ARDOT contract A30039 bid tabulation

THE PURPOSE OF THIS PROJECT IS TO OVERLAY APPROXIMATELY 11.417 MILES OF HIGHWAY 371 IN NEVADA COUNTY. THIS PROJECT CONSISTS OF AGGREGATE BASE COURSE, ACHM SURFACE COURSE, COLD MILLING ASPHALT PAVEMENT, ACHM PATCHING OF EXISTING ROADWAY, MAINTENANCE OF TRAFFIC, RUMBLE STRIPS AND STRIPES, PAVEMENT MARKING, AND MISC. ITEMS. Let by Arkansas DOT on January 21, 2026, Nevada. 2 bids received; low bid $4,752,638 by Cranford Construction Co..

Owner
Arkansas DOT
Letting
21 JAN 2026
Pay items
17
Data through
04 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Cranford Construction Co.$4,752,638Low
2Jet Asphalt & Rock Co., Inc.$5,040,830+6.0%
ARDOT contract A30039: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Cranford Construction Co.2. Jet Asphalt & Rock Co., Inc.
0001Aggregate base course (class 7) (303117)TON3,665$53.54$62.50
0002Tack coat (401011)GAL47,826$0.01$0.01
0003Mineral aggregate in achm surface course (1/2") (407162)TON33,654$115.76$120.00
0004Asphalt binder (PG 64-22) in achm surface course (1/2") (minimum bid $120.00) (407432)TON13$284.50$120.00
0005Asphalt binder (PG 70-22) in achm surface course (1/2") (minimum bid $120.00) (407442)TON2,134$120.00$120.00
0006Cold milling asphalt pavement (412002)SY2,578$7.58$9.00
0007Achm patching of existing roadway (415011)TON100$267.52$250.00
0008Maintenance of traffic (603009)LS1$125,908$95,000
0009Signs (604003)SF1,053$5.00$5.40
0010Construction pavement markings (604041)LF241,140$0.15$0.14
0011Roadway construction control (635011)LS1$12,193$45,000
0012Rumble strips in asphalt shoulders (642001)LF61,476$0.14$0.14
0013Centerline rumble stripes in asphalt roadways (642102)LF38,423$0.14$0.14
0014Thermoplastic pavement marking white (6") (719002)LF120,570$0.59$0.72
0015Thermoplastic pavement marking yellow (6") (719102)LF120,570$0.59$0.50
0016Raised pavement markers (type II) (721002)EACH760$4.00$4.50
0017Mobilization (unit bid amount may not exceed 5% of subtotal) (601001)LS1$15,241$123,020
ARDOT contract A30039: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from ARDOT's tabulation for this contract. ARDOT monthly bid tab PDFs (morning and afternoon sessions), January 2022 to November 2026. Base bids are printed in whole dollars; on A+B and A+C jobs the base bid is kept, and the published rank follows the award amount.

Every contract let that day: ARDOT letting of January 21, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy