Delta Asphalt of Arkansas, Inc.: ARDOT bid record
Delta Asphalt of Arkansas, Inc. submitted 69 bids on Arkansas DOT contracts in the data, from 06 NOV 2024 to 04 NOV 2026, and was the low bidder on 11 of them (16%). When it was not low, its total sat a median +21% above the low bid.
- Owner
- Arkansas DOT
- Low bid volume
- $33,115,203
- Latest bid
- 04 NOV 2026
- Data through
- 04 NOV 2026
By year
| Year | Bids | Low bids | Win rate |
|---|---|---|---|
| 2024 | 7 | 2 | 29% |
| 2025 | 31 | 0 | 0% |
| 2026 | 31 | 9 | 29% |
By county
| County | Bids | Low bids | Win rate |
|---|---|---|---|
| White | 8 | 1 | 13% |
| Mississippi | 7 | 4 | 57% |
| Craighead | 6 | 0 | 0% |
| Randolph | 5 | 0 | 0% |
| Cleburne | 4 | 0 | 0% |
| Prairie | 4 | 0 | 0% |
| Jackson | 4 | 0 | 0% |
| Lawrence | 4 | 0 | 0% |
| Cross | 3 | 0 | 0% |
| Poinsett | 3 | 0 | 0% |
| Clay | 3 | 3 | 100% |
| Monroe | 2 | 0 | 0% |
Pay items where it is most often lowest
| Pay item | Code | Unit | Lines bid | Lowest on the line | Its median price | All bidders' median |
|---|---|---|---|---|---|---|
| Signs | 604003 | SF | 69 | 46 (67%) | $7.00 | $8.40 |
| Raised pavement markers (type II) | 721002 | EACH | 39 | 26 (67%) | $4.50 | $6.50 |
| Construction pavement markings | 604041 | LF | 38 | 26 (68%) | $0.17 | $0.28 |
| Asphalt binder (PG 64-22) in achm surface course (1/2") (minimum bid $120.00) | 407432 | TON | 35 | 25 (71%) | $120.00 | $120.00 |
| Aggregate base course (class 7) | 303117 | TON | 47 | 19 (40%) | $44.12 | $52.19 |
| Water | 620030 | MGAL | 18 | 18 (100%) | $10.00 | $10.00 |
| Thermoplastic pavement marking white (6") | 719002 | LF | 32 | 17 (53%) | $0.64 | $0.90 |
| Thermoplastic pavement marking yellow (6") | 719102 | LF | 32 | 16 (50%) | $0.63 | $0.85 |
| Asphalt binder (PG 64-22) in achm surface course (3/8") (minimum bid $120.00) | 407431 | TON | 19 | 14 (74%) | $120.00 | $120.00 |
| Guardrail (type A) | 617005 | LF | 19 | 14 (74%) | $30.00 | $32.00 |
| Thermoplastic pavement marking (arrows) | 719202 | EACH | 17 | 14 (82%) | $225.00 | $290.00 |
| Guardrail terminal (type 2) | 617312 | EACH | 18 | 13 (72%) | $3,100.00 | $3,100.00 |
A line counts when the firm priced it and at least one other bidder did too; the lowest unit price on the line counts whoever won the contract. Token prices and bids over three times the low bid are left out.
Who it meets most
| Firm | Contracts in common | That firm ranked ahead |
|---|---|---|
| Rogers Group, Inc. | 51 | 28 of 51 |
| Atlas Asphalt, Inc. | 44 | 39 of 44 |
| CK Asphalt, LLC | 22 | 21 of 22 |
| Sugg Construction, Inc. | 20 | 16 of 20 |
| Richard Baughn Construction, Inc. | 18 | 11 of 18 |
| Redstone Construction Group, Inc. | 11 | 6 of 11 |
| Michelle'S Excavating, Inc. | 10 | 7 of 10 |
| Apac-Tennessee, Inc. | 7 | 1 of 7 |
| Cranford Construction Co. | 6 | 3 of 6 |
| Mobley Contractors, Inc. | 4 | 1 of 4 |
Latest bids
| Let | Contract | County | Project | Rank | Its bid | Against the low bid |
|---|---|---|---|---|---|---|
| 04 NOV 2026 | A50033 | White | THE PURPOSE OF THIS PROJECT IS TO MILL AND OVERLAY AND PLACE ULTRATHIN BONDED WEARING COURSE ON APPROXIMATELY 5.952 MILES OF HIGHWAY 367 IN | 3 of 3 | $2,302,186 | +25% |
| 04 NOV 2026 | 101141 | Mississippi | THE PURPOSE OF THIS PROJECT IS TO IMPROVE THE INTERSECTION ON HIGHWAYS 61 AND 140 IN MISSISSIPPI COUNTY. THIS PROJECT CONSISTS OF REMOVAL AN | 3 of 4 | $3,808,729 | +5.0% |
| 04 NOV 2026 | A00103 | Craighead | THE PURPOSE OF THIS PROJECT IS TO PLACE ULTRATHIN BONDED WEARING COURSE ON APPROXIMATELY 4.858 MILES OF HIGHWAY 18 IN CRAIGHEAD COUNTY. THIS | 3 of 3 | $1,388,633 | +21% |
| 24 JUN 2026 | SA1260 | Cleburne | THE PURPOSE OF THIS PROJECT IS TO OVERLAY APPROXIMATELY 2.52 MILES OF DRY MOUNTAIN RD. IN CLEBURNE COUNTY. THIS PROJECT CONSISTS OF ACHM SUR | 2 of 4 | $413,408 | +14% |
| 24 JUN 2026 | SA3466 | Jackson | THE PURPOSE OF THIS PROJECT IS TO OVERLAY APPROXIMATELY 3.00 MILES OF CO. RD. 37 IN JACKSON COUNTY. THIS PROJECT CONSISTS OF AGGREGATE BASE | 3 of 4 | $425,405 | +8.0% |
| 24 JUN 2026 | SA73A1 | White | THE PURPOSE OF THIS PROJECT IS TO OVERLAY APPROXIMATELY 1.54 MILES OF BLACKJACK MOUNTAIN ROAD AND APPROXIMATELY 1.10 MILES OF OLD RAILROAD R | 2 of 3 | $481,265 | +22% |
| 20 MAY 2026 | A00095 | Craighead | THE PURPOSE OF THIS PROJECT IS TO PLACE ULTRATHIN BONDED WEARING COURSE ON APPROXIMATELY 4.003 MILES OF HIGHWAY 135 IN CRAIGHEAD COUNTY. THI | 2 of 3 | $1,117,659 | +22% |
| 20 MAY 2026 | C73017 | White | THE PURPOSE OF THIS PROJECT IS TO CONSTRUCT 0.331 MILE OF CITY STREET IN WHITE COUNTY. THIS PROJECT CONSISTS OF CLEARING AND GRUBBING, REMOV | 1 of 5 | $670,893 | Low, 2.0% under the second |
| 20 MAY 2026 | SA1670 | Craighead | THE PURPOSE OF THIS PROJECT IS TO OVERLAY APPROXIMATELY 4.54 MILES OF COUNTY ROAD 928 IN CRAIGHEAD COUNTY. THIS PROJECT CONSISTS OF ULTRATHI | 2 of 3 | $379,136 | +13% |
| 20 MAY 2026 | SA3859 | Lawrence | THE PURPOSE OF THIS PROJECT IS TO SURFACE APPROXIMATELY 1.00 MILE OF COUNTY ROAD 504 IN LAWRENCE COUNTY. THIS PROJECT CONSISTS OF AGGREGATE | 3 of 5 | $181,919 | +30% |
| 20 MAY 2026 | SA3860 | Lawrence | THE PURPOSE OF THIS PROJECT IS TO SEAL APPROXIMATELY 0.70 MILE AND SURFACE 0.80 MILE OF COUNTY ROAD 529 IN LAWRENCE COUNTY. THIS PROJECT CON | 3 of 3 | $203,481 | +12% |
| 20 MAY 2026 | SA4749 | Mississippi | THE PURPOSE OF THIS PROJECT IS TO LEVEL AND RESEAL APPROXIMATELY 2.00 MILES OF CO. RD. 474 IN MISSISSIPPI COUNTY. THIS PROJECT CONSISTS OF A | 1 of 2 | $181,452 | Low, 12% under the second |
| 20 MAY 2026 | SA4750 | Mississippi | THE PURPOSE OF THIS PROJECT IS TO OVERLAY APPROXIMATELY 2.99 MILES OF COUNTY ROAD 599 IN MISSISSIPPI COUNTY. THIS PROJECT CONSISTS OF AGGREG | 1 of 3 | $650,512 | Low, 2.0% under the second |
| 08 APR 2026 | 110832 | Cross | THE PURPOSE OF THIS PROJECT IS TO REPAIR A SLIDE ON HIGHWAY 75 IN CROSS COUNTY. THIS PROJECT CONSISITS OF CLEARING AND GRUBBING, EARTHWORK, | 4 of 8 | $3,092,897 | +22% |
| 08 APR 2026 | A00074 | Mississippi | THE PURPOSE OF THIS PROJECT IS TO OVERLAY APPROXIMATELY 4.751 MILES OF HIGHWAY 140 IN MISSISSIPPI COUNTY. THIS PROJECT CONSISTS OF REMOVAL A | 1 of 3 | $4,112,785 | Low, 3.0% under the second |
| 08 APR 2026 | A00093 | Clay | THE PURPOSE OF THIS PROJECT IS TO OVERLAY AND PLACE ULTRATHIN BONDED WEARING COURSE ON APPROXIMATELY 13.921 MILES OF HIGHWAY 62 IN CLAY COUN | 1 of 4 | $4,887,829 | Low, 2.0% under the second |
| 04 MAR 2026 | A50045 | White | THE PURPOSE OF THIS PROJECT IS TO OVERLAY APPROXIMATELY 4.191 MILES OF HIGHWAYS 13 AND 267 IN WHITE COUNTY. THIS PROJECT CONSISTS OF REMOVAL | 3 of 4 | $1,771,245 | +4.0% |
| 04 MAR 2026 | A00096 | Craighead, Greene | THE PURPOSE OF THIS PROJECT IS TO OVERLAY APPROXIMATELY 12.283 MILES OF HIGHWAY 141 IN CRAIGHEAD AND GREENE COUNTIES. THIS PROJECT CONSISTS | 2 of 4 | $4,398,497 | +10% |
| 04 MAR 2026 | A00097 | Clay | THE PURPOSE OF THIS PROJECT IS TO REPLACE CONCRETE PAVEMENT ON APPROXIMATELY 0.500 MILE OF HIGHWAY 67 IN CLAY COUNTY. THIS PROJECT CONSISTS | 1 of 2 | $1,303,576 | Low, 8.0% under the second |
| 21 JAN 2026 | A10051 | Crittenden | THE PURPOSE OF THIS PROJECT IS TO OVERLAY APPROXIMATELY 11.319 MILES OF HIGHWAYS 50 AND 64B IN CRITTENDEN COUNTY. THIS PROJECT CONSISTS OF T | 1 of 3 | $4,066,218 | Low, 22% under the second |
| 21 JAN 2026 | A60057 | Prairie | THE PURPOSE OF THIS PROJECT IS TO OVERLAY APPROXIMATELY 13.441 MILES OF HIGHWAY 63 IN PRAIRIE COUNTY. THIS PROJECT CONSISTS OF AGGREGATE BAS | 4 of 5 | $5,739,844 | +19% |
| 21 JAN 2026 | 100881 | Craighead | THE PURPOSE OF THIS PROJECT IS TO WIDEN HIGHWAY 1B TO FIVE LANES IN CRAIGHEAD COUNTY. THIS PROJECT CONSISTS OF CLEARING AND GRUBBING, REMOVA | 3 of 3 | $6,499,045 | +11% |
| 21 JAN 2026 | A00091 | Poinsett | THE PURPOSE OF THIS PROJECT IS TO MILL AND OVERLAY APPROXIMATELY 3.899 MILES OF HIGHWAY 1 IN POINSETT COUNTY. THIS PROJECT CONSISTS OF ACHM | 2 of 4 | $1,333,011 | +11% |
| 21 JAN 2026 | A00092 | Mississippi | THE PURPOSE OF THIS PROJECT IS TO MILL AND OVERLAY APPROXIMATELY 3.613 MILES OF HIGHWAY 18 IN MISSISSIPPI COUNTY. THIS PROJECT CONSISTS OF A | 1 of 2 | $2,084,107 | Low, 40% under the second |
| 21 JAN 2026 | C19007 | Cross | THE PURPOSE OF THIS PROJECT IS TO OVERLAY AND SURFACE APPROXIMATELY 0.97 MILE OF VARIOUS CITY STREETS IN THE CITY OF CHERRY VALLEY AND 1.63 | 4 of 5 | $531,226 | +17% |
How this record was read
ARDOT monthly bid tab PDFs (morning and afternoon sessions), January 2022 to November 2026. Base bids are printed in whole dollars; on A+B and A+C jobs the base bid is kept, and the published rank follows the award amount.
- Every bid counted here matched its published total to within one dollar; ARDOT's rank decides who was low.
- The gap to the low bid is the firm's total over the low total, minus one, on contracts it did not win, leaving out bids over three times the low bid.
- A record covers the lettings in the data, not every contract the firm ever bid. Coverage by year is on the state page.
A name split in two, or a figure that does not match the owner's tabulation? Write to mehdi@miragemetrics.com and we correct it.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.