ARDOT contract FA1108 bid tabulation
THE PURPOSE OF THIS PROJECT IS TO REPLACE 1 BRIDGE AND RECONSTRUCT APPROXIMATELY 1.01 MILES OF COUNTRY ROAD 53 IN CLAY COUNTY. THIS PROJECT CONSISTS OF CLEARING AND GRUBBING, REMOVAL AND DISPOSAL OF ITEMS, EARTHWORK, AGGREGATE BASE COURSE, ACHM BINDER AND SURFACE COURSES, MAINTENANCE OF TRAFFIC, MINOR DRAINAGE STRUCTURES, EROSION CONTROL ITEMS, ONE TRIPLE R.C. BOX CULVERT (TOTAL SPAN 34.74'), AND MISC. ITEMS. Let by Arkansas DOT on January 21, 2026, Clay. 7 bids received; low bid $2,967,542 by Delta Asphalt of Arkansas, Inc..
- Owner
- Arkansas DOT
- Letting
- 21 JAN 2026
- Pay items
- 67
- Data through
- 04 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Delta Asphalt of Arkansas, Inc. | $2,967,542 | Low |
| 2 | Robertson Contractors, Inc. | $3,067,778 | +3.0% |
| 3 | Michelle'S Excavating, Inc. | $3,174,197 | +7.0% |
| 4 | Seagraves Construction, Inc. | $3,267,312 | +10% |
| 5 | White River Materials, Inc. | $3,620,385 | +22% |
| 6 | Richard Baughn Construction, Inc. | $3,723,108 | +25% |
| 7 | Mobley Contractors, Inc. | $4,793,584 | +62% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Delta Asphalt of Arkansas, Inc. | 2. Robertson Contractors, Inc. | 3. Michelle'S Excavating, Inc. | 4. Seagraves Construction, Inc. | 5. White River Materials, Inc. | 6. Richard Baughn Construction, Inc. |
|---|---|---|---|---|---|---|---|---|---|
| 0001 | Clearing (201012) | STA | 53 | $203.68 | $850.00 | $1,500.00 | $1,500.00 | $1,492.20 | $1,200.00 |
| 0002 | Grubbing (201111) | STA | 53 | $226.01 | $370.00 | $1,500.00 | $1,500.00 | $1,683.03 | $1,200.00 |
| 0003 | Removal and disposal of fence (202011) | LF | 2,117 | $4.06 | $5.50 | $2.00 | $2.00 | $4.03 | $0.20 |
| 0004 | Removal and disposal of gates (202017) | EACH | 4 | $746.52 | $650.00 | $200.00 | $200.00 | $442.01 | $100.00 |
| 0005 | Removal and disposal of pipe culverts (202096) | EACH | 3 | $1,389.83 | $850.00 | $500.00 | $500.00 | $1,485.76 | $500.00 |
| 0006 | Removal of existing bridge structure (site no. 1) (205011) | LS | 1 | $29,938 | $30,000 | $40,000 | $40,000 | $25,335 | $24,000 |
| 0007 | Flowable select material (206021) | CY | 4 | $215.17 | $250.00 | $550.00 | $550.00 | $572.34 | $375.00 |
| 0008 | Stone backfill (207011) | TON | 533 | $63.74 | $51.00 | $76.50 | $76.50 | $56.11 | $58.00 |
| 0009 | Fence removed and reconstructed (208001) | LF | 485 | $15.27 | $15.00 | $9.00 | $9.00 | $7.00 | $30.00 |
| 0010 | Unclassified excavation (210213) | CY | 21,805 | $9.98 | $21.65 | $12.00 | $13.00 | $24.56 | $12.00 |
| 0011 | Compacted embankment (210611) | CY | 19,407 | $8.10 | $8.00 | $12.00 | $13.00 | $21.29 | $17.50 |
| 0012 | Aggregate base course (class 7) (303117) | TON | 14,203 | $30.76 | $28.54 | $37.50 | $38.50 | $45.45 | $42.80 |
| 0013 | Tack coat (401011) | GAL | 993 | $4.20 | $5.00 | $6.50 | $6.50 | $5.00 | $3.10 |
| 0014 | Mineral aggregate in achm binder course (1") (406161) | TON | 1,981 | $93.38 | $82.43 | $103.00 | $103.00 | $82.43 | $122.11 |
| 0015 | Asphalt binder (PG 64-22) in achm binder course (1") (minimum bid $120.00) (406402) | TON | 98 | $120.00 | $120.00 | $120.00 | $120.00 | $120.00 | $120.00 |
| 0016 | Mineral aggregate in achm surface course (1/2") (407162) | TON | 1,717 | $108.25 | $94.35 | $103.00 | $103.00 | $94.35 | $142.84 |
| 0017 | Asphalt binder (PG 64-22) in achm surface course (1/2") (minimum bid $120.00) (407432) | TON | 102 | $120.00 | $120.00 | $120.00 | $120.00 | $120.00 | $120.00 |
| 0018 | Mobilization (unit bid amount may not exceed 5% of subtotal) (601001) | LS | 1 | $95,000 | $146,000 | $122,000 | $150,000 | $62,316 | $100,000 |
| 0019 | Furnishing field office (602011) | EACH | 1 | $30,000 | $15,000 | $30,000 | $40,000 | $22,990 | $40,000 |
| 0020 | Maintenance of traffic (603011) | LS | 1 | $125,000 | $40,000 | $60,000 | $70,000 | $86,280 | $75,000 |
| 0021 | Signs (604003) | SF | 409 | $6.50 | $6.50 | $9.00 | $7.00 | $6.50 | $12.00 |
| 0022 | Barricades (604013) | LF | 64 | $18.00 | $18.00 | $23.00 | $16.00 | $18.00 | $24.00 |
| 0023 | Traffic drums (604023) | EACH | 75 | $25.00 | $25.00 | $23.00 | $25.00 | $25.00 | $30.00 |
| 0024 | Vertical panels (604083) | EACH | 25 | $25.00 | $25.00 | $25.00 | $35.00 | $25.00 | $30.00 |
| 0025 | Concrete ditch paving (type A) (605011) | SY | 172 | $196.25 | $180.00 | $131.00 | $131.00 | $102.22 | $225.68 |
| 0026 | Concrete ditch paving (type B) (605012) | SY | 1,547 | $145.31 | $158.00 | $121.00 | $121.00 | $101.56 | $167.11 |
| 0027 | 18" reinforced concrete pipe culverts (class V) (605604) | LF | 32 | $150.54 | $205.00 | $108.50 | $108.50 | $94.24 | $74.00 |
| 0028 | 30" reinforced concrete pipe culverts (class IV) (605613) | LF | 154 | $97.17 | $165.00 | ||||
| 0029 | 54" reinforced concrete pipe culverts (class IV) (605633) | LF | 152 | $261.33 | $315.00 | ||||
| 0032 | 30" aluminum coated corrugated steel pipe culverts (16 gauge) (605707) | LF | 154 | $128.55 | $128.55 | $126.77 | $110.00 | ||
| 0033 | 54" aluminum coated corrugated steel pipe culverts (16 gauge) (605712) | LF | 158 | $215.88 | $215.88 | $236.77 | $240.00 | ||
| 0036 | 54" flared end sections for reinforced concrete pipe culverts (605868) | EACH | 4 | $3,885.56 | $4,800.00 | ||||
| 0037 | 54" flared end sections for corrugated steel pipe culverts (605869) | EACH | 4 | $4,550.00 | $4,550.00 | $4,580.20 | $3,700.00 | ||
| 0038 | 18" side drain (606703) | LF | 356 | $67.81 | $110.00 | $70.13 | $70.13 | $75.15 | $84.00 |
| 0039 | 24" side drain (606704) | LF | 88 | $89.08 | $155.00 | $89.07 | $89.07 | $83.95 | $88.00 |
| 0040 | 30" side drain (606705) | LF | 74 | $106.51 | $180.00 | $107.28 | $107.28 | $102.14 | $104.00 |
| 0041 | 48" side drain (606708) | LF | 92 | $127.49 | $240.00 | $224.32 | $224.32 | $182.76 | $197.00 |
| 0042 | Selected pipe bedding (606994) | CY | 78 | $47.94 | $52.00 | $25.00 | $25.00 | $1.82 | $28.00 |
| 0043 | Wire fence (type C) (619027) | LF | 340 | $8.25 | $8.25 | $7.00 | $7.00 | $8.25 | $9.00 |
| 0044 | Wire fence (type D-1) (619029) | LF | 1,755 | $6.00 | $6.00 | $7.00 | $7.00 | $6.00 | $6.75 |
| 0045 | 18' steel gates (619333) | EACH | 4 | $750.00 | $750.00 | $750.00 | $750.00 | $750.00 | $825.00 |
| 0047 | Lime (620001) | TON | 21 | $100.00 | $100.00 | $100.00 | $100.00 | $100.00 | $105.00 |
| 0048 | Seeding (620011) | ACRE | 10.30 | $1,375.00 | $1,375.00 | $1,375.00 | $1,375.00 | $1,375.00 | $1,400.00 |
| 0049 | Mulch cover (620022) | ACRE | 20.65 | $1,025.00 | $1,025.00 | $1,025.00 | $1,025.00 | $1,025.00 | $1,035.00 |
| 0050 | Water (620030) | MGAL | 1,276.90 | $5.00 | $5.00 | $5.00 | $5.00 | $5.00 | $5.75 |
| 0051 | Temporary seeding (621001) | ACRE | 10.35 | $675.00 | $675.00 | $675.00 | $675.00 | $675.00 | $675.00 |
| 0052 | Silt fence (621021) | LF | 7,730 | $3.00 | $3.00 | $3.00 | $3.00 | $3.00 | $3.20 |
| 0053 | Sand bag ditch checks (621031) | BAG | 1,804 | $9.00 | $9.00 | $9.00 | $9.00 | $9.00 | $12.00 |
| 0054 | Diversion ditch (621041) | LF | 1,000 | $20.67 | $1.10 | $2.00 | $1.00 | $4.13 | $0.50 |
| 0055 | Sediment basin (621071) | CY | 1,800 | $16.62 | $1.83 | $3.00 | $1.00 | $1.27 | $5.00 |
| 0056 | Obliteration of sediment basin (621101) | CY | 1,800 | $11.56 | $1.83 | $3.00 | $1.00 | $0.90 | $5.00 |
| 0057 | Sediment removal and disposal (621111) | CY | 3,567.80 | $3.10 | $1.54 | $3.00 | $0.50 | $1.29 | $5.00 |
| 0058 | Pipe for slope drains (621131) | LF | 250 | $62.20 | $8.00 | $20.00 | $2.00 | $29.97 | $35.00 |
| 0059 | Rock ditch checks (621151) | CY | 57 | $94.71 | $135.00 | $100.00 | $100.00 | $84.48 | $88.00 |
| 0060 | Filter sock (18") (621169) | LF | 6,315 | $11.50 | $11.50 | $11.50 | $11.50 | $11.50 | $11.85 |
| 0061 | Solid sodding (624001) | SY | 1,222 | $5.00 | $5.00 | $5.00 | $5.00 | $5.00 | $5.75 |
| 0062 | Roadway construction control (635001) | LS | 1 | $45,000 | $50,000 | $80,000 | $90,000 | $147,824 | $48,500 |
| 0063 | Reflectorized paint pavement marking white (4") (718001) | LF | 10,700 | $0.15 | $0.15 | $0.30 | $0.29 | $0.30 | $0.16 |
| 0064 | Reflectorized paint pavement marking yellow (4") (718101) | LF | 10,700 | $0.15 | $0.15 | $0.30 | $0.29 | $0.30 | $0.16 |
| 0065 | Standard sign (726002) | SF | 60 | $20.00 | $20.00 | $23.00 | $50.00 | $20.00 | $34.00 |
| 0066 | Channel post sign support (type A) (729001) | EACH | 7 | $90.00 | $90.00 | $100.00 | $200.00 | $90.00 | $100.00 |
| 0067 | Channel post sign support (type C) (729003) | EACH | 4 | $85.00 | $85.00 | $80.00 | $100.00 | $85.00 | $95.00 |
| 0068 | Unclassified excavation for structures-roadway (801101) | CY | 141 | $104.57 | $85.00 | $150.00 | $150.00 | $86.05 | $58.00 |
| 0069 | Class S concrete-roadway (802012) | CY | 303.04 | $1,352.66 | $1,465.00 | $1,425.00 | $1,425.00 | $1,346.28 | $2,275.00 |
| 0070 | Reinforcing steel-roadway (grade 60) (804003) | LB | 43,414 | $4.30 | $2.20 | $2.10 | $2.10 | $2.50 | $1.95 |
| 0071 | Filter blanket (816003) | SY | 786 | $5.90 | $4.05 | $15.00 | $15.00 | $7.23 | $3.20 |
| 0072 | Dumped riprap (816111) | CY | 491 | $93.36 | $85.00 | $100.00 | $100.00 | $76.23 | $104.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ARDOT's tabulation for this contract. ARDOT monthly bid tab PDFs (morning and afternoon sessions), January 2022 to November 2026. Base bids are printed in whole dollars; on A+B and A+C jobs the base bid is kept, and the published rank follows the award amount.
Every contract let that day: ARDOT letting of January 21, 2026. Compiled by Mirage Metrics.