ARDOT contract SA0449 bid tabulation

THE PURPOSE OF THIS PROJECT IS TO OVERLAY APPROXIMATELY 3.02 MILES OF W. MOUNTAIN RD. AND CARLTON DR. IN BENTON COUNTY. THIS PROJECT CONSISTS OF AGGREGATE BASE COURSE, ACHM SURFACE COURSE, COLD MILLING ASPHALT PAVEMENT, ACHM PATCHING OF EXISTING ROADWAY, MAINTENANCE OF TRAFFIC, PAVEMENT MARKING, AND MISC. ITEMS. Let by Arkansas DOT on May 20, 2026, Benton. 4 bids received; low bid $554,646 by Apac-Central, Inc..

Owner
Arkansas DOT
Letting
20 MAY 2026
Pay items
11
Data through
04 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Apac-Central, Inc.$554,646Low
2Emery Sapp & Sons, Inc.$593,113+7.0%
3Grant Garrett Excavating, Inc.$639,996+15%
4McKenzie Asphalt, LLC$758,611+37%
ARDOT contract SA0449: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Apac-Central, Inc.2. Emery Sapp & Sons, Inc.3. Grant Garrett Excavating, Inc.4. McKenzie Asphalt, LLC
0001Aggregate base course (class 7) (303117)TON479$21.00$33.03$55.48$47.95
0002Tack coat (401011)GAL4,342$3.70$3.40$2.80$3.00
0003Mineral aggregate in achm surface course (1/2") (407162)TON4,833$92.00$97.40$105.69$128.00
0004Asphalt binder (PG 64-22) in achm surface course (1/2") (minimum bid $120.00) (407432)TON309$120.00$120.00$120.00$120.00
0005Cold milling asphalt pavement (412002)SY609$18.00$8.25$5.26$10.68
0006Achm patching of existing roadway (415011)TON40$240.00$149.23$144.60$250.00
0007Maintenance of traffic (603009)LS1$2,500.00$9,387.87$11,315$8,500.00
0008Signs (604003)SF208$34.00$37.76$39.29$34.00
0009Reflectorized paint pavement marking white (4") (718001)LF32,208$0.22$0.24$0.25$0.22
0010Reflectorized paint pavement marking yellow (4") (718101)LF32,208$0.22$0.24$0.25$0.22
0011Mobilization (unit bid amount may not exceed 5% of subtotal) (601001)LS1$2,500.00$11,020$8,805.00$20,665
ARDOT contract SA0449: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from ARDOT's tabulation for this contract. ARDOT monthly bid tab PDFs (morning and afternoon sessions), January 2022 to November 2026. Base bids are printed in whole dollars; on A+B and A+C jobs the base bid is kept, and the published rank follows the award amount.

Every contract let that day: ARDOT letting of May 20, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy