ARDOT contract 101141 bid tabulation
THE PURPOSE OF THIS PROJECT IS TO IMPROVE THE INTERSECTION ON HIGHWAYS 61 AND 140 IN MISSISSIPPI COUNTY. THIS PROJECT CONSISTS OF REMOVAL AND DISPOSAL ITEMS, STONE BACKFILL, EARTHWORK, AGGREGATE BASE COURSE, ACHM BASE, BINDER, AND SURFACE COURSES, COLD MILLING ASPHALT PAVEMENT, PORTLAND CEMENT CONCRETE DRIVEWAY, MAINTENANCE OF TRAFFIC, CONCRETE DITCH PAVING, MINOR DRAINAGE, EROSION CONTROL, CONCRETE ISLAND, WALKS, AND CURB, WHEELCHAIR RAMPS, TRAFFIC SIGNAL ITEMS, PAVEMENT MARKINGS, AND MISC. ITEMS. Let by Arkansas DOT on November 4, 2026, Mississippi. 4 bids received; low bid $3,643,596 by Bluff City Construction Co., LLC.
- Owner
- Arkansas DOT
- Letting
- 04 NOV 2026
- Pay items
- 130
- Data through
- 04 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Bluff City Construction Co., LLC | $3,643,596 | Low |
| 2 | White River Materials, Inc. | $3,646,951 | 0.0% |
| 3 | Delta Asphalt of Arkansas, Inc. | $3,808,729 | +5.0% |
| 4 | RL Persons Construction, Inc. | $4,192,495 | +15% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Bluff City Construction Co., LLC | 2. White River Materials, Inc. | 3. Delta Asphalt of Arkansas, Inc. | 4. RL Persons Construction, Inc. |
|---|---|---|---|---|---|---|---|
| 0001 | Removal and disposal of curb (202001) | LF | 990 | $19.60 | $10.22 | $10.00 | $24.65 |
| 0002 | Removal and disposal of curb and gutter (202003) | LF | 330 | $37.75 | $23.76 | $15.00 | $24.70 |
| 0003 | Removal and disposal of concrete pavement (202042) | SY | 316 | $26.30 | $48.90 | $15.00 | $47.50 |
| 0004 | Removal and disposal of concrete islands (202047) | SY | 418 | $29.80 | $48.41 | $15.00 | $36.00 |
| 0005 | Removal and disposal of concrete driveways (202062) | SY | 1,846 | $15.00 | $20.85 | $15.00 | $29.50 |
| 0006 | Removal and disposal of walks (202072) | SY | 11 | $125.80 | $101.82 | $15.00 | $175.00 |
| 0007 | Removal and disposal of drop inlets (202093) | EACH | 1 | $1,826.80 | $2,035.31 | $500.00 | $1,800.00 |
| 0008 | Removal and disposal of pipe culverts (202096) | EACH | 11 | $2,013.00 | $2,819.96 | $300.00 | $1,205.00 |
| 0009 | Removal and disposal of headwalls (202099) | EACH | 1 | $1,384.00 | $651.02 | $500.00 | $890.00 |
| 0010 | Stone backfill (207011) | TON | 45 | $121.00 | $83.04 | $83.04 | $125.50 |
| 0011 | Unclassified excavation (210213) | CY | 669 | $43.75 | $84.78 | $20.00 | $39.15 |
| 0012 | Compacted embankment (210611) | CY | 2,646 | $78.25 | $84.64 | $24.00 | $55.50 |
| 0013 | Soil stabilization (210702) | TON | 100 | $208.00 | $214.97 | $700.00 | $665.00 |
| 0014 | Aggregate base course (class 7) (303117) | TON | 201 | $198.90 | $157.43 | $65.00 | $103.65 |
| 0015 | Portland cement concrete base (5" uniform thickness) (309505) | SY | 300 | $112.35 | $141.48 | $180.00 | $135.65 |
| 0016 | Tack coat (401011) | GAL | 1,861 | $1.05 | $5.00 | $4.00 | $6.70 |
| 0017 | Mineral aggregate in achm base course (1 1/2") (405161) | TON | 606 | $131.25 | $163.69 | $245.00 | $218.80 |
| 0018 | Asphalt binder (PG 70-22) in achm base course (1 1/2") (minimum bid $120.00) (405412) | TON | 24 | $892.50 | $120.00 | $120.00 | $160.50 |
| 0019 | Mineral aggregate in achm binder course (1") (406161) | TON | 356 | $132.30 | $164.74 | $310.00 | $220.25 |
| 0020 | Asphalt binder (PG 70-22) in achm binder course (1") (minimum bid $120.00) (406412) | TON | 15 | $945.00 | $120.00 | $120.00 | $160.50 |
| 0021 | Mineral aggregate in achm surface course (1/2") (407162) | TON | 2,997 | $136.50 | $159.96 | $260.00 | $215.00 |
| 0022 | Asphalt binder (PG 76-22) in achm surface course (1/2") (minimum bid $120.00) (407452) | TON | 171 | $997.50 | $120.00 | $120.00 | $160.50 |
| 0023 | Cold milling asphalt pavement (412002) | SY | 4,490 | $6.30 | $7.30 | $11.00 | $10.00 |
| 0024 | Asphalt concrete patching for maintenance of traffic (414011) | TON | 25 | $315.00 | $250.00 | $225.00 | $470.00 |
| 0025 | Portland cement concrete driveway (505011) | SY | 1,088.54 | $130.00 | $116.91 | $210.00 | $120.00 |
| 0026 | Maintenance of traffic (603009) | LS | 1 | $123,030 | $168,822 | $475,000 | $288,164 |
| 0027 | Signs (604003) | SF | 530 | $12.00 | $12.00 | $12.00 | $16.00 |
| 0028 | Barricades (604013) | LF | 36 | $21.00 | $20.00 | $20.00 | $26.50 |
| 0029 | Traffic drums (604023) | EACH | 55 | $42.00 | $40.00 | $40.00 | $83.95 |
| 0030 | Traffic cone (604026) | EACH | 180 | $16.80 | $16.00 | $16.00 | $40.25 |
| 0031 | Furnishing and installing precast concrete barrier (604031) | LF | 133 | $231.00 | $70.00 | $90.00 | $130.00 |
| 0032 | Relocating precast concrete barrier (max. bid 25% of item number ) (604036) | LF | 93 | $28.35 | $17.50 | $22.00 | $32.50 |
| 0033 | Construction pavement markings (604041) | LF | 16,502 | $0.50 | $0.60 | $0.45 | $0.80 |
| 0034 | Construction pavement markings (words) (604045) | EACH | 7 | $225.75 | $80.00 | $215.00 | $106.00 |
| 0035 | Construction pavement markings (arrows) (604046) | EACH | 7 | $210.00 | $40.00 | $200.00 | $52.95 |
| 0036 | Removal of construction pavement markings (604055) | LF | 8,109 | $1.20 | $0.80 | $1.15 | $1.10 |
| 0037 | Removal of construction pavement markings (words) (604056) | EACH | 3 | $157.50 | $80.00 | $150.00 | $106.00 |
| 0038 | Removal of construction pavement markings (arrows) (604057) | EACH | 3 | $126.00 | $40.00 | $120.00 | $52.95 |
| 0039 | Vertical panels (604083) | EACH | 32 | $50.40 | $48.00 | $48.00 | $76.75 |
| 0040 | Concrete ditch paving (type B) (605012) | SY | 16 | $1,854.30 | $144.15 | $300.00 | $830.00 |
| 0041 | 36" X 23" side drain (606737) | LF | 68 | $267.45 | $156.16 | $250.00 | $275.00 |
| 0042 | Selected pipe bedding (606994) | CY | 150 | $62.40 | $1.79 | $30.00 | $155.00 |
| 0043 | Drop inlets (type C) (609013) | EACH | 5 | $11,879 | $14,985 | $10,600 | $11,350 |
| 0044 | Drop inlets (type MO) (609134) | EACH | 10 | $7,412.20 | $9,872.17 | $4,000.00 | $6,210.00 |
| 0045 | Drop inlets (type special) (609144) | EACH | 6 | $8,056.50 | $13,393 | $4,000.00 | $5,150.00 |
| 0046 | 4" pipe underdrains (611008) | LF | 750 | $45.25 | $2.50 | $25.00 | $44.25 |
| 0047 | Underdrain outlet protectors (611013) | EACH | 3 | $605.00 | $250.00 | $700.00 | $1,715.00 |
| 0048 | Lime (620001) | TON | 2 | $262.50 | $125.00 | $125.00 | $165.50 |
| 0049 | Seeding (620011) | ACRE | 0.96 | $2,625.00 | $1,687.29 | $1,687.29 | $2,235.00 |
| 0050 | Mulch cover (620022) | ACRE | 2 | $1,500.00 | $1,687.29 | $1,687.29 | $2,235.00 |
| 0051 | Water (620030) | MGAL | 126.70 | $10.50 | $10.00 | $10.00 | $13.25 |
| 0052 | Temporary seeding (621001) | ACRE | 1.04 | $1,500.00 | $1,337.48 | $1,337.48 | $1,775.00 |
| 0053 | Silt fence (621021) | LF | 2,355 | $3.50 | $3.68 | $3.68 | $4.90 |
| 0054 | Sand bag ditch checks (621031) | BAG | 264 | $12.60 | $11.98 | $11.98 | $16.00 |
| 0055 | Sediment basin (621071) | CY | 100 | $8.95 | $1.48 | $30.00 | $76.00 |
| 0056 | Obliteration of sediment basin (621101) | CY | 100 | $8.95 | $1.15 | $30.00 | $75.25 |
| 0057 | Sediment removal and disposal (621111) | CY | 300 | $1.05 | $1.69 | $50.00 | $48.50 |
| 0058 | Rock ditch checks (621151) | CY | 27 | $115.50 | $174.53 | $125.00 | $168.20 |
| 0059 | Filter sock (12") (621168) | LF | 2,490 | $10.25 | $8.18 | $8.18 | $10.85 |
| 0060 | Second seeding application (623001) | ACRE | 0.96 | $735.00 | $535.00 | $535.00 | $708.25 |
| 0061 | Solid sodding (624001) | SY | 613 | $7.60 | $8.68 | $5.68 | $7.50 |
| 0062 | Concrete island (632011) | SY | 290 | $222.90 | $198.08 | $70.00 | $160.00 |
| 0063 | Concrete walks (633011) | SY | 894 | $113.20 | $87.78 | $70.00 | $90.90 |
| 0064 | Concrete combination curb and gutter (type A) (1' 6") (634201) | LF | 2,408 | $53.35 | $79.00 | $35.00 | $53.00 |
| 0065 | Roadway construction control (635001) | LS | 1 | $103,740 | $173,749 | $250,000 | $29,500 |
| 0066 | Modifying drop inlets (640021) | EACH | 1 | $18,177 | $9,512.70 | $9,000.00 | $2,440.00 |
| 0067 | Wheelchair ramps (type 3) (641020) | SY | 29 | $859.10 | $1,067.84 | $400.00 | $575.00 |
| 0068 | Actuated controller TS2-type 2 (8 phases) (701029) | EACH | 2 | $37,800 | $35,118 | $32,050 | $47,180 |
| 0069 | Traffic signal head, LED, (3 section, 1 way) (706039) | EACH | 18 | $1,207.50 | $1,426.94 | $1,180.00 | $1,920.00 |
| 0070 | Traffic signal head, LED, (4 section, 1 way) (706043) | EACH | 8 | $1,522.50 | $2,092.61 | $2,060.00 | $2,810.00 |
| 0071 | Central control unit (707006) | EACH | 1 | $4,200.00 | $5,047.68 | $4,840.00 | $6,780.00 |
| 0072 | Pole mounted assembly (707007) | EACH | 4 | $1,260.00 | $1,797.12 | $1,520.00 | $2,415.00 |
| 0073 | Countdown pedestrian signal head, LED (707015) | EACH | 4 | $1,260.00 | $1,789.32 | $1,220.00 | $2,410.00 |
| 0074 | Traffic signal cable (5C/12 A.W.G.) (708007) | LF | 921 | $5.25 | $3.75 | $4.50 | $5.05 |
| 0075 | Traffic signal cable (5C/14 A.W.G.) (708008) | LF | 1,701 | $4.20 | $2.75 | $5.00 | $3.70 |
| 0076 | Traffic signal cable (7C/14 A.W.G.) (708012) | LF | 1,840 | $6.30 | $3.00 | $7.00 | $4.00 |
| 0077 | Traffic signal cable (20C/14 A.W.G.) (708038) | LF | 576 | $12.60 | $5.50 | $10.00 | $7.40 |
| 0078 | Electrical conductors-in-conduit (1C/8 A.W.G., E.G.C.) (708207) | LF | 682 | $3.15 | $2.25 | $2.50 | $3.00 |
| 0079 | Electrical conductors-in-conduit (1C/12 A.W.G., E.G.C.) (708211) | LF | 381 | $2.65 | $1.95 | $1.70 | $2.65 |
| 0080 | Electrical conductors-in-conduit (2C/6 A.W.G.) (708217) | LF | 103 | $6.30 | $4.50 | $10.00 | $6.05 |
| 0081 | Electrical conductors for luminaires (708451) | LF | 1,277 | $2.65 | $2.65 | $3.50 | $3.60 |
| 0082 | Galvanized steel conduit (2") (709004) | LF | 64 | $52.50 | $35.00 | $64.50 | $47.00 |
| 0083 | Galvanized steel conduit (3") (709005) | LF | 30 | $68.25 | $45.00 | $97.00 | $60.45 |
| 0084 | Non-metallic conduit (2") (710004) | LF | 66 | $31.50 | $30.23 | $64.00 | $40.65 |
| 0085 | Non-metallic conduit (3") (710005) | LF | 618 | $55.00 | $28.60 | $66.50 | $38.50 |
| 0086 | Concrete pull box (type 2) (711004) | EACH | 4 | $1,260.00 | $1,450.00 | $2,050.00 | $1,950.00 |
| 0087 | Concrete pull box (type 1 HD) (711104) | EACH | 1 | $1,500.00 | $1,450.00 | $1,920.00 | $1,950.00 |
| 0088 | Concrete pull box (type 2 HD) (711105) | EACH | 4 | $1,968.75 | $1,750.00 | $2,170.00 | $2,350.00 |
| 0089 | Span wire assembly (713013) | EACH | 1 | $4,725.00 | $24,940 | $14,000 | $33,500 |
| 0090 | Utility pole used as temporary span wire pole (713023) | EACH | 1 | $4,462.50 | $2,287.50 | $1,500.00 | $3,075.00 |
| 0091 | Traffic signal mast arm and pole with foundation (0') (714003) | EACH | 1 | $23,625 | $23,043 | $21,500 | $31,000 |
| 0092 | Traffic signal mast arm and pole with foundation (40') (714040) | EACH | 1 | $36,225 | $39,956 | $37,500 | $54,000 |
| 0093 | Traffic signal mast arm and pole with foundation (42') (714042) | EACH | 1 | $48,300 | $43,331 | $37,750 | $58,250 |
| 0094 | Traffic signal mast arm and pole with foundation (46') (714046) | EACH | 1 | $48,300 | $44,437 | $42,250 | $59,700 |
| 0095 | Traffic signal mast arm and pole with foundation (66') (714066) | EACH | 1 | $62,423 | $59,912 | $51,270 | $80,500 |
| 0096 | LED luminaire assembly (714724) | EACH | 6 | $1,627.50 | $1,313.03 | $1,450.00 | $1,765.00 |
| 0097 | Traffic signal pedestal pole with foundation (715011) | EACH | 2 | $7,875.00 | $6,652.33 | $5,200.00 | $8,950.00 |
| 0098 | Service point assembly (2 circuits) (715102) | EACH | 1 | $10,500 | $5,012.79 | $4,850.00 | $6,735.00 |
| 0099 | Removal of traffic signal equipment (715704) | LS | 1 | $4,410.00 | $22,872 | $5,000.00 | $30,750 |
| 0100 | Treated wood pole (class 2, 45') (716245) | EACH | 3 | $3,675.00 | $10,421 | $7,150.00 | $14,000 |
| 0101 | Reflectorized paint pavement marking white (10") (718004) | LF | 357 | $2.10 | $2.40 | $2.00 | $3.20 |
| 0102 | Reflectorized paint pavement marking yellow (10") (718104) | LF | 635 | $2.10 | $2.40 | $2.00 | $3.20 |
| 0103 | Thermoplastic pavement marking white (6") (719002) | LF | 3,186 | $1.50 | $1.32 | $1.40 | $1.75 |
| 0104 | Thermoplastic pavement marking white (24") (719006) | LF | 424 | $25.20 | $8.00 | $24.00 | $10.60 |
| 0105 | Thermoplastic pavement marking yellow (6") (719102) | LF | 4,822 | $1.50 | $1.32 | $1.40 | $1.75 |
| 0106 | Thermoplastic pavement marking (words) (719201) | EACH | 4 | $336.00 | $280.00 | $320.00 | $375.00 |
| 0107 | Thermoplastic pavement marking (arrows) (719202) | EACH | 4 | $320.25 | $240.00 | $305.00 | $320.00 |
| 0108 | Raised pavement markers (type II) (721002) | EACH | 49 | $15.75 | $8.00 | $15.00 | $10.60 |
| 0109 | Temporary impact attenuation barrier (731071) | EACH | 1 | $6,300.00 | $5,438.32 | $7,000.00 | $14,000 |
| 0110 | Temporary impact attenuation barrier (repair) (731072) | EACH | 2 | $1,200.00 | $515.23 | $3,100.00 | $1,600.00 |
| 0111 | Temporary impact attenuation barrier (relocation) (731075) | EACH | 1 | $3,360.00 | $4,795.88 | $3,900.00 | $10,200 |
| 0112 | Video detector (IP) (733008) | EACH | 5 | $5,500.00 | $4,810.51 | $4,400.00 | $6,500.00 |
| 0113 | Hybrid video/radar detector (733009) | EACH | 3 | $8,000.00 | $7,922.19 | $7,400.00 | $10,650 |
| 0114 | Video cable (exterior cat 5E) (733035) | LF | 1,793 | $3.15 | $2.25 | $2.00 | $3.00 |
| 0115 | Video monitor (CLR) (733042) | EACH | 2 | $1,312.50 | $1,398.45 | $1,400.00 | $1,900.00 |
| 0116 | Central control unit (8 channel) (733105) | EACH | 2 | $50,925 | $41,489 | $46,250 | $55,750 |
| 0117 | Unclassified excavation for structures-roadway (801101) | CY | 13 | $100.00 | $410.15 | $410.15 | $190.00 |
| 0118 | Class S concrete-roadway (802012) | CY | 20.31 | $3,455.80 | $1,973.98 | $1,973.98 | $3,390.00 |
| 0119 | Reinforcing steel-roadway (grade 60) (804003) | LB | 2,675 | $1.60 | $4.19 | $4.19 | $3.00 |
| 0120 | 18" reinforced concrete pipe culverts (class III) (605601) | LF | 304 | $191.00 | $175.52 | $45.00 | $250.00 |
| 0123 | 24" reinforced concrete pipe culverts (class III) (605606) | LF | 226 | $220.50 | $198.09 | $68.00 | $260.00 |
| 0126 | 48" reinforced concrete pipe culverts (class III) (605626) | LF | 18 | $432.40 | $525.60 | $250.00 | $625.00 |
| 0129 | 36" X 23" reinforced concrete arch pipe culverts (class III) (605760) | LF | 908 | $248.50 | $125.00 | $325.75 | |
| 0131 | 35” X 24” smooth spiral rib polymer precoated metallic coated corrugated steel pipe (605919) | LF | 908 | $209.57 | |||
| 0132 | 18" flared end sections for reinforced concrete pipe culverts (605856) | EACH | 5 | $2,240.20 | $2,409.17 | $1,075.00 | $1,650.00 |
| 0134 | 24" flared end sections for reinforced concrete pipe culverts (605858) | EACH | 2 | $2,391.40 | $2,730.99 | $1,265.00 | $1,825.00 |
| 0136 | 48" flared end sections for reinforced concrete pipe culverts (605866) | EACH | 1 | $6,017.00 | $7,759.80 | $4,050.00 | $4,550.00 |
| 0138 | 36" X 23" flared end sections for reinforced concrete arch pipe culverts (605885) | EACH | 2 | $2,849.40 | $1,825.00 | $2,380.00 | |
| 0139 | 35" X 24" flared end sections for corrugated steel arch pipe culvert (605886) | EACH | 2 | $2,094.64 | |||
| 0140 | Mobilization (unit bid amount may not exceed 5% of subtotal) (601001) | LS | 1 | $170,000 | $166,875 | $95,000 | $199,500 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ARDOT's tabulation for this contract. ARDOT monthly bid tab PDFs (morning and afternoon sessions), January 2022 to November 2026. Base bids are printed in whole dollars; on A+B and A+C jobs the base bid is kept, and the published rank follows the award amount.
Every contract let that day: ARDOT letting of November 4, 2026. Compiled by Mirage Metrics.