ARDOT contract A50045 bid tabulation
THE PURPOSE OF THIS PROJECT IS TO OVERLAY APPROXIMATELY 4.191 MILES OF HIGHWAYS 13 AND 267 IN WHITE COUNTY. THIS PROJECT CONSISTS OF REMOVAL AND DISPOSAL ITEMS, EARTHWORK, TRENCHING AND SHOULDER PREPARATION, AGGREGATE BASE COURSE, ACHM SURFACE COURSE, COLD MILLING ASPHALT PAVEMENT, ACHM PATCHING OF EXISTING ROADWAY, APPROACH SLABS AND GUTTERS, MAINTENANCE OF TRAFFIC, GUARDRAIL, EROSION CONTROL, PAVEMENT MARKING, AND MISC. ITEMS. Let by Arkansas DOT on March 4, 2026, White. 4 bids received; low bid $1,702,033 by CK Asphalt, LLC.
- Owner
- Arkansas DOT
- Letting
- 04 MAR 2026
- Pay items
- 32
- Data through
- 04 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | CK Asphalt, LLC | $1,702,033 | Low |
| 2 | Rogers Group, Inc. | $1,714,515 | +1.0% |
| 3 | Delta Asphalt of Arkansas, Inc. | $1,771,245 | +4.0% |
| 4 | Redstone Construction Group, Inc. | $1,989,382 | +17% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. CK Asphalt, LLC | 2. Rogers Group, Inc. | 3. Delta Asphalt of Arkansas, Inc. | 4. Redstone Construction Group, Inc. |
|---|---|---|---|---|---|---|---|
| 0001 | Removal and disposal of approach gutters (202052) | EACH | 8 | $1,500.00 | $2,000.00 | $861.59 | $1,850.00 |
| 0002 | Removal and disposal of guardrail (202132) | LF | 1,100 | $6.00 | $8.15 | $8.00 | $7.30 |
| 0003 | Flowable select material (206021) | CY | 20 | $450.00 | $570.00 | $262.70 | $550.00 |
| 0004 | Stone backfill (207011) | TON | 250 | $65.00 | $83.00 | $56.89 | $80.00 |
| 0005 | Trenching and shoulder preparation (215011) | STA | 223 | $75.00 | $69.00 | $38.70 | $89.58 |
| 0006 | Aggregate base course (class 7) (303117) | TON | 879 | $49.00 | $38.00 | $31.79 | $42.39 |
| 0007 | Tack coat (401011) | GAL | 12,457 | $1.00 | $1.00 | $4.05 | $0.01 |
| 0008 | Mineral aggregate in achm surface course (1/2") (407162) | TON | 10,954 | $82.67 | $57.00 | $90.30 | $110.75 |
| 0009 | Asphalt binder (PG 64-22) in achm surface course (1/2") (minimum bid $120.00) (407432) | TON | 761 | $120.00 | $445.00 | $120.00 | $120.00 |
| 0010 | Cold milling asphalt pavement (412002) | SY | 3,044 | $6.50 | $3.00 | $5.15 | $7.35 |
| 0011 | Achm patching of existing roadway (415011) | TON | 500 | $135.00 | $150.00 | $116.49 | $188.94 |
| 0012 | Approach slabs (504031) | CY | 143.76 | $1,200.00 | $1,010.00 | $975.00 | $975.00 |
| 0013 | Approach gutters (504264) | CY | 38.96 | $1,650.00 | $2,375.00 | $2,300.00 | $2,300.00 |
| 0014 | Maintenance of traffic (603009) | LS | 1 | $32,000 | $43,000 | $39,000 | $37,501 |
| 0015 | Signs (604003) | SF | 619 | $5.50 | $6.00 | $6.00 | $5.50 |
| 0016 | Traffic drums (604023) | EACH | 36 | $25.00 | $28.00 | $28.00 | $25.00 |
| 0017 | Construction pavement markings (604041) | LF | 124,084 | $0.15 | $0.15 | $0.14 | $0.14 |
| 0018 | Removal of permanent pavement markings (604061) | LF | 1,840 | $0.90 | $0.60 | $0.60 | $0.60 |
| 0019 | Guardrail (type A) (617005) | LF | 700 | $28.00 | $36.00 | $35.00 | $28.00 |
| 0020 | Guardrail terminal (type 2) (617312) | EACH | 8 | $3,000.00 | $3,425.00 | $3,200.00 | $3,000.00 |
| 0021 | Thrie beam guardrail terminal (617332) | EACH | 8 | $2,000.00 | $2,460.00 | $2,300.00 | $2,000.00 |
| 0022 | Silt fence (621021) | LF | 500 | $5.00 | $5.45 | $5.00 | $5.00 |
| 0023 | Roadway construction control (635011) | LS | 1 | $18,000 | $20,000 | $18,000 | $6,449.59 |
| 0024 | Mailboxes (637001) | EACH | 20 | $40.00 | $41.00 | $40.00 | $40.00 |
| 0025 | Mailbox supports (single) (637017) | EACH | 14 | $150.00 | $200.00 | $200.00 | $150.00 |
| 0026 | Mailbox supports (double) (637018) | EACH | 3 | $200.00 | $225.00 | $225.00 | $200.00 |
| 0027 | Portable traffic signal system - actuated (701603) | WEEK | 12 | $850.00 | $875.00 | $875.00 | $850.00 |
| 0028 | Thermoplastic pavement marking white (6") (719002) | LF | 45,156 | $0.63 | $0.63 | $0.58 | $0.58 |
| 0029 | Thermoplastic pavement marking yellow (6") (719102) | LF | 16,886 | $0.63 | $0.63 | $0.58 | $0.58 |
| 0030 | Raised pavement markers (type II) (721002) | EACH | 283 | $3.75 | $4.25 | $4.00 | $4.00 |
| 0031 | Reinforcing steel-roadway (grade 60) (804003) | LB | 4,720 | $2.00 | $2.70 | $2.50 | $2.50 |
| 0032 | Mobilization (unit bid amount may not exceed 5% of subtotal) (601001) | LS | 1 | $65,000 | $81,000 | $50,000 | $35,650 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ARDOT's tabulation for this contract. ARDOT monthly bid tab PDFs (morning and afternoon sessions), January 2022 to November 2026. Base bids are printed in whole dollars; on A+B and A+C jobs the base bid is kept, and the published rank follows the award amount.
Every contract let that day: ARDOT letting of March 4, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.