ARDOT contract C76087 bid tabulation

THE PURPOSE OF THIS PROJECT IS TO OVERLAY APPROXIMATELY 1.05 MILES OF VARIOUS CITY STREETS IN THE CITY OF DAMASCUS IN VAN BUREN COUNTY, APPROXIMATELY 2.38 MILES OF VARIOUS CITY STREETS IN THE CITY OF GUY IN FAULKNER COUNTY, AND APPROXIMATELY 2.02 MILES IN THE CITY OF ROSE BUD IN WHITE COUNTY. THIS PROJECT CONSISTS OF AGGREGATE SURFACE COURSE, RECONSTRUCTED BASE COURSE, ACHM SURFACE AND BINDER COURSES, ACHM PATCHING OF EXISTING ROADWAY, MAINTENANCE OF TRAFFIC, AND MISC. ITEMS. Let by Arkansas DOT on January 15, 2025, Faulkner, Van Buren, White. 2 bids received; low bid $764,580 by Rogers Group, Inc..

Owner
Arkansas DOT
Letting
15 JAN 2025
Pay items
15
Data through
04 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Rogers Group, Inc.$764,580Low
2CK Asphalt, LLC$884,585+16%
ARDOT contract C76087: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Rogers Group, Inc.2. CK Asphalt, LLC
0001Removal and disposal of pipe culverts (202096)EACH2$1,500.00$450.00
0002Trenching and shoulder preparation (215001)STA19$160.00$225.00
0003Aggregate surface course (class D-8) (303308)TON386$45.00$28.65
0004Reconstructed base course (305011)STA17$275.00$275.00
0005Tack coat (401011)GAL5,369$1.00$3.00
0006Mineral aggregate in achm binder course (1") (406161)TON254$75.00$89.62
0007Asphalt binder (PG 64-22) in achm binder course (1") (minimum bid $120.00) (406402)TON12$590.00$120.00
0008Mineral aggregate in achm surface course (3/8") (407161)TON5,940$55.00$28.00
0009Asphalt binder (PG 64-22) in achm surface course (3/8") (minimum bid $120.00) (407431)TON406$590.00$1,400.00
0010Cold milling asphalt pavement (412001)SY385$10.00$6.40
0011Achm patching of existing roadway (415011)TON225$170.00$155.00
0012Mobilization (unit bid amount may not exceed 5% of subtotal) (601001)LS1$34,000$32,000
0013Maintenance of traffic (603009)LS1$50,000$11,500
0014Signs (604003)SF600$12.00$8.00
001512" side drain (606701)LF62$88.00$48.50
ARDOT contract C76087: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from ARDOT's tabulation for this contract. ARDOT monthly bid tab PDFs (morning and afternoon sessions), January 2022 to November 2026. Base bids are printed in whole dollars; on A+B and A+C jobs the base bid is kept, and the published rank follows the award amount.

Every contract let that day: ARDOT letting of January 15, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy