ARDOT contract C76091 bid tabulation

THE PURPOSE OF THIS PROJECT IS TO OVERLAY APPROXIMATELY 1.01 MILES OF VARIOUS CITY STREETS IN THE CITY OF HAYNES IN LEE COUNTY, AND OVERLAY AND SURFACE APPROXIMATELY 1.09 MILES OF VARIOUS CITY STREETS IN THE CITY OF MADISON IN ST. FRANCIS COUNTY. THIS PROJECT CONSISTS OF AGGREGATE BASE COURSE, ACHM SURFACE COURSE, ACHM PATCHING, MAINTENANCE OF TRAFFIC, UNCLASSIFIED EXCAVATION, AND MISC ITEMS. Let by Arkansas DOT on January 21, 2026, Lee, St. Francis. 3 bids received; low bid $525,395 by Atlas Asphalt, Inc..

Owner
Arkansas DOT
Letting
21 JAN 2026
Pay items
10
Data through
04 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Atlas Asphalt, Inc.$525,395Low
2M & T Paving & Const. Co., Inc.$543,090+3.0%
3SN Contractors LLC$754,386+44%
ARDOT contract C76091: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Atlas Asphalt, Inc.2. M & T Paving & Const. Co., Inc.3. SN Contractors LLC
0001Unclassified excavation (210201)CY50$36.77$20.00$30.00
0002Aggregate base course (class 7) (303107)TON1,464$65.00$67.45$57.00
0003Tack coat (401011)GAL2,334$4.00$3.75$5.00
0004Mineral aggregate in achm surface course (3/8") (407161)TON2,546$124.71$127.51$196.00
0005Asphalt binder (PG 64-22) in achm surface course (3/8") (minimum bid $120.00) (407431)TON175$120.00$127.51$147.00
0006Cold milling asphalt pavement (412001)SY4,861$3.17$3.48$5.00
0007Achm patching of existing roadway (415011)TON220$150.00$210.00$310.00
0008Maintenance of traffic (603009)LS1$8,221.81$6,000.00$13,750
0009Signs (604003)SF360$7.00$7.00$7.70
0010Mobilization (unit bid amount may not exceed 5% of subtotal) (601001)LS1$21,397$16,000$24,000
ARDOT contract C76091: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from ARDOT's tabulation for this contract. ARDOT monthly bid tab PDFs (morning and afternoon sessions), January 2022 to November 2026. Base bids are printed in whole dollars; on A+B and A+C jobs the base bid is kept, and the published rank follows the award amount.

Every contract let that day: ARDOT letting of January 21, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy