ARDOT contract 061371 bid tabulation
THE PURPOSE OF THIS PROJECT IS TO RECONFIGURE THE HIGHWAY 5 INTERCHANGE AND REPLACE ONE STRUCTURE OVER I-57 IN LONOKE COUNTY. THIS PROJECT CONSISTS OF CLEARING AND GRUBBING, REMOVAL AND DISPOSAL ITEMS, FLOWABLE SELECT MATERIAL, STONE BACKFILL, EARTHWORK, SELECT GRANULAR BACKFILL,TRENCHING AND SHOULDER PREPARATION, AGGREGATE BASE COURSE, CEMENT STABILIZED CRUSHED STONE BASE COURSE, PORTLAND CEMENT CONCRETE BASE, ACHM BASE, BINDER, AND SURFACE COURSES, COLD MILLING ASPHALT PAVEMENT, ACHM PATCHING OF EXISTING ROADWAY, PORTLAND CEMENT CONCRETE PAVEMENT, APPROACH SLABS, PORTLAND CEMENT CONCRETE DRIVEWAY, MAINTENANCE OF TRAFFIC, CONCRETE DITCH PAVING, MINOR DRAINAGE, GUARDRAIL, EROSION CONTROL, CONCRETE ISLAND, CONCRETE WALKS, CURB, AND GUTTER, WHEELCHAIR RAMPS, TRAFFIC SIGNAL ITEMS, SIGNING ITEMS, LIGHTING ITEMS, PAVEMENT MARKING, CONSTRUCT ONE PRESTRESSED CONCRETE GIRDER UNIT (TOTAL LENGTH 182.22'), AND MISC. ITEMS. Let by Arkansas DOT on January 21, 2026, Lonoke. 4 bids received; low bid $53,972,317 by Weaver-Bailey Contractors, Inc..
- Owner
- Arkansas DOT
- Letting
- 21 JAN 2026
- Pay items
- 274
- Data through
- 04 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Weaver-Bailey Contractors, Inc. | $53,972,317 | Low |
| 2 | McMillen, Inc. | $55,391,633 | +3.0% |
| 3 | Webber, LLC | $58,000,000 | +7.0% |
| 4 | McGeorge Contracting Co., Inc. | $64,570,218 | +20% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Weaver-Bailey Contractors, Inc. | 2. McMillen, Inc. | 3. Webber, LLC | 4. McGeorge Contracting Co., Inc. |
|---|---|---|---|---|---|---|---|
| 0001 | Clearing (201011) | STA | 24 | $6,234.38 | $25,000 | $125,330 | $16,630 |
| 0002 | Grubbing (201111) | STA | 24 | $2,079.00 | $18,000 | $122,260 | $7,705.55 |
| 0003 | Removal and disposal of curb and gutter (202003) | LF | 1,787 | $15.89 | $35.00 | $5.60 | $5.22 |
| 0004 | Removal and disposal of gates (202017) | EACH | 4 | $722.82 | $1,000.00 | $922.00 | $1,303.65 |
| 0005 | Removal and disposal of barrier wall (202037) | LF | 763 | $85.25 | $125.00 | $34.25 | $29.09 |
| 0006 | Removal of existing portland cement concrete pavement (202044) | SY | 1,713 | $43.35 | $55.00 | $11.60 | $20.35 |
| 0007 | Removal and disposal of concrete islands (202047) | SY | 702 | $20.74 | $55.00 | $26.00 | $5.79 |
| 0008 | Removal and disposal of approach slab and gutters (202053) | EACH | 2 | $9,818.35 | $15,000 | $3,810.00 | $1,001.10 |
| 0009 | Removal and disposal of concrete driveways (202062) | SY | 3,876 | $23.36 | $20.00 | $21.50 | $9.39 |
| 0010 | Removal and disposal of walks (202072) | SY | 450 | $16.93 | $50.00 | $17.69 | $11.59 |
| 0011 | Removal and disposal of sign foundations (202084) | EACH | 2 | $3,419.29 | $2,500.00 | $309.00 | $5,214.64 |
| 0012 | Removal and disposal of drop inlets (202093) | EACH | 12 | $1,090.44 | $3,000.00 | $1,130.00 | $1,303.66 |
| 0013 | Removal and disposal of pipe culverts (202096) | EACH | 39 | $2,091.45 | $1,900.00 | $4,510.00 | $1,303.66 |
| 0014 | Removal and disposal of headwalls (202099) | EACH | 4 | $2,079.04 | $2,400.00 | $819.00 | $1,001.08 |
| 0015 | Removal and disposal of guardrail (202132) | LF | 1,586 | $8.26 | $14.00 | $10.20 | $13.89 |
| 0016 | Removal and disposal of signs (202191) | EACH | 18 | $2,460.97 | $900.00 | $614.00 | $637.08 |
| 0017 | Removal and disposal of mailboxes (202200) | EACH | 12 | $598.65 | $500.00 | $164.00 | $200.22 |
| 0018 | Removal of existing bridge structure (site no. 1) (205011) | LS | 1 | $525,000 | $600,000 | $428,765 | $464,695 |
| 0019 | Flowable select material (206021) | CY | 160 | $366.49 | $300.00 | $200.00 | $339.78 |
| 0020 | Stone backfill (207011) | TON | 165 | $109.26 | $120.00 | $130.00 | $79.63 |
| 0021 | Unclassified excavation (210213) | CY | 85,864 | $19.35 | $17.00 | $23.75 | $52.06 |
| 0022 | Select granular backfill (210433) | CY | 40,039 | $56.76 | $65.00 | $55.75 | $52.14 |
| 0023 | Compacted embankment (210611) | CY | 420,794 | $24.50 | $19.00 | $19.50 | $37.38 |
| 0024 | Soil stabilization (210702) | TON | 1,500 | $331.23 | $350.00 | $204.00 | $5.35 |
| 0025 | Trenching and shoulder preparation (215011) | STA | 9 | $2,241.26 | $3,500.00 | $146.00 | $2,479.23 |
| 0026 | Aggregate base course (class 7) (303117) | TON | 28,845 | $49.07 | $31.00 | $40.25 | $46.46 |
| 0027 | Aggregate in cement stabilized crushed stone base course (308021) | TON | 5,421 | $32.87 | $31.00 | $26.80 | $179.84 |
| 0028 | Cement in cement stabilized crushed stone base course (308203) | TON | 346 | $239.65 | $265.00 | $236.00 | $346.38 |
| 0029 | Processing cement stabilized crushed stone base course (308204) | SY | 16,476 | $15.78 | $3.50 | $4.25 | $10.26 |
| 0030 | Portland cement concrete base (5" uniform thickness) (309505) | SY | 1,879 | $119.54 | $100.00 | $131.00 | $104.00 |
| 0031 | Tack coat (401011) | GAL | 11,333 | $1.06 | $1.00 | $1.05 | $1.11 |
| 0032 | Tack coat (401011) | GAL | 48 | $1.00 | $1.05 | ||
| 0033 | Mineral aggregate in achm base course (1 1/2") (405161) | TON | 12,959 | $65.67 | $62.00 | $66.00 | $69.10 |
| 0034 | Mineral aggregate in achm base course (1 1/2") (405161) | TON | 202 | $62.00 | $66.00 | ||
| 0035 | Asphalt binder (PG 70-22) in achm base course (1 1/2") (minimum bid $120.00) (405412) | TON | 582 | $741.42 | $720.00 | $767.00 | $802.40 |
| 0036 | Asphalt binder (PG 70-22) in achm base course (1 1/2") (minimum bid $120.00) (405412) | TON | 9 | $720.00 | $767.00 | ||
| 0037 | Mineral aggregate in achm binder course (1") (406161) | TON | 9,491 | $75.20 | $73.00 | $78.00 | $81.35 |
| 0038 | Mineral aggregate in achm binder course (1") (406161) | TON | 88 | $73.00 | $80.00 | ||
| 0039 | Asphalt binder (PG 70-22) in achm binder course (1") (minimum bid $120.00) (406412) | TON | 447 | $741.42 | $720.00 | $767.00 | $802.40 |
| 0040 | Asphalt binder (PG 70-22) in achm binder course (1") (minimum bid $120.00) (406412) | TON | 4 | $720.00 | $767.00 | ||
| 0041 | Mineral aggregate in achm surface course (3/8") (407161) | TON | 852 | $79.44 | $77.50 | $82.50 | $86.37 |
| 0042 | Mineral aggregate in achm surface course (1/2") (407162) | TON | 15,803 | $84.73 | $78.25 | $83.25 | $87.20 |
| 0043 | Mineral aggregate in achm surface course (1/2") (407162) | TON | 50 | $78.25 | $83.25 | ||
| 0044 | Asphalt binder (PG 64-22) in achm surface course (3/8") (minimum bid $120.00) (407431) | TON | 54 | $582.55 | $566.00 | $603.00 | $630.77 |
| 0045 | Asphalt binder (PG 64-22) in achm surface course (1/2") (minimum bid $120.00) (407432) | TON | 28 | $582.55 | $566.00 | $603.00 | $630.77 |
| 0046 | Asphalt binder (PG 70-22) in achm surface course (1/2") (minimum bid $120.00) (407442) | TON | 111 | $741.42 | $721.00 | $768.00 | $803.51 |
| 0047 | Asphalt binder (PG 70-22) in achm surface course (1/2") (minimum bid $120.00) (407442) | TON | 3 | $720.00 | $767.00 | ||
| 0048 | Asphalt binder (PG 76-22) in achm surface course (1/2") (minimum bid $120.00) (407452) | TON | 819 | $847.34 | $824.00 | $878.00 | $918.30 |
| 0049 | Cold milling asphalt pavement (412002) | SY | 4,880 | $5.83 | $5.65 | $6.00 | $5.93 |
| 0050 | Asphalt concrete patching for maintenance of traffic (414011) | TON | 100 | $270.86 | $275.00 | $272.00 | $322.29 |
| 0051 | Achm patching of existing roadway (415011) | TON | 200 | $318.58 | $232.00 | $247.00 | $243.66 |
| 0052 | Portland cement concrete pavement (9" uniform thickness) (501209) | SY | 481 | $129.68 | $138.96 | ||
| 0053 | Portland cement concrete pavement (12" uniform thickness) (501212) | SY | 14,479 | $145.86 | $155.00 | $103.00 | $170.24 |
| 0054 | Approach slabs (504031) | CY | 629 | $787.50 | $800.00 | $443.00 | $901.12 |
| 0055 | Portland cement concrete driveway (505011) | SY | 3,577.77 | $129.66 | $165.00 | $120.00 | $92.23 |
| 0056 | Mobilization (unit bid amount may not exceed 5% of subtotal) (601001) | LS | 1 | $2,570,000 | $2,480,000 | $2,570,733 | $1,338,600 |
| 0057 | Furnishing field office (602011) | EACH | 1 | $61,646 | $150,000 | $498,665 | $427,294 |
| 0058 | Maintenance of traffic (603010) | LS | 1 | $2,385,348 | $1,500,000 | $5,333,992 | $4,985,863 |
| 0059 | 18" temporary culvert (603018) | LF | 100 | $208.81 | $100.00 | $119.00 | $75.62 |
| 0060 | 24" temporary culvert (603024) | LF | 100 | $224.47 | $150.00 | $132.00 | $91.69 |
| 0061 | Signs (604003) | SF | 2,851 | $5.25 | $7.00 | $5.10 | $6.00 |
| 0062 | Construction project information sign update (604010) | EACH | 6 | $10.50 | $15.00 | $10.20 | $75.00 |
| 0063 | Barricades (604013) | LF | 32 | $21.00 | $30.00 | $20.50 | $16.00 |
| 0064 | Traffic drums (604023) | EACH | 411 | $26.25 | $50.00 | $26.00 | $25.00 |
| 0065 | Traffic cone (604026) | EACH | 96 | $21.00 | $30.00 | $20.50 | $10.00 |
| 0066 | Furnishing and installing precast concrete barrier (604031) | LF | 8,495 | $88.45 | $150.00 | $50.00 | $44.50 |
| 0067 | Relocating precast concrete barrier (max. bid 25% of item number ) (604036) | LF | 10,222 | $15.63 | $18.00 | $10.00 | $11.00 |
| 0068 | Construction pavement markings (604041) | LF | 65,741 | $0.31 | $0.39 | $0.15 | $0.16 |
| 0069 | Construction pavement markings (words) (604045) | EACH | 39 | $55.00 | $70.00 | $102.00 | $100.00 |
| 0070 | Construction pavement markings (arrows) (604046) | EACH | 39 | $55.00 | $70.00 | $102.00 | $100.00 |
| 0071 | Removable construction pavement markings (604051) | LF | 42,618 | $1.98 | $2.50 | $1.95 | $1.92 |
| 0072 | Removal of construction pavement markings (604055) | LF | 8,924 | $1.67 | $2.20 | $0.50 | $0.50 |
| 0073 | Removal of permanent pavement markings (604061) | LF | 11,604 | $1.67 | $2.20 | $0.50 | $0.50 |
| 0074 | Advance warning arrow panel (604071) | DAY | 2,920 | $10.50 | $10.00 | $10.20 | $20.00 |
| 0075 | Portable changeable message sign (604078) | WEEK | 624 | $157.50 | $160.00 | $154.00 | $150.00 |
| 0076 | Mobile speed notification system (special) (604160) | EACH | 2 | $7,350.00 | $35,000 | $7,170.00 | $11,500 |
| 0077 | Concrete ditch paving (type B) (605012) | SY | 351 | $153.94 | $250.00 | $87.00 | $198.99 |
| 0078 | 18" reinforced concrete pipe culverts (class III) (605601) | LF | 1,435 | $108.66 | $110.00 | $112.00 | $99.59 |
| 0079 | 24" reinforced concrete pipe culverts (class III) (605606) | LF | 471 | $161.45 | $130.00 | $184.00 | $182.49 |
| 0080 | 30" reinforced concrete pipe culverts (class III) (605611) | LF | 19 | $152.33 | $275.00 | $704.00 | $145.84 |
| 0081 | 36" reinforced concrete pipe culverts (class III) (605616) | LF | 8 | $193.21 | $500.00 | $471.00 | $201.76 |
| 0082 | 36" reinforced concrete pipe culverts (class IV) (605618) | LF | 447 | $208.95 | $200.00 | $168.00 | $215.71 |
| 0083 | 42" reinforced concrete pipe culverts (class III) (605621) | LF | 13 | $280.07 | $475.00 | $362.00 | $278.08 |
| 0084 | 42" reinforced concrete pipe culverts (class IV) (605623) | LF | 205 | $464.43 | $300.00 | $202.00 | $550.67 |
| 0085 | 48" reinforced concrete pipe culverts (class IV) (605628) | LF | 312 | $281.60 | $310.00 | $223.00 | $361.42 |
| 0086 | 18" flared end sections for reinforced concrete pipe culverts (605856) | EACH | 10 | $2,006.81 | $3,000.00 | $1,330.00 | $1,982.12 |
| 0087 | 24" flared end sections for reinforced concrete pipe culverts (605858) | EACH | 7 | $2,166.65 | $3,100.00 | $1,470.00 | $2,326.45 |
| 0088 | 30" flared end sections for reinforced concrete pipe culverts (605860) | EACH | 2 | $2,770.68 | $3,200.00 | $1,900.00 | $2,870.57 |
| 0089 | 36" flared end sections for reinforced concrete pipe culverts (605862) | EACH | 7 | $3,623.14 | $3,500.00 | $2,230.00 | $3,594.15 |
| 0090 | 42" flared end sections for reinforced concrete pipe culverts (605864) | EACH | 1 | $5,154.42 | $4,000.00 | $2,930.00 | $4,588.00 |
| 0091 | 48" flared end sections for reinforced concrete pipe culverts (605866) | EACH | 4 | $5,700.51 | $4,500.00 | $3,990.00 | $5,787.84 |
| 0092 | 18" side drain (606703) | LF | 196 | $103.12 | $150.00 | $93.00 | $86.16 |
| 0093 | 24" side drain (606704) | LF | 102 | $116.59 | $120.00 | $104.00 | $104.64 |
| 0094 | Selected pipe bedding (606994) | CY | 500 | $103.99 | $50.00 | $99.53 | $141.72 |
| 0095 | Drop inlets (type C) (609013) | EACH | 6 | $10,385 | $20,000 | $10,590 | $10,792 |
| 0096 | Drop inlets (type E) (609015) | EACH | 15 | $6,344.86 | $20,000 | $4,420.00 | $5,598.50 |
| 0097 | Drop inlets (type MO) (609134) | EACH | 65 | $6,885.47 | $15,000 | $8,290.00 | $8,519.65 |
| 0098 | Drop inlets (type ST) (609138) | EACH | 1 | $9,229.27 | $20,000 | $7,280.00 | $8,784.06 |
| 0099 | Drop inlets (type special) (609144) | EACH | 1 | $10,617 | $21,000 | $5,440.00 | $8,654.23 |
| 0100 | Junction boxes (type E) (609215) | EACH | 5 | $6,491.90 | $20,000 | $7,890.00 | $9,640.95 |
| 0101 | Drop inlet extensions (4') (609311) | EACH | 48 | $1,652.13 | $6,000.00 | $5,290.00 | $1,056.54 |
| 0102 | Drop inlet extensions (8') (609312) | EACH | 1 | $3,265.98 | $13,000 | $5,730.00 | $1,657.58 |
| 0103 | 4" pipe underdrains (611008) | LF | 500 | $23.44 | $30.00 | $21.40 | $59.78 |
| 0104 | Underdrain outlet protectors (611013) | EACH | 10 | $1,385.37 | $1,000.00 | $1,430.00 | $837.20 |
| 0105 | Pavement repair over culverts (asphalt) (615022) | TON | 211 | $241.69 | $450.00 | $258.00 | $398.09 |
| 0106 | Guardrail (type A) (617005) | LF | 650 | $33.60 | $34.00 | $32.75 | $32.00 |
| 0107 | Guardrail terminal (type 2) (617312) | EACH | 4 | $3,255.00 | $3,400.00 | $3,170.00 | $3,100.00 |
| 0108 | Thrie beam guardrail terminal (617332) | EACH | 2 | $2,205.00 | $2,400.00 | $2,150.00 | $2,100.00 |
| 0109 | Lime (620001) | TON | 51 | $78.75 | $85.00 | $76.75 | $75.00 |
| 0110 | Seeding (620011) | ACRE | 25.30 | $1,422.75 | $1,500.00 | $1,370.00 | $1,355.00 |
| 0111 | Mulch cover (620022) | ACRE | 50.60 | $945.00 | $1,000.00 | $819.00 | $900.00 |
| 0112 | Water (620030) | MGAL | 3,132.20 | $5.25 | $6.00 | $14.00 | $5.00 |
| 0113 | Temporary seeding (621001) | ACRE | 25.30 | $735.00 | $800.00 | $817.00 | $700.00 |
| 0114 | Silt fence (621021) | LF | 12,878 | $3.15 | $4.00 | $3.05 | $3.00 |
| 0115 | Sand bag ditch checks (621031) | BAG | 1,408 | $8.66 | $12.00 | $9.00 | $8.25 |
| 0116 | Sediment basin (621071) | CY | 250 | $58.79 | $85.00 | $19.50 | $49.37 |
| 0117 | Obliteration of sediment basin (621101) | CY | 250 | $55.34 | $35.00 | $20.00 | $49.37 |
| 0118 | Sediment removal and disposal (621111) | CY | 727 | $83.61 | $80.00 | $16.40 | $49.37 |
| 0119 | Rock ditch checks (621151) | CY | 375 | $110.02 | $160.00 | $114.00 | $69.76 |
| 0120 | Filter sock (18") (621169) | LF | 2,720 | $12.60 | $18.00 | $12.30 | $12.00 |
| 0121 | Second seeding application (623001) | ACRE | 25.30 | $210.00 | $250.00 | $205.00 | $200.00 |
| 0122 | Solid sodding (624001) | SY | 2,822 | $5.51 | $7.50 | $5.40 | $5.25 |
| 0123 | Erosion control matting (class 3) (626003) | SY | 1,497 | $6.25 | $8.50 | $6.10 | $5.95 |
| 0124 | Concrete barrier wall (median type SP-5) (631046) | LF | 200 | $656.08 | $900.00 | $457.00 | $762.74 |
| 0125 | Concrete barrier wall (side type SP-2) (631183) | LF | 663 | $640.50 | $700.00 | $626.00 | $403.55 |
| 0126 | Concrete island (632011) | SY | 1,366 | $76.63 | $285.00 | $99.00 | $121.56 |
| 0127 | Concrete walks (633011) | SY | 3,942 | $95.86 | $120.00 | $93.00 | $91.75 |
| 0128 | Concrete walks (type special) (633017) | SY | 65 | $1,228.33 | $1,400.00 | $927.00 | $1,210.40 |
| 0129 | Hand railing (633201) | LF | 117 | $140.05 | $140.00 | $158.00 | $59.97 |
| 0130 | Concrete curb (type D) (634104) | LF | 99 | $94.10 | $55.00 | $102.00 | $169.98 |
| 0131 | Concrete combination curb and gutter (type A) (1' 6") (634201) | LF | 13,119 | $38.40 | $55.00 | $32.25 | $35.19 |
| 0132 | Roadway construction control (635001) | LS | 1 | $551,203 | $750,000 | $875,400 | $2,174,223 |
| 0133 | Bridge construction control (636001) | LS | 1 | $141,750 | $600,000 | $265,600 | $149,213 |
| 0134 | Mailboxes (637001) | EACH | 12 | $52.50 | $75.00 | $51.25 | $50.00 |
| 0135 | Mailbox supports (single) (637017) | EACH | 12 | $157.50 | $220.00 | $154.00 | $150.00 |
| 0136 | Modifying drop inlets (640021) | EACH | 3 | $7,058.88 | $10,000 | $4,300.00 | $5,000.00 |
| 0137 | Wheelchair ramps (type 3) (641020) | SY | 207 | $414.26 | $600.00 | $400.00 | $488.20 |
| 0138 | Wheelchair ramps (type 4) (641021) | SY | 181 | $405.28 | $500.00 | $400.00 | $385.43 |
| 0139 | Wheelchair ramps (type 5) (641022) | SY | 11 | $483.50 | $2,200.00 | $400.00 | $690.83 |
| 0140 | Actuated controller TS2-type 2 (2 phases) (701022) | EACH | 1 | $25,973 | $35,000 | $25,720 | $24,736 |
| 0141 | System local controller TS2-type 2, E-net (8 phases) (701227) | EACH | 6 | $32,661 | $35,000 | $32,340 | $31,105 |
| 0142 | Traffic signal controller (modification) (701401) | EACH | 4 | $2,341.00 | $2,400.00 | $2,320.00 | $2,229.52 |
| 0143 | Ethernet switch, T100 hardened (8-port) (701722) | EACH | 6 | $799.59 | $800.00 | $792.00 | $761.51 |
| 0144 | E-net cable (exterior cat 5E) (701751) | LF | 256 | $1.67 | $1.75 | $1.65 | $1.59 |
| 0145 | Local radio (E-net 5.8) with antenna (702304) | EACH | 4 | $738.84 | $800.00 | $732.00 | $703.66 |
| 0146 | Battery backup system (702335) | EACH | 2 | $12,909 | $14,000 | $13,030 | $12,295 |
| 0147 | Wic fiber enclosure (704431) | EACH | 2 | $1,285.38 | $1,400.00 | $1,270.00 | $1,224.17 |
| 0148 | Traffic signal head, LED, (1 section,1 way) (706031) | EACH | 1 | $876.62 | $900.00 | $868.00 | $834.88 |
| 0149 | Traffic signal head, LED, (3 section, 1 way) (706039) | EACH | 84 | $1,313.39 | $1,300.00 | $1,300.00 | $1,250.85 |
| 0150 | Traffic signal head, LED, (4 section, 1 way) (706043) | EACH | 17 | $1,688.47 | $1,700.00 | $1,670.00 | $1,608.07 |
| 0151 | Relocation of traffic signal head (706103) | EACH | 43 | $471.03 | $500.00 | $466.00 | $448.60 |
| 0152 | Louvers (706201) | EACH | 11 | $507.90 | $500.00 | $503.00 | $483.71 |
| 0153 | Central control unit (707006) | EACH | 3 | $4,594.01 | $4,500.00 | $4,550.00 | $4,375.25 |
| 0154 | Pole mounted assembly (707007) | EACH | 26 | $1,123.94 | $1,200.00 | $1,110.00 | $1,070.42 |
| 0155 | Countdown pedestrian signal head, LED (707015) | EACH | 26 | $931.90 | $1,000.00 | $923.00 | $887.52 |
| 0156 | Traffic signal cable (3C/14 A.W.G.) (708004) | LF | 493 | $2.49 | $2.75 | $2.45 | $2.37 |
| 0157 | Traffic signal cable (5C/12 A.W.G.) (708007) | LF | 7,741 | $4.00 | $4.00 | $3.95 | $3.81 |
| 0158 | Traffic signal cable (5C/14 A.W.G.) (708008) | LF | 13,203 | $3.12 | $3.20 | $3.10 | $2.97 |
| 0159 | Traffic signal cable (7C/14 A.W.G.) (708012) | LF | 11,876 | $3.33 | $3.50 | $3.30 | $3.17 |
| 0160 | Traffic signal cable (20C/14 A.W.G.) (708038) | LF | 2,250 | $9.49 | $10.00 | $9.39 | $9.04 |
| 0161 | Electrical conductors-in-conduit (1C/8 A.W.G., E.G.C.) (708207) | LF | 3,599 | $2.75 | $3.00 | $2.70 | $2.62 |
| 0162 | Electrical conductors-in-conduit (1C/12 A.W.G., E.G.C.) (708211) | LF | 605 | $1.98 | $2.00 | $1.95 | $1.89 |
| 0163 | Electrical conductors-in-conduit (2C/6 A.W.G.) (708217) | LF | 497 | $5.54 | $6.00 | $5.50 | $5.28 |
| 0164 | Electrical conductors-in-conduit, copper (2C/1 A.W.G., E.G.C.) (708253) | LF | 2,500 | $19.50 | $19.00 | $19.30 | $18.57 |
| 0165 | Electrical conductors-in-conduit copper (2C/6 A.W.G., E.G.C.) (708406) | LF | 3,700 | $7.68 | $8.00 | $7.60 | $7.31 |
| 0166 | Electrical conductors for luminaires (708451) | LF | 4,434 | $3.29 | $3.50 | $3.25 | $3.13 |
| 0167 | Communication cable, fiber (12 channel) (708594) | LF | 2,228 | $4.24 | $4.50 | $4.20 | $4.04 |
| 0168 | Galvanized steel conduit (2") (709004) | LF | 238 | $39.09 | $45.00 | $38.00 | $37.23 |
| 0169 | Galvanized steel conduit (3") (709005) | LF | 210 | $64.43 | $65.00 | $63.75 | $61.36 |
| 0170 | Fiberglass conduit H.D. (3") (709069) | LF | 135 | $155.46 | $150.00 | $154.00 | $148.06 |
| 0171 | Non-metallic conduit (1.25") (710002) | LF | 274 | $22.47 | $23.00 | $22.30 | $21.40 |
| 0172 | Non-metallic conduit (2") (710004) | LF | 4,870 | $19.73 | $20.00 | $19.50 | $18.79 |
| 0173 | Non-metallic conduit (3") (710005) | LF | 3,939 | $21.23 | $22.00 | $21.00 | $20.22 |
| 0174 | Concrete pull box (type 2) (711004) | EACH | 21 | $1,125.09 | $1,100.00 | $1,110.00 | $1,071.51 |
| 0175 | Concrete pull box (type 3) (711005) | EACH | 2 | $1,190.98 | $1,200.00 | $1,180.00 | $1,134.26 |
| 0176 | Concrete pull box (type 3) (711016) | EACH | 3 | $1,343.75 | $1,300.00 | $1,330.00 | $1,279.76 |
| 0177 | Concrete pull box (type 1 HD) (711104) | EACH | 6 | $2,215.77 | $2,200.00 | $2,190.00 | $2,110.26 |
| 0178 | Concrete pull box (type 2 HD) (711105) | EACH | 5 | $2,597.25 | $2,500.00 | $2,570.00 | $2,473.57 |
| 0179 | Concrete pull box (type 3 HD) (711106) | EACH | 4 | $3,113.61 | $3,000.00 | $3,080.00 | $2,965.34 |
| 0180 | Concrete pull box (type 2 HD) (711117) | EACH | 24 | $2,419.22 | $2,400.00 | $2,400.00 | $2,304.02 |
| 0181 | Concrete pull box (type 3 HD) (711118) | EACH | 8 | $2,601.62 | $2,500.00 | $2,580.00 | $2,477.73 |
| 0182 | Span wire assembly (713011) | EACH | 4 | $8,628.47 | $8,300.00 | $8,540.00 | $8,217.59 |
| 0183 | Traffic signal mast arm and pole with foundation (0') (714003) | EACH | 2 | $14,035 | $13,500 | $13,900 | $13,367 |
| 0184 | Traffic signal mast arm and pole with foundation (30') (714030) | EACH | 1 | $29,136 | $28,000 | $28,850 | $27,748 |
| 0185 | Traffic signal mast arm and pole with foundation (32') (714032) | EACH | 1 | $29,584 | $29,000 | $29,290 | $28,175 |
| 0186 | Traffic signal mast arm and pole with foundation (38') (714038) | EACH | 3 | $32,618 | $32,000 | $32,300 | $31,065 |
| 0187 | Traffic signal mast arm and pole with foundation (52') (714052) | EACH | 2 | $46,897 | $48,000 | $46,440 | $44,664 |
| 0188 | Traffic signal mast arm and pole with foundation (62') (714062) | EACH | 2 | $52,567 | $55,000 | $52,100 | $50,064 |
| 0189 | High mast illumination assembly (150'-4 luminaire) (714676) | EACH | 2 | $231,587 | $240,000 | $246,800 | $220,559 |
| 0190 | LED luminaire assembly (714724) | EACH | 11 | $2,657.71 | $2,800.00 | $2,630.00 | $2,531.15 |
| 0191 | LED roadway illumination pole (10,150 lumens, cobra head, bridge, 30') (714841) | EACH | 8 | $7,111.69 | $7,200.00 | $7,040.00 | $6,773.04 |
| 0192 | LED roadway illumination pole (10,150 lumens, cobra head, T-base, 30') (714842) | EACH | 15 | $8,852.34 | $9,000.00 | $8,770.00 | $8,430.80 |
| 0193 | Traffic signal pedestal pole with foundation (715011) | EACH | 16 | $5,291.92 | $5,500.00 | $5,240.00 | $5,039.92 |
| 0194 | Service point assembly (2 circuits) (715102) | EACH | 4 | $5,410.80 | $5,500.00 | $5,360.00 | $5,153.14 |
| 0195 | Pedestal type service point assembly (100 amp) (715111) | EACH | 1 | $20,687 | $23,000 | $20,480 | $19,702 |
| 0196 | Removal of traffic signal equipment (715704) | LS | 1 | $44,810 | $55,000 | $44,370 | $42,676 |
| 0197 | Treated wood pole (class 1, 45') (716145) | EACH | 4 | $3,009.95 | $3,200.00 | $2,980.00 | $2,866.62 |
| 0198 | Treated wood pole (class 1, 50') (716150) | EACH | 1 | $3,373.26 | $3,400.00 | $3,340.00 | $3,212.63 |
| 0199 | Treated wood pole (class 2, 45') (716245) | EACH | 15 | $2,897.87 | $3,000.00 | $2,870.00 | $2,759.88 |
| 0200 | Reflectorized paint pavement marking white (10") (718004) | LF | 1,136 | $1.76 | $1.80 | $3.60 | $3.50 |
| 0201 | Thermoplastic pavement marking white (6") (719002) | LF | 9,297 | $0.74 | $0.75 | $0.70 | $0.69 |
| 0202 | Thermoplastic pavement marking white (8") (719003) | LF | 787 | $2.47 | $2.50 | $3.05 | $3.00 |
| 0203 | Thermoplastic pavement marking white (12") (719005) | LF | 2,710 | $6.60 | $6.50 | $5.25 | $5.15 |
| 0204 | Thermoplastic pavement marking yellow (6") (719102) | LF | 18,243 | $0.71 | $0.85 | $0.70 | $0.69 |
| 0205 | Thermoplastic pavement marking yellow (8") (719103) | LF | 1,101 | $2.47 | $2.50 | $3.60 | $3.50 |
| 0206 | Thermoplastic pavement marking (words) (719201) | EACH | 30 | $275.00 | $300.00 | $282.00 | $275.00 |
| 0207 | Thermoplastic pavement marking (arrows) (719202) | EACH | 30 | $275.00 | $300.00 | $256.00 | $250.00 |
| 0208 | Thermoplastic pavement marking (yield line) (719210) | LF | 153 | $23.10 | $25.00 | $16.40 | $16.00 |
| 0209 | Enhanced thermoplastic pavement marking white (6") (719502) | LF | 9,265 | $0.75 | $0.85 | $0.75 | $0.74 |
| 0210 | Enhanced thermoplastic pavement marking white (12") (719505) | LF | 1,238 | $7.15 | $7.50 | $5.80 | $5.70 |
| 0211 | Enhanced thermoplastic pavement marking yellow (6") (719602) | LF | 5,470 | $0.74 | $0.75 | $0.75 | $0.74 |
| 0212 | Raised pavement markers (type II) (721002) | EACH | 745 | $4.68 | $4.50 | $6.75 | $6.50 |
| 0213 | Steel overhead sign structure (________________) (724022) | EACH | 1 | $236,250 | $300,000 | $230,400 | $225,000 |
| 0214 | Steel overhead sign structure (________________) (724023) | EACH | 1 | $236,250 | $300,000 | $230,400 | $225,000 |
| 0215 | Steel overhead sign structure (________________) (724024) | EACH | 1 | $210,000 | $250,000 | $204,800 | $200,000 |
| 0216 | Steel overhead sign structure (________________) (724025) | EACH | 1 | $210,000 | $250,000 | $204,800 | $200,000 |
| 0217 | Steel monotube sign structure (__________) (724600) | EACH | 1 | $259,128 | $300,000 | $256,600 | $246,788 |
| 0218 | Guide sign-roadside mounted (demountable legend) (725003) | SF | 572 | $44.10 | $45.00 | $43.00 | $42.00 |
| 0219 | Guide sign-overhead mounted (demountable legend) (725103) | SF | 2,142 | $45.15 | $45.00 | $44.00 | $43.00 |
| 0220 | Standard sign (726002) | SF | 805 | $34.65 | $35.00 | $55.50 | $33.00 |
| 0221 | 18" street name sign (726012) | EACH | 8 | $532.30 | $600.00 | $527.00 | $506.95 |
| 0222 | Exit number panel (type A) (727004) | SF | 60 | $44.10 | $50.00 | $43.00 | $42.00 |
| 0223 | Delineator (type 2) (728013) | EACH | 122 | $231.00 | $250.00 | $225.00 | $220.00 |
| 0224 | Barrier wall delineator (728031) | EACH | 64 | $10.50 | $20.00 | $102.00 | $105.00 |
| 0225 | Breakaway sign support (type G-2) (730202) | LB | 8,494 | $9.45 | $10.00 | $9.20 | $9.00 |
| 0226 | Omni-directional breakaway sign supports (type G-1) (730499) | EACH | 16 | $3,360.00 | $3,400.00 | $3,280.00 | $3,200.00 |
| 0227 | Omni-directional breakaway sign supports (type G-2) (730500) | EACH | 1 | $3,675.00 | $3,700.00 | $3,580.00 | $3,500.00 |
| 0228 | Omni-directional breakaway sign supports (type G2-1) (730502) | EACH | 15 | $3,675.00 | $3,700.00 | $3,580.00 | $3,500.00 |
| 0229 | Omni-directional breakaway sign supports (type G2-3) (730504) | EACH | 11 | $3,675.00 | $3,700.00 | $3,580.00 | $3,500.00 |
| 0230 | Omni-directional breakaway sign supports (type G2-6) (730507) | EACH | 4 | $3,675.00 | $3,700.00 | $3,580.00 | $3,500.00 |
| 0231 | Temporary impact attenuation barrier (731071) | EACH | 11 | $5,250.00 | $5,500.00 | $5,120.00 | $5,000.00 |
| 0232 | Temporary impact attenuation barrier (repair) (731072) | EACH | 26 | $1,050.00 | $1,200.00 | $1,020.00 | $1,750.00 |
| 0233 | Temporary impact attenuation barrier (relocation) (731075) | EACH | 15 | $3,675.00 | $3,800.00 | $3,580.00 | $4,000.00 |
| 0234 | Video detector relocation (733003) | EACH | 3 | $963.75 | $1,000.00 | $954.00 | $917.86 |
| 0235 | Video detector rotation (733005) | EACH | 22 | $507.19 | $550.00 | $502.00 | $483.04 |
| 0236 | Video detector (IP) (733008) | EACH | 25 | $5,003.19 | $5,500.00 | $4,950.00 | $4,764.94 |
| 0237 | Hybrid video/radar detector (733009) | EACH | 8 | $11,465 | $12,000 | $11,350 | $10,919 |
| 0238 | Video cable (exterior cat 5E) (733035) | LF | 10,796 | $2.68 | $3.00 | $2.65 | $2.55 |
| 0239 | Video monitor (CLR) (733042) | EACH | 7 | $1,106.30 | $1,200.00 | $1,100.00 | $1,053.62 |
| 0240 | Central control unit (8 channel) (733105) | EACH | 10 | $42,879 | $45,000 | $42,460 | $40,837 |
| 0241 | Unclassified excavation for structures-bridge (801001) | CY | 80 | $157.50 | $150.00 | $86.00 | $124.28 |
| 0242 | Unclassified excavation for structures-roadway (801101) | CY | 68 | $341.18 | $140.00 | $55.00 | $20.97 |
| 0243 | Class S concrete-roadway (802012) | CY | 150.17 | $2,680.95 | $1,900.00 | $1,010.00 | $2,463.10 |
| 0244 | Class S concrete-bridge (802112) | CY | 878.20 | $1,470.00 | $1,600.00 | $865.00 | $1,210.97 |
| 0245 | Class S(AE) concrete-bridge (802122) | CY | 1,319.30 | $1,391.25 | $2,400.00 | $1,600.00 | $1,200.86 |
| 0246 | Retaining wall (802222) | SF | 19,290 | $68.67 | $55.00 | $75.00 | $68.31 |
| 0247 | Temporary retaining wall (802226) | SF | 13,780 | $18.94 | $45.00 | $45.00 | $29.37 |
| 0248 | Architectural finish (802229) | SF | 2,711 | $42.00 | $45.00 | $30.00 | $25.24 |
| 0249 | Prestressed concrete girders (type IV) (802681) | LF | 4,877.60 | $535.50 | $350.00 | $425.00 | $436.54 |
| 0250 | Textured coating finish (802951) | SY | 3,484 | $21.96 | $25.00 | $21.60 | $15.36 |
| 0251 | Class 2 protective surface treatment (803004) | SY | 4,024.20 | $6.56 | $3.50 | $9.25 | $6.96 |
| 0252 | Reinforcing steel-roadway (grade 60) (804003) | LB | 83,547 | $1.64 | $1.75 | $1.85 | $1.73 |
| 0253 | Reinforcing steel-bridge (grade 60) (804013) | LB | 156,690 | $1.84 | $1.75 | $1.45 | $2.30 |
| 0254 | Epoxy coated reinforcing steel (grade 60) (804023) | LB | 324,360 | $2.36 | $2.02 | $1.65 | $2.30 |
| 0255 | Steel piling (HP 14X73) (805024) | LF | 2,424 | $199.50 | $275.00 | $229.00 | $209.54 |
| 0256 | Coring drilled shaft (805041) | LF | 33 | $246.75 | $300.00 | $133.00 | $300.00 |
| 0257 | Drilled shaft (72" diameter) (805059) | LF | 240 | $2,887.50 | $2,600.00 | $900.00 | $2,968.70 |
| 0258 | Permanent steel casing (84" diameter) (805088) | LF | 168 | $1,050.00 | $1,500.00 | $1,060.00 | $1,490.38 |
| 0259 | Crosshole sonic logging (72" diameter) (805712) | EACH | 8 | $2,205.00 | $7,000.00 | $4,620.00 | $2,400.00 |
| 0260 | Metal bridge railing (type H) (806020) | LF | 377 | $210.00 | $165.00 | $130.00 | $228.79 |
| 0261 | Elastomeric bearings (808002) | CUIN | 20,358 | $6.30 | $6.50 | $4.20 | $5.11 |
| 0262 | Silicone joint sealant (809015) | LF | 452 | $78.75 | $45.00 | $7.63 | $92.55 |
| 0263 | Bridge name plate (type D) (812004) | EACH | 1 | $3,150.00 | $5,000.00 | $20,580 | $4,965.60 |
| 0264 | Concrete riprap (816121) | CY | 42 | $2,362.50 | $1,900.00 | $55.75 | $1,669.30 |
| 0265 | Shoring (site no. 1) (821072) | LS | 1 | $236,250 | $530,000 | $254,445 | $232,601 |
| 0266 | NEMA 4X stainless steel junction box (901213) | EACH | 18 | $3,098.34 | $4,000.00 | $3,070.00 | $2,950.80 |
| 0267 | Plane mouldings (916040) | EACH | 2 | $36,750 | $15,000 | $14,730 | $13,135 |
| 0268 | 18" reinforced concrete pipe culverts (class III) (605601) | LF | 3,845 | $108.65 | $75.00 | $112.00 | $99.59 |
| 0271 | 24" reinforced concrete pipe culverts (class III) (605606) | LF | 1,509 | $161.45 | $88.00 | $149.00 | $124.11 |
| 0274 | 30" reinforced concrete pipe culverts (class III) (605611) | LF | 137 | $152.41 | $125.00 | $181.00 | $145.87 |
| 0277 | 36" reinforced concrete pipe culverts (class III) (605616) | LF | 197 | $193.22 | $150.00 | $164.00 | $182.51 |
| 0280 | 42" reinforced concrete pipe culverts (class III) (605621) | LF | 460 | $280.10 | $190.00 | $194.00 | $261.78 |
| 0283 | 44" X 27" reinforced concrete arch pipe culverts (class III) (605761) | LF | 145 | $280.93 | $170.00 | $190.00 | $224.52 |
| 0286 | 51" X 31" reinforced concrete arch pipe culverts (class III) (605762) | LF | 153 | $265.24 | $200.00 | $213.00 | $295.54 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ARDOT's tabulation for this contract. ARDOT monthly bid tab PDFs (morning and afternoon sessions), January 2022 to November 2026. Base bids are printed in whole dollars; on A+B and A+C jobs the base bid is kept, and the published rank follows the award amount.
Every contract let that day: ARDOT letting of January 21, 2026. Compiled by Mirage Metrics.