ARDOT letting results, January 21, 2026
53 contracts let by Arkansas DOT on January 21, 2026, $150,200,330 in low bids, a median of 3 bidders per contract.
- Owner
- Arkansas DOT
- Contracts
- 53
- Low bids, total
- $150,200,330
- Data through
- 04 NOV 2026
Contracts let that day
| Contract | Project | County | Bids | Low bidder | Low bid | Second bid | Gap | Source |
|---|---|---|---|---|---|---|---|---|
| 061371 | THE PURPOSE OF THIS PROJECT IS TO RECONFIGURE THE HIGHWAY 5 INTERCHANGE AND REPLACE ONE STRUCTURE OVER I-57 IN LONOKE COUNTY. THIS PROJECT CONSISTS OF CLEARING | Lonoke | 4 | Weaver-Bailey Contractors, Inc. | $53,972,317 | $55,391,633 | +3.0% | ARDOT |
| AX0008 | THE PURPOSE OF THIS PROJECT IS TO MILL, OVERLAY, AND DIAMOND GRIND ENTRANCE AND EXIT RAMPS ALONG I-57 IN JACKSON, LONOKE, AND WHITE COUNTIES. THIS PROJECT CONSI | Jackson, Lonoke, White | 3 | Rogers Group, Inc. | $13,857,556 | $14,516,781 | +5.0% | ARDOT |
| A90043 | THE PURPOSE OF THIS PROJECT IS TO OVERLAY APPROXIMATELY 20.315 MILES OF HIGHWAY 412 IN CARROLL AND MADISON COUNTIES. THIS PROJECT CONSISTS OF AGGREGATE BASE COU | Carroll, Madison | 2 | Atlas Asphalt, Inc. | $7,322,883 | $8,213,795 | +12% | ARDOT |
| A70035 | THE PURPOSE OF THIS PROJECT IS TO OVERLAY APPROXIMATELY 18.322 MILES OF HIGHWAY 8 IN DALLAS COUNTY. THIS PROJECT CONSISTS OF REMOVAL AND DISPOSAL OF GUARDRAIL, | Dallas | 2 | Jet Asphalt & Rock Co., Inc. | $6,396,427 | $6,542,424 | +2.0% | ARDOT |
| 100881 | THE PURPOSE OF THIS PROJECT IS TO WIDEN HIGHWAY 1B TO FIVE LANES IN CRAIGHEAD COUNTY. THIS PROJECT CONSISTS OF CLEARING AND GRUBBING, REMOVAL AND DISPOSAL ITEMS | Craighead | 3 | Rogers Group, Inc. | $5,870,408 | $6,095,468 | +4.0% | ARDOT |
| A20038 | THE PURPOSE OF THIS PROJECT IS TO MILL AND OVERLAY APPROXIMATELY 8.277 MILES OF HIGHWAY 167 IN GRANT COUNTY. THIS PROJECT CONSISTS OF AGGREGATE BASE COURSE, ACH | Grant | 2 | Cranford Construction Co. | $5,267,592 | $6,456,216 | +23% | ARDOT |
| A60057 | THE PURPOSE OF THIS PROJECT IS TO OVERLAY APPROXIMATELY 13.441 MILES OF HIGHWAY 63 IN PRAIRIE COUNTY. THIS PROJECT CONSISTS OF AGGREGATE BASE COURSE, ACHM SURFA | Prairie | 5 | Rogers Group, Inc. | $4,808,215 | $5,333,864 | +11% | ARDOT |
| A40047 | THE PURPOSE OF THIS PROJECT IS TO MILL, OVERLAY, AND SCRUB SEAL APPROXIMATELY 12.878 MILES OF HIGHWAY 16 IN WASHINGTON COUNTY. THIS PROJECT CONSISTS OF TRENCHIN | Washington | 3 | Grant Garrett Excavating, Inc. | $4,798,314 | $5,445,157 | +13% | ARDOT |
| A30039 | THE PURPOSE OF THIS PROJECT IS TO OVERLAY APPROXIMATELY 11.417 MILES OF HIGHWAY 371 IN NEVADA COUNTY. THIS PROJECT CONSISTS OF AGGREGATE BASE COURSE, ACHM SURFA | Nevada | 2 | Cranford Construction Co. | $4,752,638 | $5,040,830 | +6.0% | ARDOT |
| A80042 | THE PURPOSE OF THIS PROJECT IS TO MILL AND OVERLAY APPROXIMATELY 9.025 MILES OF HIGHWAYS 7 AND 27 IN YELL COUNTY. THIS PROJECT CONSISTS OF REMOVAL AND DISPOSAL | Yell | 1 | Blackstone Construction, LLC | $4,617,183 | ARDOT | ||
| A80046 | THE PURPOSE OF THIS PROJECT IS TO OVERLAY APPROXIMATELY 12.513 MILES OF HIGHWAY 225 IN FAULKNER COUNTY. THIS PROJECT CONSISTS OF CLEARING AND GRUBBING, REMOVAL | Faulkner | 2 | Rogers Group, Inc. | $4,070,029 | $4,758,439 | +17% | ARDOT |
| A10051 | THE PURPOSE OF THIS PROJECT IS TO OVERLAY APPROXIMATELY 11.319 MILES OF HIGHWAYS 50 AND 64B IN CRITTENDEN COUNTY. THIS PROJECT CONSISTS OF TRENCHING AND SHOULDE | Crittenden | 3 | Delta Asphalt of Arkansas, Inc. | $4,066,218 | $4,943,918 | +22% | ARDOT |
| A30040 | THE PURPOSE OF THIS PROJECT IS TO OVERLAY APPROXIMATELY 7.639 MILES OF HIGHWAY 27 IN PIKE COUNTY. THIS PROJECT CONSISTS OF REMOVAL AND DISPOSAL ITEMS, AGGREGATE | Pike | 3 | Blackstone Construction, LLC | $3,051,326 | $3,080,681 | +1.0% | ARDOT |
| FA1108 | THE PURPOSE OF THIS PROJECT IS TO REPLACE 1 BRIDGE AND RECONSTRUCT APPROXIMATELY 1.01 MILES OF COUNTRY ROAD 53 IN CLAY COUNTY. THIS PROJECT CONSISTS OF CLEARING | Clay | 7 | Delta Asphalt of Arkansas, Inc. | $2,967,542 | $3,067,778 | +3.0% | ARDOT |
| A00092 | THE PURPOSE OF THIS PROJECT IS TO MILL AND OVERLAY APPROXIMATELY 3.613 MILES OF HIGHWAY 18 IN MISSISSIPPI COUNTY. THIS PROJECT CONSISTS OF ACHM SURFACE COURSE, | Mississippi | 2 | Delta Asphalt of Arkansas, Inc. | $2,084,107 | $2,911,212 | +40% | ARDOT |
| 061920 | THE PURPOSE OF THIS PROJECT IS TO PLACE ULTRATHIN BONDED WEARING COURSE ON APPROXIMATELY 6.235 MILES ON VARIOUS SECTIONS IN VARIOUS COUNTIES. THIS PROJECT CONSI | Various | 2 | Redstone Construction Group, Inc. | $1,799,733 | $1,823,147 | +1.0% | ARDOT |
| A80041 | THE PURPOSE OF THIS PROJECT IS TO LEVEL AND OVERLAY APPROXIMATELY 5.290 MILES OF HIGHWAY 154 IN CONWAY COUNTY. THIS PROJECT CONSISTS OF AGGREGATE SURFACE COURSE | Conway | 3 | Blackstone Construction, LLC | $1,370,692 | $1,454,747 | +6.0% | ARDOT |
| 012550 | THE PURPOSE OF THIS PROJECT IS TO INSTALL RAISED PAVEMENT MARKERS ON VARIOUS ROUTES IN VARIOUS COUNTIES. THIS PROJECT CONSISTS OF MAINTENANCE OF TRAFFIC, RAISED | Various | 5 | Highway Graphics, L.L.C. | $1,291,187 | $1,321,794 | +2.0% | ARDOT |
| 012552 | THE PURPOSE OF THIS PROJECT IS TO INSTALL RAISED PAVEMENT MARKERS ON VARIOUS ROUTES IN VARIOUS COUNTIES. THIS PROJECT CONSISTS OF MAINTENANCE OF TRAFFIC, RAISED | Various | 4 | Contractor'S Specialty Service Co. | $1,202,684 | $1,219,229 | +1.0% | ARDOT |
| A00091 | THE PURPOSE OF THIS PROJECT IS TO MILL AND OVERLAY APPROXIMATELY 3.899 MILES OF HIGHWAY 1 IN POINSETT COUNTY. THIS PROJECT CONSISTS OF ACHM SURFACE COURSE, COLD | Poinsett | 4 | Atlas Asphalt, Inc. | $1,195,815 | $1,333,011 | +11% | ARDOT |
| 012542 | THE PURPOSE OF THIS PROJECT IS TO LAY A HIGH FRICTION SURFACE TREATMENT ON APPROXIMATELY 3.348 MILES ON VARIOUS SECTIONS IN VARIOUS COUNTIES. THIS PROJECT CONSI | Various | 3 | The Truesdell Corporation | $1,139,139 | $1,156,534 | +2.0% | ARDOT |
| SA7041 | THE PURPOSE OF THIS PROJECT IS TO OVERLAY APPROXIMATELY 3.97 MILES OF CO. RD. 2 (WESSON RD.) IN UNION COUNTY. THIS PROJECT CONSISTS OF ACHM SURFACE COURSE, MAIN | Union | 1 | Jet Asphalt & Rock Co., Inc. | $981,119 | ARDOT | ||
| C76095 | THE PURPOSE OF THIS PROJECT IS TO OVERLAY APPROXIMATELY 0.75 MILE OF VARIOUS CITY STREETS IN THE CITY OF GOULD AND APPROXIMATELY 1.49 MILES OF VARIOUS CITY STRE | Drew, Lincoln | 2 | Pine Bluff Sand & Gravel Co. | $840,891 | $866,966 | +3.0% | ARDOT |
| C73018 | THE PURPOSE OF THIS PROJECT IS TO OVERLAY 1.95 MILES OF VARIOUS CITY STREETS IN GARNER, 2.25 MILES OF VARIOUS CITY STREETS IN JUDSONIA, AND 2.12 MILES OF VARIOU | White | 4 | CK Asphalt, LLC | $836,167 | $917,949 | +10% | ARDOT |
| C10008 | THE PURPOSE OF THIS PROJECT IS TO OVERLAY AND SURFACE APPROXIMATELY 1.06 MILES OF VARIOUS CITY STREETS IN THE CITY OF GUM SPRINGS, OVERLAY APPROXIMATELY 1.04 MI | Clark | 4 | Salt Creek Paving & Const. Co., Inc. | $813,515 | $832,258 | +2.0% | ARDOT |
| SA7140 | THE PURPOSE OF THIS PROJECT IS TO OVERLAY APPROXIMATELY 4.95 MILES OF BANNER MOUNTAIN ROAD IN VAN BUREN COUNTY. THIS PROJECT CONSISTS OF AGGREGATE SURFACE COURS | Van Buren | 2 | Rogers Group, Inc. | $811,586 | $818,195 | +1.0% | ARDOT |
| A60059 | THE PURPOSE OF THIS PROJECT IS TO MILL AND OVERLAY APPROXIMATELY 1.787 MILES OF HIGHWAY 70 IN PULASKI COUNTY. THIS PROJECT CONSISTS OF ACHM SURFACE COURSE, COLD | Pulaski | 2 | Cranford Construction Co. | $810,825 | $997,441 | +23% | ARDOT |
| C42007 | THE PURPOSE OF THIS PROJECT IS TO OVERLAY AND SURFACE APPROXIMATELY 1.23 MILES OF VARIOUS CITY STREETS IN THE CITY OF BLUE MOUNTAIN, OVERLAY APPROXIMATELY 0.95 | Logan | 4 | Blackstone Construction, LLC | $718,829 | $731,914 | +2.0% | ARDOT |
| C75007 | THE PURPOSE OF THIS PROJECT IS TO OVERLAY APPROXIMATELY 1.93 MILES OF VARIOUS CITY STREETS IN THE CITY OF BELLEVILLE, OVERLAY AND SURFACE APPROXIMATELY 0.68 MIL | Yell | 1 | Blackstone Construction, LLC | $645,813 | ARDOT | ||
| C04029 | THE PURPOSE OF THIS PROJECT IS TO OVERLAY APPROXIMATELY 1.12 MILES OF VARIOUS CITY STREETS IN THE CITY OF BELLA VISTA & 2.25 MILES IN THE CITY OF HIGHFILL IN BE | Benton | 4 | Emery Sapp & Sons, Inc. | $532,629 | $544,883 | +2.0% | ARDOT |
| C76091 | THE PURPOSE OF THIS PROJECT IS TO OVERLAY APPROXIMATELY 1.01 MILES OF VARIOUS CITY STREETS IN THE CITY OF HAYNES IN LEE COUNTY, AND OVERLAY AND SURFACE APPROXIM | Lee, St. Francis | 3 | Atlas Asphalt, Inc. | $525,395 | $543,090 | +3.0% | ARDOT |
| SA3550 | THE PURPOSE OF THIS PROJECT IS TO OVERLAY APPROXIMATELY 2.80 MILES OF ISLAND HARBOR MARINA DR. IN JEFFERSON COUNTY. THIS PROJECT CONSISTS OF ACHM SURFACE COURSE | Jefferson | 1 | Pine Bluff Sand & Gravel Co. | $510,239 | ARDOT | ||
| C47022 | THE PURPOSE OF THIS PROJECT IS TO OVERLAY APPROXIAMATELY 1.16 MILES OF VARIOUS CITY STREETS IN BLYTHEVILLE AND APPROXIMATELY 1.60 MILES OF VARIOUS CITY STREETS | Mississippi | 3 | Sugg Construction, Inc. | $508,935 | $530,824 | +4.0% | ARDOT |
| SA0654 | THE PURPOSE OF THIS PROJECT IS TO LEVEL AND RESEAL APPROXIMATELY 8.76 MILES ON COUNTY ROADS 1, 55, & 57 IN BRADLEY COUNTY. THIS PROJECT CONSISTS OF ACHM SURFACE | Bradley | 2 | Salt Creek Paving & Const. Co., Inc. | $482,950 | $498,037 | +3.0% | ARDOT |
| C19007 | THE PURPOSE OF THIS PROJECT IS TO OVERLAY AND SURFACE APPROXIMATELY 0.97 MILE OF VARIOUS CITY STREETS IN THE CITY OF CHERRY VALLEY AND 1.63 MILES OF VARIOUS CIT | Cross | 5 | Sugg Construction, Inc. | $454,684 | $467,033 | +3.0% | ARDOT |
| C25005 | THE PURPOSE OF THIS PROJECT IS TO OVERLAY APPROXIMATELY 1.25 MILES OF VARIOUS CITY STREETS IN THE CITY OF SALEM AND APPROXIMATELY 1.55 MILES OF VARIOUS CITY STR | Fulton | 2 | Atlas Asphalt, Inc. | $436,753 | $450,537 | +3.0% | ARDOT |
| C76094 | THE PURPOSE OF THIS PROJECT IS TO SURFACE APPROXIMATELY 0.43 MILE OF HILBURN POINT ROAD IN THE CITY OF ALTUS IN FRANKLIN COUNTY AND TO OVERLAY APPROXIMATELY 1.0 | Franklin, Johnson | 2 | Blackstone Construction, LLC | $379,851 | $463,353 | +22% | ARDOT |
| 030656 | THE PURPOSE OF THIS PROJECT IS TO PLACE ULTRATHIN BONDED WEARING COURSE ON APPROXIMATELY 1.94 MILES ON I-30 IN HEMPSTEAD COUNTY. THIS PROJECT CONSISTS OF ULTRAT | Hempstead | 2 | Redstone Construction Group, Inc. | $367,213 | $435,309 | +19% | ARDOT |
| C76093 | THE PURPOSE OF THIS PROJECT IS TO OVERLAY AND SURFACE APPROXIMATELY 1.55 MILES OF VARIOUS CITY STREETS IN THE CITY OF AMAGON IN JACKSON COUNTY AND 1.02 MILES OF | Craighead, Jackson | 5 | Atlas Asphalt, Inc. | $363,830 | $371,308 | +2.0% | ARDOT |
| C37007 | THE PURPOSE OF THIS PROJECT IS TO OVERLAY APPROXIMATELY 0.83 MILE OF VARIOUS CITY STREETS IN THE CITY OF BRADLEY IN LAFAYETTE COUNTY. THIS PROJECT CONSISTS OF B | Lafayette | 2 | Cranford Construction Co. | $338,571 | $426,493 | +26% | ARDOT |
| C55003 | THE PURPOSE OF THIS PROJECT IS TO OVERLAY APPROXIMATELY 1.66 MILES OF VARIOUS CITY STREETS IN THE CITY OF DELIGHT, LOCATED IN PIKE COUNTY. THIS PROJECT CONSISTS | Pike | 4 | Blackstone Construction, LLC | $327,642 | $345,238 | +5.0% | ARDOT |
| C05010 | THE PURPOSE OF THIS PROJECT IS TO OVERLAY APPROXIMATELY 1.05 MILES OF VARIOUS CITY STREETS IN THE CITY OF BELLEFONTE AND 0.67 MILE OF VARIOUS CITY STREETS IN TH | Boone | 2 | Apac-Central, Inc. | $303,035 | $458,883 | +51% | ARDOT |
| C07003 | THE PURPOSE OF THIS PROJECT IS TO SURFACE APPROXIMATELY 0.87 MILE OF VARIOUS CITY STREETS IN THE CITY OF HARRELL IN CALHOUN COUNTY. THIS PROJECT CONSISTS OF AGG | Calhoun | 1 | Smackover Paving Co. | $297,688 | ARDOT | ||
| SA6146 | THE PURPOSE OF THIS PROJECT IS TO OVERLAY APPROXIMATELY 2.00 MILES OF CO. RDS. 2 AND 16 IN RANDOLPH COUNTY. THIS PROJECT CONSISTS OF AGGREGATE BASE COURSE, ACHM | Randolph | 5 | Atlas Asphalt, Inc. | $250,965 | $267,804 | +7.0% | ARDOT |
| C18021 | THE PURPOSE OF THIS PROJECT IS TO OVERLAY APPROXIMATELY 1.84 MILES OF VARIOUS CITY STREETS IN THE CITY OF HORSESHOE LAKE IN CRITTENDEN COUNTY. THIS PROJECT CONS | Crittenden | 3 | M & T Paving & Const. Co., Inc. | $246,085 | $247,618 | +1.0% | ARDOT |
| SA4284 | THE PURPOSE OF THIS PROJECT IS TO LEVEL AND RESEAL APPROXIMATELY 4.10 MILES ON COUNTY ROAD 92 IN LOGAN COUNTY. THIS PROJECT CONSISTS OF ACHM SURFACE COURSE, RES | Logan | 2 | Salt Creek Paving & Const. Co., Inc. | $237,470 | $328,707 | +38% | ARDOT |
| C60015 | THE PURPOSE OF THIS PROJECT IS TO OVERLAY APPROXIMATELY 0.67 MILE OF MAIN STREET IN THE CITY OF NORTH LITTLE ROCK IN PULASKI COUNTY. THIS PROJECT CONSISTS OF AC | Pulaski | 2 | Cranford Construction Co. | $231,410 | $299,601 | +29% | ARDOT |
| C45008 | THE PURPOSE OF THIS PROJECT IS TO OVERLAY APPROXIMATELY 1.27 MILES OF VARIOUS CITY STREETS IN THE CITY OF BULL SHOALS IN MARION COUNTY. THIS PROJECT CONSISTS OF | Marion | 2 | Apac-Central, Inc. | $224,809 | $236,586 | +5.0% | ARDOT |
| C53009 | THE PURPOSE OF THIS PROJECT IS TO OVERLAY APPROXIMATELY 1.13 MILES OF VARIOUS CITY STREETS IN THE CITY OF PERRY IN PERRY COUNTY. THIS PROJECT CONSISTS OF AGGREG | Perry | 3 | CK Asphalt, LLC | $187,870 | $189,686 | +1.0% | ARDOT |
| SA2045 | THE PURPOSE OF THIS PROJECT IS TO OVERLAY APPROXIMATELY 1.02 MILES OF CO. RD. 236 IN DALLAS COUNTY. THIS PROJECT CONSISTS OF ACHM SURFACE COURSE, MAINTENANCE OF | Dallas | 4 | Cranford Construction Co. | $178,286 | $187,122 | +5.0% | ARDOT |
| C32011 | THE PURPOSE OF THIS PROJECT IS TO OVERLAY APPROXIMATELY 1.45 MILES OF VARIOUS CITY STREETS IN THE CITY OF OIL TROUGH IN INDEPENDENCE COUNTY. THIS PROJECT CONSIS | Independence | 3 | Atlas Asphalt, Inc. | $176,146 | $190,281 | +8.0% | ARDOT |
| C38015 | THE PURPOSE OF THIS PROJECT IS TO OVERLAY APPROXIMATELY 1.52 MILES OF VARIOUS CITY STREETS IN THE CITY OF STRAWBERRY, LOCATED IN LAWRENCE COUNTY. THIS PROJECT C | Lawrence | 4 | Atlas Asphalt, Inc. | $171,095 | $194,148 | +13% | ARDOT |
| C33011 | THE PURPOSE OF THIS PROJECT IS TO SURFACE APPROXIMATELY 0.29 MILE OF KENT MILLER ROAD IN THE CITY OF GUION IN IZARD COUNTY. THIS PROJECT CONSISTS OF AGGREGATE B | Izard | 1 | Atlas Asphalt, Inc. | $106,029 | ARDOT |
Gap is the second bid over the low bid. Where a contract shows fewer bids than ARDOT received, the others did not match their published totals and are left out. Each contract number opens its full bid tabulation.