ARDOT contract SA4284 bid tabulation

THE PURPOSE OF THIS PROJECT IS TO LEVEL AND RESEAL APPROXIMATELY 4.10 MILES ON COUNTY ROAD 92 IN LOGAN COUNTY. THIS PROJECT CONSISTS OF ACHM SURFACE COURSE, RESEALING, SINGLE ASPHALT SURFACE TREATMENT, PAVEMENT MARKING, MAINTENANCE OF TRAFFIC, ACHM PATCHING, AND MISC. ITEMS. Let by Arkansas DOT on January 21, 2026, Logan. 2 bids received; low bid $237,470 by Salt Creek Paving & Const. Co., Inc..

Owner
Arkansas DOT
Letting
21 JAN 2026
Pay items
13
Data through
04 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Salt Creek Paving & Const. Co., Inc.$237,470Low
2Apac-Central, Inc.$328,707+38%
ARDOT contract SA4284: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Salt Creek Paving & Const. Co., Inc.2. Apac-Central, Inc.
0001Tack coat (401011)GAL1,290$4.25$3.50
0002Mineral aggregate in asphalt surface treatment (class 2) (402112)TON727$48.00$45.00
0003Polymer modified cationic emulsified asphalt (CRS-2P) (solid polymer) (402214)GAL16,971$4.62$5.65
0004Mineral aggregate in achm surface course (3/8") (407161)TON805$98.10$175.00
0005Asphalt binder (PG 64-22) in achm surface course (3/8") (minimum bid $120.00) (407431)TON55$120.00$120.00
0006Achm patching of existing roadway (415011)TON40$250.00$275.00
0007Maintenance of traffic (603001)LS1$3,300.00$7,500.00
0008Signs (604003)SF292$18.00$19.40
0009Reflectorized paint pavement marking yellow (4") (718101)LF43,296$0.16$0.17
0010Standard sign (726002)SF30.25$25.00$26.94
0011Channel post sign support (type A) (729001)EACH1$90.00$96.99
0012Channel post sign support (type C) (729003)EACH7$90.00$96.99
0013Mobilization (unit bid amount may not exceed 5% of subtotal) (601001)LS1$6,155.00$15,000
ARDOT contract SA4284: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from ARDOT's tabulation for this contract. ARDOT monthly bid tab PDFs (morning and afternoon sessions), January 2022 to November 2026. Base bids are printed in whole dollars; on A+B and A+C jobs the base bid is kept, and the published rank follows the award amount.

Every contract let that day: ARDOT letting of January 21, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way