ARDOT contract SA3859 bid tabulation

THE PURPOSE OF THIS PROJECT IS TO SURFACE APPROXIMATELY 1.00 MILE OF COUNTY ROAD 504 IN LAWRENCE COUNTY. THIS PROJECT CONSISTS OF AGGREGATE BASE COURSE, RECONSTRUCTED BASE COURSE, ACHM SURFACE COURSE, MAINTENANCE OF TRAFFIC, AND MISC. ITEMS. Let by Arkansas DOT on May 20, 2026, Lawrence. 5 bids received; low bid $139,834 by Richard Baughn Construction, Inc..

Owner
Arkansas DOT
Letting
20 MAY 2026
Pay items
8
Data through
04 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Richard Baughn Construction, Inc.$139,834Low
2Atlas Asphalt, Inc.$164,047+17%
3Delta Asphalt of Arkansas, Inc.$181,919+30%
4Sugg Construction, Inc.$189,748+36%
5Rogers Group, Inc.$223,554+60%
ARDOT contract SA3859: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Richard Baughn Construction, Inc.2. Atlas Asphalt, Inc.3. Delta Asphalt of Arkansas, Inc.4. Sugg Construction, Inc.5. Rogers Group, Inc.
0001Aggregate base course (class 7) (303117)TON222$36.00$37.66$65.00$40.00$60.00
0002Reconstructed base course (305001)STA48$175.00$198.38$244.00$365.00$400.00
0003Tack coat (401011)GAL109$0.10$3.50$4.15$3.50$1.00
0004Mineral aggregate in achm surface course (1/2") (407162)TON1,239$89.83$101.72$105.00$103.50$85.00
0005Asphalt binder (PG 64-22) in achm surface course (1/2") (minimum bid $120.00) (407432)TON73$120.00$120.00$120.00$120.00$750.00
0006Maintenance of traffic (603009)LS1$1,000.00$3,393.12$7,000.00$15,500$15,000
0007Signs (604003)SF196$7.00$7.50$7.50$7.50$35.00
0008Mobilization (unit bid amount may not exceed 5% of subtotal) (601001)LS1$1,000.00$6,128.53$8,000.00$9,000.00$9,000.00
ARDOT contract SA3859: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from ARDOT's tabulation for this contract. ARDOT monthly bid tab PDFs (morning and afternoon sessions), January 2022 to November 2026. Base bids are printed in whole dollars; on A+B and A+C jobs the base bid is kept, and the published rank follows the award amount.

Every contract let that day: ARDOT letting of May 20, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.