ARDOT contract FA5310 bid tabulation

THE PURPOSE OF THIS PROJECT IS TO SURFACE APPROXIMATELY 5.28 MILES OF UNION VALLEY RD. IN PERRY COUNTY. THIS PROJECT CONSISTS OF AGGREGATE BASE COURSE, AGGREGATE SURFACE COURSE, RECONSTRUCTED BASE COURSE, ACHM SURFACE COURSE, MAINTENANCE OF TRAFFIC, PAVEMENT MARKING, AND MISC. ITEMS. Let by Arkansas DOT on May 20, 2026, Perry. 3 bids received; low bid $1,785,414 by Blackstone Construction, LLC.

Owner
Arkansas DOT
Letting
20 MAY 2026
Pay items
12
Data through
04 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Blackstone Construction, LLC$1,785,414Low
2Redstone Construction Group, Inc.$1,847,093+3.0%
3Rogers Group, Inc.$1,910,014+7.0%
ARDOT contract FA5310: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Blackstone Construction, LLC2. Redstone Construction Group, Inc.3. Rogers Group, Inc.
0001Aggregate base course (class 7) (303117)TON4,193$53.20$45.00$45.00
0002Aggregate surface course (class D-8) (303308)TON2,274$39.39$45.00$55.00
0003Reconstructed base course (305001)STA279$384.00$725.00$550.00
0004Mineral aggregate in achm surface course (1/2") (407162)TON10,041$111.96$114.25$64.00
0005Asphalt binder (PG 64-22) in achm surface course (1/2") (minimum bid $120.00) (407432)TON675$120.00$120.00$800.00
0006Maintenance of traffic (603009)LS1$15,000$45,011$102,000
0007Signs (604003)SF152$8.00$6.15$30.00
0008Traffic drums (604023)EACH50$50.00$45.00$60.00
0009Roadway construction control (635001)LS1$40,000$25,250$35,000
0010Reflectorized paint pavement marking white (4") (718001)LF55,706$0.15$0.14$0.23
0011Reflectorized paint pavement marking yellow (4") (718101)LF55,706$0.15$0.14$0.23
0012Mobilization (unit bid amount may not exceed 5% of subtotal) (601001)LS1$85,020$36,575$90,000
ARDOT contract FA5310: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from ARDOT's tabulation for this contract. ARDOT monthly bid tab PDFs (morning and afternoon sessions), January 2022 to November 2026. Base bids are printed in whole dollars; on A+B and A+C jobs the base bid is kept, and the published rank follows the award amount.

Every contract let that day: ARDOT letting of May 20, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy