIMATELY 4.858 MILES OF HIGHWAY 18 IN CRAIGHEAD COUNTY. THIS | 2 of 3 | $1,330,277 | +16% |
| 24 JUN 2026 | 101189 | Craighead | THE PURPOSE OF THIS PROJECT IS TO IMPROVE THE INTERSECTION AT HIGHWAYS 18 AND 139 IN MONETTE IN CRAIGHEAD COUNTY. THIS PROJECT CONSISITS OF | 2 of 2 | $1,792,551 | +2.0% |
| 24 JUN 2026 | SA1260 | Cleburne | THE PURPOSE OF THIS PROJECT IS TO OVERLAY APPROXIMATELY 2.52 MILES OF DRY MOUNTAIN RD. IN CLEBURNE COUNTY. THIS PROJECT CONSISTS OF ACHM SUR | 3 of 4 | $498,688 | +38% |
| 24 JUN 2026 | SA4348 | Lonoke | THE PURPOSE OF THIS PROJECT IS TO OVERLAY APPROXIMATELY 4.86 MILES OF VARIOUS ROADS IN LONOKE COUNTY. THIS PROJECT CONSISTS OF AGGREGATE BAS | 2 of 2 | $999,917 | +31% |
| 24 JUN 2026 | SA5956 | Prairie | THE PURPOSE OF THIS PROJECT IS TO OVERLAY APPROXIMATELY 0.80 MILE OF W. JACKSON ST. IN PRAIRIE COUNTY. THIS PROJECT CONSISTS OF ACHM SURFACE | 4 of 5 | $135,939 | +14% |
| 24 JUN 2026 | SA73A1 | White | THE PURPOSE OF THIS PROJECT IS TO OVERLAY APPROXIMATELY 1.54 MILES OF BLACKJACK MOUNTAIN ROAD AND APPROXIMATELY 1.10 MILES OF OLD RAILROAD R | 3 of 3 | $528,284 | +34% |
| 20 MAY 2026 | A10052 | Lee, Monroe | THE PURPOSE OF THIS PROJECT IS TO OVERLAY APPROXIMATELY 4.776 MILES OF HIGHWAY 79 IN LEE AND MONROE COUNTIES. THIS PROJECT CONSISTS OF AGGRE | 4 of 5 | $1,056,956 | +25% |
| 20 MAY 2026 | A00095 | Craighead | THE PURPOSE OF THIS PROJECT IS TO PLACE ULTRATHIN BONDED WEARING COURSE ON APPROXIMATELY 4.003 MILES OF HIGHWAY 135 IN CRAIGHEAD COUNTY. THI | 3 of 3 | $1,167,569 | +27% |
| 20 MAY 2026 | FA5310 | Perry | THE PURPOSE OF THIS PROJECT IS TO SURFACE APPROXIMATELY 5.28 MILES OF UNION VALLEY RD. IN PERRY COUNTY. THIS PROJECT CONSISTS OF AGGREGATE B | 3 of 3 | $1,910,014 | +7.0% |
| 20 MAY 2026 | SA1670 | Craighead | THE PURPOSE OF THIS PROJECT IS TO OVERLAY APPROXIMATELY 4.54 MILES OF COUNTY ROAD 928 IN CRAIGHEAD COUNTY. THIS PROJECT CONSISTS OF ULTRATHI | 3 of 3 | $401,414 | +19% |
| 20 MAY 2026 | SA3280 | Independence | THE PURPOSE OF THIS PROJECT IS TO OVERLAY APPROXIMATELY 2.94 MILES OF WISH ST. IN INDEPENDENCE COUNTY. THIS PROJECT CONSISTS OF AGGREGATE BA | 3 of 3 | $661,596 | +48% |
| 20 MAY 2026 | SA3859 | Lawrence | THE PURPOSE OF THIS PROJECT IS TO SURFACE APPROXIMATELY 1.00 MILE OF COUNTY ROAD 504 IN LAWRENCE COUNTY. THIS PROJECT CONSISTS OF AGGREGATE | 5 of 5 | $223,554 | +60% |
| 20 MAY 2026 | SA4750 | Mississippi | THE PURPOSE OF THIS PROJECT IS TO OVERLAY APPROXIMATELY 2.99 MILES OF COUNTY ROAD 599 IN MISSISSIPPI COUNTY. THIS PROJECT CONSISTS OF AGGREG | 3 of 3 | $829,929 | +28% |
| 20 MAY 2026 | SA4840 | Monroe | THE PURPOSE OF THIS PROJECT IS TO OVERLAY APPROXIMATELY 3.10 MILES OF BETHLEHEM RD. IN MONROE COUNTY. THIS PROJECT CONSISTS OF AGGREGATE BAS | 3 of 5 | $667,645 | +8.0% |
| 08 APR 2026 | A50046 | Independence | THE PURPOSE OF THIS PROJECT IS TO PLACE ULTRATHIN BONDED WEARING COURSE ON APPROXIMATELY 9.707 MILES OF HIGHWAY 25 IN INDEPENDENCE COUNTY. T | 2 of 2 | $3,588,423 | +28% |
| 04 MAR 2026 | A50045 | White | THE PURPOSE OF THIS PROJECT IS TO OVERLAY APPROXIMATELY 4.191 MILES OF HIGHWAYS 13 AND 267 IN WHITE COUNTY. THIS PROJECT CONSISTS OF REMOVAL | 2 of 4 | $1,714,515 | +1.0% |
| 04 MAR 2026 | A00096 | Craighead, Greene | THE PURPOSE OF THIS PROJECT IS TO OVERLAY APPROXIMATELY 12.283 MILES OF HIGHWAY 141 IN CRAIGHEAD AND GREENE COUNTIES. THIS PROJECT CONSISTS | 4 of 4 | $5,469,057 | +37% |
| 04 MAR 2026 | 012539 | Various | THE PURPOSE OF THIS PROJECT IS TO PLACE ULTRATHIN BONDED WEARING COURSE ON APPROXIMATELY 5.29 MILES ON VARIOUS SECTIONS IN VARIOUS COUNTIES. | 2 of 2 | $1,266,558 | +22% |
| 04 MAR 2026 | AX0009 | Perry, Pulaski | THE PURPOSE OF THIS PROJECT IS TO MILL AND OVERLAY APPROXIMATELY 15.525 MILES OF HIGHWAY 10 IN PERRY AND PULASKI COUNTIES. THIS PROJECT CONS | 1 of 4 | $3,999,231 | Low, 1.0% under the second |
| 21 JAN 2026 | 030656 | Hempstead | THE PURPOSE OF THIS PROJECT IS TO PLACE ULTRATHIN BONDED WEARING COURSE ON APPROXIMATELY 1.94 MILES ON I-30 IN HEMPSTEAD COUNTY. THIS PROJEC | 2 of 2 | $435,309 | +19% |
| 21 JAN 2026 | 061920 | Various | THE PURPOSE OF THIS PROJECT IS TO PLACE ULTRATHIN BONDED WEARING COURSE ON APPROXIMATELY 6.235 MILES ON VARIOUS SECTIONS IN VARIOUS COUNTIES | 2 of 2 | $1,823,147 | +1.0% |
| 21 JAN 2026 | A60057 | Prairie | THE PURPOSE OF THIS PROJECT IS TO OVERLAY APPROXIMATELY 13.441 MILES OF HIGHWAY 63 IN PRAIRIE COUNTY. THIS PROJECT CONSISTS OF AGGREGATE BAS | 1 of 5 | $4,808,215 | Low, 11% under the second |
How this record was read
ARDOT monthly bid tab PDFs (morning and afternoon sessions), January 2022 to November 2026. Base bids are printed in whole dollars; on A+B and A+C jobs the base bid is kept, and the published rank follows the award amount.
- Every bid counted here matched its published total to within one dollar; ARDOT's rank decides who was low.
- The gap to the low bid is the firm's total over the low total, minus one, on contracts it did not win, leaving out bids over three times the low bid.
- A record covers the lettings in the data, not every contract the firm ever bid. Coverage by year is on the state page.
A name split in two, or a figure that does not match the owner's tabulation? Write to mehdi@miragemetrics.com and we correct it.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.