ARDOT contract C10008 bid tabulation

THE PURPOSE OF THIS PROJECT IS TO OVERLAY AND SURFACE APPROXIMATELY 1.06 MILES OF VARIOUS CITY STREETS IN THE CITY OF GUM SPRINGS, OVERLAY APPROXIMATELY 1.04 MILES OF VARIOUS CITY STREETS IN THE CITY OF GURDON, AND OVERLAY AND SURFACE APPROXIMATELY 0.36 MILE OF VARIOUS CITY STREETS IN THE CITY OF WHELEN SPRINGS IN CLARK COUNTY. THIS PROJECT CONSISTS OF TRENCHING AND SHOULDER PREPARATION, AGGREGATE BASE COURSE, ACHM BINDER AND SURFACE COURSES, COLD MILLING ASPHALT PAVEMENT, ACHM PATCHING OF EXISTING ROADWAY, MAINTENANCE OF TRAFFIC AND MISC. ITEMS. Let by Arkansas DOT on January 21, 2026, Clark. 4 bids received; low bid $813,515 by Salt Creek Paving & Const. Co., Inc..

Owner
Arkansas DOT
Letting
21 JAN 2026
Pay items
17
Data through
04 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Salt Creek Paving & Const. Co., Inc.$813,515Low
2Redstone Construction Group, Inc.$832,258+2.0%
3Cranford Construction Co.$1,180,933+45%
4Kesser International, Inc.$1,300,716+60%
ARDOT contract C10008: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Salt Creek Paving & Const. Co., Inc.2. Redstone Construction Group, Inc.3. Cranford Construction Co.4. Kesser International, Inc.
0001Removal and disposal of curb and gutter (202003)LF80$20.00$54.66$64.69$94.98
0002Removal and disposal of pipe culverts (202096)EACH2$400.00$2,458.69$2,611.10$3,561.60
0004Scarifying and recompacting roadway (216201)STA18$500.00$549.01$1,094.61$1,484.00
0005Aggregate base course (class 7) (303107)TON2,847$56.43$58.50$137.95$93.20
0006Tack coat (401011)GAL2,366$3.57$3.50$3.97$7.12
0007Mineral aggregate in achm binder course (1") (406161)TON100$153.00$195.00$167.37$219.63
0008Asphalt binder (PG 64-22) in achm binder course (1") (minimum bid $120.00) (406402)TON5$153.00$120.00$167.37$219.63
0009Mineral aggregate in achm surface course (3/8") (407161)TON2,827$160.50$147.25$161.21$225.57
0010Asphalt binder (PG 64-22) in achm surface course (3/8") (minimum bid $120.00) (407431)TON196$160.50$120.00$161.22$225.57
0011Cold milling asphalt pavement (412001)SY3,004$6.20$4.68$3.99$18.40
0012Achm patching of existing roadway (415011)TON360$232.00$235.86$308.36$314.61
0013Maintenance of traffic (603009)LS1$1,000.00$21,400$81,732$35,616
0014Signs (604003)SF384$6.80$10.00$8.00$11.87
001518" reinforced concrete pipe culverts (class III) (605601)LF24$80.00$223.20$285.47$569.86
001612" side drain (606701)LF20$50.00$124.47$322.28$135.34
0017Concrete combination curb and gutter (type A) (1' 6") (634201)LF80$100.00$110.06$110.50$192.92
0018Mobilization (unit bid amount may not exceed 5% of subtotal) (601001)LS1$15,080$37,500$13,845$31,613
ARDOT contract C10008: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from ARDOT's tabulation for this contract. ARDOT monthly bid tab PDFs (morning and afternoon sessions), January 2022 to November 2026. Base bids are printed in whole dollars; on A+B and A+C jobs the base bid is kept, and the published rank follows the award amount.

Every contract let that day: ARDOT letting of January 21, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy