ARDOT contract A20044 bid tabulation
THE PURPOSE OF THIS PROJECT IS TO OVERLAY APPROXIMATELY 23.707 MILES OF HIGHWAY 130 IN ARKANSAS COUNTY. THIS PROJECT CONSISTS OF REMOVAL AND DISPOSAL OF GUARDRAIL, TRENCHING AND SHOULDER PREPARATION, AGGREGATE BASE COURSE, ACHM BINDER AND SURFACE COURSES, COLD MILLING ASPHALT PAVEMENT, ACHM PATCHING OF EXISTING ROADWAY, APPROACH GUTTERS, MAINTENANCE OF TRAFFIC, GUARDRAIL, EROSION CONTROL, RUMBLE STRIPES, PAVEMENT MARKING, AND MISC. ITEMS. Let by Arkansas DOT on November 4, 2026, Arkansas. 4 bids received; low bid $8,699,968 by Pine Bluff Sand & Gravel Co..
- Owner
- Arkansas DOT
- Letting
- 04 NOV 2026
- Pay items
- 42
- Data through
- 04 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Pine Bluff Sand & Gravel Co. | $8,699,968 | Low |
| 2 | Atlas Asphalt, Inc. | $9,297,763 | +7.0% |
| 3 | Rogers Group, Inc. | $9,665,352 | +11% |
| 4 | Redstone Construction Group, Inc. | $11,389,557 | +31% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Pine Bluff Sand & Gravel Co. | 2. Atlas Asphalt, Inc. | 3. Rogers Group, Inc. | 4. Redstone Construction Group, Inc. |
|---|---|---|---|---|---|---|---|
| 0001 | Removal and disposal of guardrail (202132) | LF | 1,866 | $10.00 | $12.00 | $10.50 | $11.00 |
| 0002 | Trenching and shoulder preparation (215011) | STA | 1,196 | $85.00 | $36.97 | $85.00 | $230.00 |
| 0003 | Aggregate base course (class 7) (303117) | TON | 9,472 | $50.65 | $66.41 | $60.00 | $66.00 |
| 0004 | Tack coat (401011) | GAL | 33,076 | $4.30 | $3.75 | $1.00 | $4.50 |
| 0005 | Mineral aggregate in achm binder course (1") (406161) | TON | 12,090 | $103.67 | $114.78 | $80.00 | $148.00 |
| 0006 | Asphalt binder (PG 70-22) in achm binder course (1") (minimum bid $120.00) (406412) | TON | 610 | $120.00 | $120.00 | $700.00 | $120.00 |
| 0007 | Mineral aggregate in achm surface course (1/2") (407162) | TON | 41,909 | $109.97 | $122.18 | $80.00 | $136.25 |
| 0008 | Asphalt binder (PG 70-22) in achm surface course (1/2") (minimum bid $120.00) (407442) | TON | 2,533 | $120.00 | $120.00 | $840.00 | $120.00 |
| 0009 | Cold milling asphalt pavement (412002) | SY | 8,446 | $16.00 | $2.16 | $6.00 | $33.00 |
| 0010 | Asphalt concrete patching for maintenance of traffic (414011) | TON | 625 | $150.00 | $100.00 | $190.00 | $200.00 |
| 0011 | Achm patching of existing roadway (415011) | TON | 800 | $200.00 | $125.00 | $190.00 | $325.00 |
| 0012 | Approach gutters (504264) | CY | 48.54 | $1,850.00 | $2,742.71 | $3,000.00 | $3,162.50 |
| 0013 | Maintenance of traffic (603009) | LS | 1 | $172,200 | $28,214 | $247,000 | $441,400 |
| 0014 | Signs (604003) | SF | 4,139 | $10.40 | $10.40 | $11.00 | $10.71 |
| 0015 | Construction project information sign update (604010) | EACH | 2 | $80.00 | $80.00 | $86.00 | $82.40 |
| 0016 | Traffic drums (604023) | EACH | 80 | $40.00 | $40.00 | $43.00 | $41.20 |
| 0017 | Construction pavement markings (604041) | LF | 413,168 | $0.24 | $0.24 | $0.26 | $0.25 |
| 0018 | Removable construction pavement markings (604051) | LF | 5,599 | $3.40 | $3.40 | $3.65 | $3.50 |
| 0019 | Vertical panels (604083) | EACH | 80 | $60.00 | $60.00 | $65.00 | $61.80 |
| 0020 | Guardrail (type A) (617005) | LF | 3,382 | $34.00 | $41.50 | $35.00 | $35.02 |
| 0021 | Guardrail terminal (type 2) (617312) | EACH | 26 | $3,300.00 | $3,975.00 | $3,418.00 | $3,399.00 |
| 0022 | Lime (620001) | TON | 23 | $125.00 | $5.00 | $130.00 | $125.00 |
| 0023 | Seeding (620011) | ACRE | 11.50 | $1,550.00 | $50.00 | $1,605.00 | $1,550.00 |
| 0024 | Mulch cover (620022) | ACRE | 23 | $1,250.00 | $25.00 | $1,300.00 | $1,250.00 |
| 0025 | Water (620030) | MGAL | 1,407.60 | $5.00 | $5.00 | $10.00 | $5.00 |
| 0026 | Temporary seeding (621001) | ACRE | 11.50 | $750.00 | $25.00 | $820.00 | $750.00 |
| 0027 | Silt fence (621021) | LF | 2,500 | $4.00 | $0.50 | $4.15 | $4.12 |
| 0028 | Sand bag ditch checks (621031) | BAG | 700 | $10.00 | $1.00 | $10.30 | $10.30 |
| 0029 | Sediment removal and disposal (621111) | CY | 93 | $25.00 | $1.00 | $107.00 | $21.52 |
| 0030 | Roadway construction control (635011) | LS | 1 | $7,500.00 | $7,098.05 | $26,000 | $32,100 |
| 0031 | Rumble stripes in asphalt shoulders (642011) | LF | 179,022 | $0.11 | $0.04 | $0.11 | $0.05 |
| 0032 | Centerline rumble stripes in asphalt roadways (642102) | LF | 111,888 | $0.11 | $0.06 | $0.11 | $0.06 |
| 0033 | Portable traffic signal system - actuated (701603) | WEEK | 21 | $960.00 | $2,820.55 | $1,030.00 | $1,200.00 |
| 0034 | Reflectorized paint pavement marking white (10") (718004) | LF | 130 | $1.60 | $1.60 | $1.75 | $1.65 |
| 0035 | Reflectorized paint pavement marking yellow (10") (718104) | LF | 202 | $1.60 | $1.60 | $1.75 | $1.65 |
| 0036 | Thermoplastic pavement marking white (6") (719002) | LF | 251,328 | $0.64 | $0.64 | $0.70 | $0.66 |
| 0037 | Thermoplastic pavement marking white (24") (719006) | LF | 110 | $16.00 | $16.00 | $17.00 | $16.48 |
| 0038 | Thermoplastic pavement marking yellow (6") (719102) | LF | 161,840 | $0.64 | $0.64 | $0.70 | $0.66 |
| 0039 | Raised pavement markers (type II) (721002) | EACH | 1,578 | $5.60 | $5.60 | $6.00 | $5.77 |
| 0040 | Bridge end terminal (734011) | EACH | 2 | $39,000 | $31,068 | $36,000 | $45,000 |
| 0041 | Reinforcing steel-roadway (grade 60) (804003) | LB | 3,306 | $2.00 | $5.32 | $2.85 | $3.50 |
| 0042 | Mobilization (unit bid amount may not exceed 5% of subtotal) (601001) | LS | 1 | $193,060 | $391,481 | $400,000 | $259,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ARDOT's tabulation for this contract. ARDOT monthly bid tab PDFs (morning and afternoon sessions), January 2022 to November 2026. Base bids are printed in whole dollars; on A+B and A+C jobs the base bid is kept, and the published rank follows the award amount.
Every contract let that day: ARDOT letting of November 4, 2026. Compiled by Mirage Metrics.