ARDOT contract SA5351 bid tabulation

THE PURPOSE OF THIS PROJECT IS TO SURFACE AND OVERLAY APPROXIMATELY 1.32 MILES OF COUNTY ROAD 45 AND SURFACE APPROXIMATELY 0.90 MILE OF COUNTY ROAD 70 IN PERRY COUNTY. THIS PROJECT CONSISTS OF AGGREGATE BASE COURSE, RECONSTRUCTED BASE COURSE, ACHM SURFACE COURSE, SCARIFYING AND RECOMPACTING ROADWAY, GUARDRAIL, MAINTENANCE OF TRAFFIC, PAVEMENT MARKING, AND MISC. ITEMS. Let by Arkansas DOT on January 15, 2025, Perry. 2 bids received; low bid $649,720 by Blackstone Construction, LLC.

Owner
Arkansas DOT
Letting
15 JAN 2025
Pay items
17
Data through
04 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Blackstone Construction, LLC$649,720Low
2Rogers Group, Inc.$669,534+3.0%
ARDOT contract SA5351: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Blackstone Construction, LLC2. Rogers Group, Inc.
0001Scarifying and recompacting roadway (216201)STA1$2,500.00$4,400.00
0002Aggregate base course (class 7) (303117)TON2,015$40.38$65.00
0003Reconstructed base course (305001)STA101$750.00$350.00
0004Prime coat (401001)GAL9,406$5.00$5.50
0005Tack coat (401011)GAL392$4.00$1.00
0006Mineral aggregate in achm surface course (1/2") (407162)TON2,887$117.81$69.00
0007Asphalt binder (PG 64-22) in achm surface course (1/2") (minimum bid $120.00) (407432)TON191$120.00$590.00
0008Maintenance of traffic (603009)LS1$20,000$75,000
0009Signs (604003)SF276$15.00$17.00
0010Guardrail (type A) (617001)LF100$35.00$40.00
0011Guardrail terminal (type I) (617311)EACH2$3,500.00$4,000.00
0012Reflectorized paint pavement marking yellow (4") (718101)LF23,443$0.25$0.29
0013Standard sign (726002)SF44.50$25.00$29.00
0014Channel post sign support (type A) (729001)EACH6$85.00$99.00
0015Channel post sign support (type C) (729003)EACH4$90.00$104.00
0016Achm patching of existing roadway (415011)TON40$150.00$225.00
0017Mobilization (unit bid amount may not exceed 5% of subtotal) (601001)LS1$29,986$25,000
ARDOT contract SA5351: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from ARDOT's tabulation for this contract. ARDOT monthly bid tab PDFs (morning and afternoon sessions), January 2022 to November 2026. Base bids are printed in whole dollars; on A+B and A+C jobs the base bid is kept, and the published rank follows the award amount.

Every contract let that day: ARDOT letting of January 15, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy