ARDOT contract SA4748 bid tabulation
THE PURPOSE OF THIS PROJECT IS TO LEVEL AND RESEAL APPROXIMATELY 4.43 MILES OF VARIOUS COUNTY ROADS IN MISSISSIPPI COUNTY. THIS PROJECT CONSISTS OF FOG SEAL, ACHM SURFACE COURSE, ACHM PATCHING OF EXISTING ROADWAY, MAINTENANCE OF TRAFFIC, PAVEMENT MARKING, AND MISC. ITEMS. Let by Arkansas DOT on April 9, 2025, Mississippi. 3 bids received; low bid $309,153 by Atlas Asphalt, Inc..
- Owner
- Arkansas DOT
- Letting
- 09 APR 2025
- Pay items
- 11
- Data through
- 04 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Atlas Asphalt, Inc. | $309,153 | Low |
| 2 | Sugg Construction, Inc. | $392,497 | +27% |
| 3 | Pavement Restorations, Inc. | $409,853 | +33% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Atlas Asphalt, Inc. | 2. Sugg Construction, Inc. | 3. Pavement Restorations, Inc. |
|---|---|---|---|---|---|---|
| 0001 | Fog seal (type 2) (401005) | GAL | 5,432 | $4.01 | $5.00 | $8.75 |
| 0002 | Tack coat (401011) | GAL | 491 | $5.00 | $2.80 | $6.00 |
| 0003 | Mineral aggregate in asphalt surface treatment (class 2) (402112) | TON | 951 | $104.39 | $100.00 | $72.95 |
| 0004 | Polymer modified cationic emulsified asphalt (CRS-2P) (solid polymer) (402204) | GAL | 21,726 | $4.37 | $7.25 | $5.85 |
| 0005 | Mineral aggregate in achm surface course (3/8") (407161) | TON | 308 | $175.00 | $176.10 | $310.00 |
| 0006 | Asphalt binder (PG 64-22) in achm surface course (3/8") (minimum bid $120.00) (407431) | TON | 19 | $120.00 | $120.00 | $126.00 |
| 0007 | Achm patching of existing roadway (415011) | TON | 40 | $175.00 | $275.00 | $468.00 |
| 0008 | Maintenance of traffic (603009) | LS | 1 | $10,000 | $21,000 | $23,000 |
| 0009 | Signs (604003) | SF | 344 | $5.00 | $5.00 | $15.00 |
| 0010 | Reflectorized paint pavement marking yellow (4") (718101) | LF | 47,002 | $0.13 | $0.13 | $0.15 |
| 0011 | Mobilization (unit bid amount may not exceed 5% of subtotal) (601001) | LS | 1 | $9,687.75 | $15,000 | $11,100 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ARDOT's tabulation for this contract. ARDOT monthly bid tab PDFs (morning and afternoon sessions), January 2022 to November 2026. Base bids are printed in whole dollars; on A+B and A+C jobs the base bid is kept, and the published rank follows the award amount.
Every contract let that day: ARDOT letting of April 9, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way