ARDOT contract A30040 bid tabulation

THE PURPOSE OF THIS PROJECT IS TO OVERLAY APPROXIMATELY 7.639 MILES OF HIGHWAY 27 IN PIKE COUNTY. THIS PROJECT CONSISTS OF REMOVAL AND DISPOSAL ITEMS, AGGREGATE BASE COURSE, ACHM SURFACE COURSE, COLD MILLING ASPHALT PAVEMENT, ACHM PATCHING OF EXISTING ROADWAY, MAINTENANCE OF TRAFFIC, GUARDRAIL, RUMBLE STRIPS AND STRIPES, PAVEMENT MARKING, AND MISC. ITEMS. Let by Arkansas DOT on January 21, 2026, Pike. 3 bids received; low bid $3,051,326 by Blackstone Construction, LLC.

Owner
Arkansas DOT
Letting
21 JAN 2026
Pay items
25
Data through
04 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Blackstone Construction, LLC$3,051,326Low
2Cranford Construction Co.$3,080,681+1.0%
3Redstone Construction Group, Inc.$3,196,855+5.0%
ARDOT contract A30040: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Blackstone Construction, LLC2. Cranford Construction Co.3. Redstone Construction Group, Inc.
0001Removal and disposal of guardrail (202132)LF350$12.19$12.19$12.19
0002Removal and disposal of bridge end terminal (202508)EACH1$2,676.35$2,676.35$2,676.35
0003Aggregate base course (class 7) (303117)TON2,412$40.21$56.55$54.46
0004Tack coat (401011)GAL37,610$0.01$0.01$0.01
0005Mineral aggregate in achm surface course (1/2") (407162)TON20,432$115.94$117.41$120.49
0006Asphalt binder (PG 64-22) in achm surface course (1/2") (minimum bid $120.00) (407432)TON6$120.00$120.00$120.00
0007Asphalt binder (PG 70-22) in achm surface course (1/2") (minimum bid $120.00) (407442)TON1,298$120.00$120.00$120.00
0008Cold milling asphalt pavement (412002)SY1,921$5.00$6.94$12.30
0009Asphalt concrete patching for maintenance of traffic (414011)TON191$100.00$123.15$25.00
0010Achm patching of existing roadway (415011)TON125$250.00$216.21$303.78
0011Maintenance of traffic (603009)LS1$15,000$88,163$104,304
0012Signs (604003)SF652$5.75$5.75$5.00
0013Construction pavement markings (604041)LF161,758$0.15$0.15$0.15
0014Guardrail (type A) (617005)LF300$40.69$40.69$40.69
0015Guardrail terminal (type 2) (617312)EACH3$3,864.50$3,864.50$3,864.50
0016Thrie beam guardrail terminal (617332)EACH3$2,712.79$2,712.79$2,712.79
0017Roadway construction control (635011)LS1$7,682.10$8,045.35$4,453.02
0018Rumble strips in asphalt shoulders (642001)LF60,268$0.19$0.14$0.25
0019Centerline rumble stripes in asphalt roadways (642102)LF37,668$0.19$0.14$0.14
0020Thermoplastic pavement marking white (6") (719002)LF80,879$0.70$0.60$0.60
0021Thermoplastic pavement marking yellow (6") (719102)LF80,879$0.45$0.58$0.58
0022Thermoplastic pavement marking (words) (719201)EACH2$500.00$350.00$350.00
0023Raised pavement markers (type II) (721002)EACH524$7.00$4.50$4.50
0024Bridge end terminal (734011)EACH1$36,900$36,948$30,924
0025Mobilization (unit bid amount may not exceed 5% of subtotal) (601001)LS1$125,879$12,369$55,492
ARDOT contract A30040: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from ARDOT's tabulation for this contract. ARDOT monthly bid tab PDFs (morning and afternoon sessions), January 2022 to November 2026. Base bids are printed in whole dollars; on A+B and A+C jobs the base bid is kept, and the published rank follows the award amount.

Every contract let that day: ARDOT letting of January 21, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy