ARDOT contract 110832 bid tabulation
THE PURPOSE OF THIS PROJECT IS TO REPAIR A SLIDE ON HIGHWAY 75 IN CROSS COUNTY. THIS PROJECT CONSISITS OF CLEARING AND GRUBBING, EARTHWORK, ROCK FILL, AGGREGATE BASE COURSE, ACHM SURFACE COURSE, COLD MILLING ASPHALT PAVEMENT, ACHM PATCHING OF EXISTING ROADWAY, MAINTENANCE OF TRAFFIC, MINOR DRAINAGE, EROSION CONTROL, GEOTEXTILE FABRIC, PAVEMENT MARKING AND MISC. ITEMS. Let by Arkansas DOT on April 8, 2026, Cross. 8 bids received; low bid $2,537,992 by White River Materials, Inc..
- Owner
- Arkansas DOT
- Letting
- 08 APR 2026
- Pay items
- 38
- Data through
- 04 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | White River Materials, Inc. | $2,537,992 | Low |
| 2 | Mobley Contractors, Inc. | $2,711,148 | +7.0% |
| 3 | James A. Rogers Excavating, Inc. | $2,998,788 | +18% |
| 4 | Delta Asphalt of Arkansas, Inc. | $3,092,897 | +22% |
| 5 | Sugg Construction, Inc. | $3,395,221 | +34% |
| 6 | Weaver-Bailey Contractors, Inc. | $3,517,116 | +39% |
| 7 | Robertson Contractors, Inc. | $3,534,554 | +39% |
| 8 | SN Contractors LLC | $4,735,698 | +87% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. White River Materials, Inc. | 2. Mobley Contractors, Inc. | 3. James A. Rogers Excavating, Inc. | 4. Delta Asphalt of Arkansas, Inc. | 5. Sugg Construction, Inc. | 6. Weaver-Bailey Contractors, Inc. |
|---|---|---|---|---|---|---|---|---|---|
| 0001 | Clearing (201011) | STA | 16 | $1,103.92 | $2,015.04 | $3,266.65 | $4,065.64 | $2,500.00 | $5,773.53 |
| 0002 | Grubbing (201111) | STA | 16 | $826.62 | $1,975.69 | $1,412.60 | $931.68 | $2,500.00 | $1,307.88 |
| 0003 | Unclassified excavation (210213) | CY | 20,960 | $18.97 | $14.16 | $24.36 | $26.34 | $21.00 | $43.02 |
| 0004 | Compacted embankment (210611) | CY | 130 | $49.41 | $44.77 | $43.04 | $49.34 | $100.00 | $39.23 |
| 0005 | Rock fill (210633) | TON | 39,061 | $44.18 | $43.97 | $47.29 | $49.85 | $55.00 | $46.44 |
| 0006 | Aggregate base course (class 7) (303117) | TON | 148 | $63.20 | $94.05 | $68.29 | $48.37 | $94.00 | $90.21 |
| 0007 | Tack coat (401011) | GAL | 1,025 | $7.00 | $7.70 | $4.42 | $4.52 | $5.00 | $5.11 |
| 0008 | Mineral aggregate in achm surface course (1/2") (407162) | TON | 706 | $159.12 | $202.90 | $156.86 | $155.00 | $140.00 | $182.41 |
| 0009 | Asphalt binder (PG 64-22) in achm surface course (1/2") (minimum bid $120.00) (407432) | TON | 44 | $120.00 | $132.00 | $124.71 | $120.00 | $140.00 | $145.03 |
| 0010 | Cold milling asphalt pavement (412002) | SY | 578 | $20.00 | $22.00 | $18.04 | $18.75 | $10.00 | $20.98 |
| 0011 | Asphalt concrete patching for maintenance of traffic (414011) | TON | 8 | $250.00 | $148.50 | $427.69 | $394.40 | $360.00 | $497.36 |
| 0012 | Achm patching of existing roadway (415011) | TON | 20 | $300.00 | $385.00 | $259.52 | $272.11 | $300.00 | $301.79 |
| 0013 | Maintenance of traffic (603009) | LS | 1 | $1,364.12 | $192,187 | $79,816 | $60,000 | $150,000 | $106,397 |
| 0014 | Signs (604003) | SF | 472 | $6.00 | $11.00 | $6.24 | $10.00 | $6.00 | $11.00 |
| 0015 | Traffic drums (604023) | EACH | 64 | $23.00 | $44.00 | $20.79 | $40.00 | $20.00 | $44.00 |
| 0016 | Construction pavement markings (604041) | LF | 1,720 | $0.22 | $0.24 | $1.74 | $0.22 | $1.67 | $0.24 |
| 0017 | Removable construction pavement markings (604051) | LF | 20 | $20.00 | $22.00 | $5.20 | $20.00 | $5.00 | $22.00 |
| 0018 | Removal of construction pavement markings (604055) | LF | 200 | $0.35 | $0.39 | $0.68 | $0.35 | $0.65 | $0.39 |
| 0019 | Removal of permanent pavement markings (604061) | LF | 3,440 | $0.35 | $0.39 | $0.68 | $0.35 | $0.65 | $0.39 |
| 0020 | 24" flared end sections for reinforced concrete pipe culverts (605858) | EACH | 1 | $2,262.22 | $4,356.11 | $3,019.81 | $6,082.26 | $4,750.00 | $3,968.72 |
| 0021 | 24" side drain (606704) | LF | 52 | $62.73 | $108.65 | $76.37 | $132.33 | $190.00 | $86.62 |
| 0022 | Selected pipe bedding (606994) | CY | 20 | $6.61 | $141.67 | $68.76 | $184.91 | $45.00 | $137.33 |
| 0023 | Lime (620001) | TON | 1 | $125.00 | $550.00 | $129.91 | $500.00 | $600.00 | $137.50 |
| 0024 | Seeding (620011) | ACRE | 0.50 | $2,685.30 | $6,600.00 | $2,790.74 | $6,000.00 | $1,500.00 | $2,953.84 |
| 0025 | Mulch cover (620022) | ACRE | 0.50 | $2,685.30 | $5,500.00 | $2,790.74 | $5,000.00 | $2,000.00 | $2,953.84 |
| 0026 | Water (620030) | MGAL | 51.30 | $10.00 | $11.00 | $10.39 | $10.00 | $10.00 | $11.00 |
| 0027 | Silt fence (621021) | LF | 3,349 | $3.38 | $3.85 | $3.51 | $3.50 | $3.00 | $3.72 |
| 0028 | Sand bag ditch checks (621031) | BAG | 198 | $12.86 | $13.75 | $13.37 | $12.50 | $14.00 | $14.15 |
| 0029 | Sediment removal and disposal (621111) | CY | 133 | $4.46 | $48.29 | $14.13 | $28.67 | $20.00 | $28.21 |
| 0030 | Second seeding application (623001) | ACRE | 0.50 | $795.10 | $1,100.00 | $826.31 | $1,000.00 | $500.00 | $874.62 |
| 0031 | Solid sodding (624001) | SY | 25 | $13.84 | $44.00 | $19.55 | $40.00 | $30.00 | $15.22 |
| 0032 | Geotextile fabric (type 5) (625005) | SY | 18,258 | $4.84 | $2.08 | $5.57 | $3.66 | $7.00 | $6.62 |
| 0033 | Roadway construction control (635001) | LS | 1 | $49,422 | $18,780 | $56,504 | $20,000 | $75,000 | $50,688 |
| 0034 | Portable traffic signal system - actuated (701603) | WEEK | 13 | $1,094.42 | $1,320.00 | $1,130.08 | $1,200.00 | $800.00 | $1,320.00 |
| 0035 | Reflectorized paint pavement marking white (6") (718002) | LF | 3,440 | $0.24 | $0.26 | $1.29 | $0.24 | $0.91 | $0.26 |
| 0036 | Reflectorized paint pavement marking yellow (6") (718102) | LF | 3,440 | $0.24 | $0.26 | $1.29 | $0.24 | $0.91 | $0.26 |
| 0037 | Raised pavement markers (type II) (721002) | EACH | 22 | $10.00 | $11.00 | $14.13 | $10.00 | $10.00 | $11.00 |
| 0038 | Mobilization (unit bid amount may not exceed 5% of subtotal) (601001) | LS | 1 | $37,855 | $112,591 | $109,893 | $145,000 | $161,000 | $165,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ARDOT's tabulation for this contract. ARDOT monthly bid tab PDFs (morning and afternoon sessions), January 2022 to November 2026. Base bids are printed in whole dollars; on A+B and A+C jobs the base bid is kept, and the published rank follows the award amount.
Every contract let that day: ARDOT letting of April 8, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.