ARDOT contract A00093 bid tabulation
THE PURPOSE OF THIS PROJECT IS TO OVERLAY AND PLACE ULTRATHIN BONDED WEARING COURSE ON APPROXIMATELY 13.921 MILES OF HIGHWAY 62 IN CLAY COUNTY. THIS PROJECT CONSISTS OF REMOVAL AND DISPOSAL OF GUARDRAIL, AGGREGATE BASE COURSE, ACHM SURFACE COURSE, ULTRATHIN BONDED WEARING COURSE, COLD MILLING ASPHALT PAVEMENT, ACHM PATCHING OF EXISTING ROADWAY, APPROACH GUTTERS, MAINTENANCE OF TRAFFIC, GUARDRAIL, EROSION CONTROL, RUMBLE STRIPES, PAVEMENT MARKING, AND MISC. ITEMS. Let by Arkansas DOT on April 8, 2026, Clay. 4 bids received; low bid $4,887,829 by Delta Asphalt of Arkansas, Inc..
- Owner
- Arkansas DOT
- Letting
- 08 APR 2026
- Pay items
- 38
- Data through
- 04 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Delta Asphalt of Arkansas, Inc. | $4,887,829 | Low |
| 2 | Atlas Asphalt, Inc. | $4,969,232 | +2.0% |
| 3 | Emery Sapp & Sons, Inc. | $6,623,904 | +36% |
| 4 | Richard Baughn Construction, Inc. | $8,009,240 | +64% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Delta Asphalt of Arkansas, Inc. | 2. Atlas Asphalt, Inc. | 3. Emery Sapp & Sons, Inc. | 4. Richard Baughn Construction, Inc. |
|---|---|---|---|---|---|---|---|
| 0001 | Removal and disposal of guardrail (202132) | LF | 2,785 | $9.00 | $6.50 | $7.20 | $9.45 |
| 0002 | Aggregate base course (class 7) (303117) | TON | 3,968 | $34.38 | $31.50 | $50.20 | $41.12 |
| 0003 | Tack coat (401011) | GAL | 55,158 | $0.01 | $0.01 | $3.55 | $3.05 |
| 0004 | Mineral aggregate in achm surface course (1/2") (407162) | TON | 32,273 | $90.50 | $87.78 | $117.25 | $148.79 |
| 0005 | Asphalt binder (PG 64-22) in achm surface course (1/2") (minimum bid $120.00) (407432) | TON | 1,915 | $120.00 | $120.00 | $120.00 | $120.00 |
| 0006 | Ultrathin bonded wearing course (5/8"-type B) (407905) | TON | 3,839 | $127.79 | $148.08 | $148.00 | $168.00 |
| 0007 | Cold milling asphalt pavement (412002) | SY | 18,911 | $2.05 | $2.77 | $3.90 | $4.94 |
| 0008 | Asphalt concrete patching for maintenance of traffic (414011) | TON | 350 | $122.67 | $100.00 | $175.00 | $225.00 |
| 0009 | Achm patching of existing roadway (415011) | TON | 450 | $132.18 | $100.00 | $150.00 | $225.00 |
| 0010 | Approach gutters (504264) | CY | 77.04 | $2,100.00 | $2,500.00 | $2,330.70 | $2,205.00 |
| 0011 | Maintenance of traffic (603009) | LS | 1 | $114,789 | $199,507 | $395,340 | $457,749 |
| 0012 | Signs (604003) | SF | 1,989 | $7.00 | $5.35 | $5.95 | $5.51 |
| 0013 | Traffic drums (604023) | EACH | 67 | $42.00 | $20.00 | $22.30 | $26.25 |
| 0014 | Construction pavement markings (604041) | LF | 303,000 | $0.15 | $0.14 | $0.16 | $0.16 |
| 0015 | Removable construction pavement markings (604051) | LF | 4,260 | $2.00 | $1.90 | $2.15 | $2.10 |
| 0016 | Guardrail (type A) (617005) | LF | 5,992 | $29.00 | $25.00 | $27.75 | $30.45 |
| 0017 | Guardrail terminal (type 2) (617312) | EACH | 24 | $3,300.00 | $3,000.00 | $3,330.00 | $3,465.00 |
| 0018 | Lime (620001) | TON | 2 | $0.01 | $10.00 | $280.00 | $262.50 |
| 0019 | Seeding (620011) | ACRE | 1.10 | $0.01 | $10.00 | $3,535.00 | $3,344.25 |
| 0020 | Mulch cover (620022) | ACRE | 2.20 | $0.01 | $10.00 | $1,665.00 | $1,575.00 |
| 0021 | Water (620030) | MGAL | 134.60 | $10.00 | $10.00 | $11.15 | $10.50 |
| 0022 | Temporary seeding (621001) | ACRE | 1.10 | $0.01 | $10.00 | $1,665.00 | $1,575.00 |
| 0023 | Silt fence (621021) | LF | 4,800 | $0.01 | $0.10 | $3.90 | $3.68 |
| 0024 | Sediment removal and disposal (621111) | CY | 178 | $18.14 | $1.79 | $20.00 | $14.00 |
| 0025 | Second seeding application (623001) | ACRE | 1.10 | $0.01 | $5.00 | $666.00 | $1,456.35 |
| 0026 | Roadway construction control (635011) | LS | 1 | $8,159.39 | $20,353 | $16,650 | $125,000 |
| 0027 | Rumble stripes in asphalt shoulders (642011) | LF | 105,301 | $0.12 | $0.12 | $0.13 | $0.15 |
| 0028 | Centerline rumble stripes in asphalt roadways (642102) | LF | 64,629 | $0.13 | $0.12 | $0.13 | $0.15 |
| 0029 | Portable traffic signal system - actuated (701603) | WEEK | 36 | $975.00 | $800.00 | $890.00 | $1,500.00 |
| 0030 | Reflectorized paint pavement marking white (6") (718002) | LF | 107,830 | $0.18 | $0.17 | $0.19 | $0.19 |
| 0031 | Reflectorized paint pavement marking yellow (6") (718102) | LF | 107,830 | $0.18 | $0.17 | $0.19 | $0.19 |
| 0032 | Thermoplastic pavement marking white (6") (719002) | LF | 42,430 | $0.64 | $0.56 | $0.62 | $0.67 |
| 0033 | Thermoplastic pavement marking white (12") (719005) | LF | 24 | $25.00 | $15.00 | $16.65 | $26.25 |
| 0034 | Thermoplastic pavement marking yellow (6") (719102) | LF | 42,430 | $0.64 | $0.56 | $0.62 | $0.67 |
| 0035 | Thermoplastic pavement marking (railroad emblems) (719203) | EACH | 2 | $650.00 | $565.00 | $627.08 | $682.50 |
| 0036 | Raised pavement markers (type II) (721002) | EACH | 970 | $4.00 | $4.89 | $5.43 | $4.20 |
| 0037 | Reinforcing steel-roadway (grade 60) (804003) | LB | 5,976 | $2.50 | $2.25 | $2.77 | $2.63 |
| 0038 | Mobilization (unit bid amount may not exceed 5% of subtotal) (601001) | LS | 1 | $160,500 | $209,976 | $310,000 | $381,392 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ARDOT's tabulation for this contract. ARDOT monthly bid tab PDFs (morning and afternoon sessions), January 2022 to November 2026. Base bids are printed in whole dollars; on A+B and A+C jobs the base bid is kept, and the published rank follows the award amount.
Every contract let that day: ARDOT letting of April 8, 2026. Compiled by Mirage Metrics.