ARDOT contract SA6146 bid tabulation
THE PURPOSE OF THIS PROJECT IS TO OVERLAY APPROXIMATELY 2.00 MILES OF CO. RDS. 2 AND 16 IN RANDOLPH COUNTY. THIS PROJECT CONSISTS OF AGGREGATE BASE COURSE, ACHM SURFACE COURSE, ACHM PATCHING, PAVEMENT MARKING, MAINTENANCE OF TRAFFIC AND MISC. ITEMS. Let by Arkansas DOT on January 21, 2026, Randolph. 5 bids received; low bid $250,965 by Atlas Asphalt, Inc..
- Owner
- Arkansas DOT
- Letting
- 21 JAN 2026
- Pay items
- 11
- Data through
- 04 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Atlas Asphalt, Inc. | $250,965 | Low |
| 2 | Richard Baughn Construction, Inc. | $267,804 | +7.0% |
| 3 | Sugg Construction, Inc. | $317,603 | +27% |
| 4 | Michelle'S Excavating, Inc. | $331,477 | +32% |
| 5 | Delta Asphalt of Arkansas, Inc. | $347,165 | +38% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Atlas Asphalt, Inc. | 2. Richard Baughn Construction, Inc. | 3. Sugg Construction, Inc. | 4. Michelle'S Excavating, Inc. | 5. Delta Asphalt of Arkansas, Inc. |
|---|---|---|---|---|---|---|---|---|
| 0001 | Aggregate base course (class 7) (303107) | TON | 308 | $26.79 | $38.00 | $38.00 | $40.00 | $42.08 |
| 0002 | Tack coat (401011) | GAL | 2,425 | $3.75 | $2.98 | $3.00 | $6.50 | $4.07 |
| 0003 | Mineral aggregate in achm surface course (1/2") (407162) | TON | 2,503 | $79.46 | $87.04 | $99.00 | $102.63 | $107.54 |
| 0004 | Asphalt binder (PG 64-22) in achm surface course (1/2") (minimum bid $120.00) (407432) | TON | 148 | $120.00 | $120.00 | $120.00 | $120.00 | $120.00 |
| 0005 | Achm patching of existing roadway (415011) | TON | 20 | $125.00 | $118.00 | $150.00 | $200.00 | $307.49 |
| 0006 | Maintenance of traffic (603009) | LS | 1 | $2,187.91 | $1,000.00 | $12,500 | $6,500.00 | $9,000.00 |
| 0007 | Signs (604003) | SF | 284 | $7.00 | $7.10 | $7.00 | $7.00 | $7.00 |
| 0008 | Reflectorized paint pavement marking yellow (4") (718101) | LF | 21,120 | $0.15 | $0.16 | $0.15 | $0.15 | $0.15 |
| 0009 | Standard sign (726002) | SF | 72 | $23.00 | $24.10 | $23.00 | $23.00 | $23.00 |
| 0010 | Channel post sign support (type C) (729003) | EACH | 18 | $80.00 | $84.00 | $80.00 | $80.00 | $80.00 |
| 0011 | Mobilization (unit bid amount may not exceed 5% of subtotal) (601001) | LS | 1 | $4,031.91 | $1,250.00 | $9,315.00 | $10,000 | $14,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ARDOT's tabulation for this contract. ARDOT monthly bid tab PDFs (morning and afternoon sessions), January 2022 to November 2026. Base bids are printed in whole dollars; on A+B and A+C jobs the base bid is kept, and the published rank follows the award amount.
Every contract let that day: ARDOT letting of January 21, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.