ARDOT contract SA2550 bid tabulation

THE PURPOSE OF THIS PROJECT IS TO LEVEL AND RESEAL APPROXIMATELY 2.93 MILES ON HEART RD. IN FULTON COUNTY. THIS PROJECT CONSISTS OF ACHM SURFACE COURSE, SINGLE ASPHALT SURFACE TREATMENT, ACHM PATCHING, PAVEMENT MARKING, MAINTENANCE OF TRAFFIC AND MISC. ITEMS. Let by Arkansas DOT on March 4, 2026, Fulton. 2 bids received; low bid $101,997 by Apac-Central, Inc..

Owner
Arkansas DOT
Letting
04 MAR 2026
Pay items
12
Data through
04 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Apac-Central, Inc.$101,997Low
2Atlas Asphalt, Inc.$134,355+32%
ARDOT contract SA2550: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Apac-Central, Inc.2. Atlas Asphalt, Inc.
0001Tack coat (401011)GAL158$2.65$5.00
0002Mineral aggregate in asphalt surface treatment (class 2) (402112)TON606$22.50$62.60
0003Polymer modified cationic emulsified asphalt (CRS-2P) (solid polymer) (402214)GAL13,853$3.90$4.06
0004Mineral aggregate in achm surface course (3/8") (407161)TON98$115.00$177.89
0005Asphalt binder (PG 64-22) in achm surface course (3/8") (minimum bid $120.00) (407431)TON7$120.00$120.00
0006Achm patching of existing roadway (415011)TON20$108.00$150.00
0007Maintenance of traffic (603009)LS1$2,000.00$2,500.00
0008Signs (604003)SF224$10.00$6.00
0009Reflectorized paint pavement marking yellow (4") (718101)LF30,940$0.23$0.15
0010Standard sign (726002)SF96$20.00$22.00
0011Channel post sign support (type C) (729003)EACH22$85.00$80.00
0012Mobilization (unit bid amount may not exceed 5% of subtotal) (601001)LS1$4,500.00$5,755.61
ARDOT contract SA2550: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from ARDOT's tabulation for this contract. ARDOT monthly bid tab PDFs (morning and afternoon sessions), January 2022 to November 2026. Base bids are printed in whole dollars; on A+B and A+C jobs the base bid is kept, and the published rank follows the award amount.

Every contract let that day: ARDOT letting of March 4, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy