ARDOT contract SA7635 bid tabulation
THE PURPOSE OF THIS PROJECT IS TO OVERLAY APPROXIMATELY 0.48 MILE OF COUNTY ROAD 18 IN CLEVELAND AND LINCOLN COUNTIES. THIS PROJECT CONSISTS OF AGGREGATE BASE COURSE, ACHM SURFACE COURSE, ACHM PATCHING OF EXISTING ROADWAY, MAINTENANCE OF TRAFFIC, PAVEMENT MARKING, AND MISC. ITEMS. Let by Arkansas DOT on September 17, 2025, Cleveland, Lincoln. 3 bids received; low bid $129,153 by Pine Bluff Sand & Gravel Co..
- Owner
- Arkansas DOT
- Letting
- 17 SEP 2025
- Pay items
- 9
- Data through
- 04 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Pine Bluff Sand & Gravel Co. | $129,153 | Low |
| 2 | Salt Creek Paving & Const. Co., Inc. | $131,508 | +2.0% |
| 3 | Redstone Construction Group, Inc. | $144,268 | +12% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Pine Bluff Sand & Gravel Co. | 2. Salt Creek Paving & Const. Co., Inc. | 3. Redstone Construction Group, Inc. |
|---|---|---|---|---|---|---|
| 0001 | Aggregate base course (class 7) (303117) | TON | 76 | $120.00 | $116.00 | $126.92 |
| 0002 | Tack coat (401011) | GAL | 605 | $7.00 | $3.75 | $4.94 |
| 0003 | Mineral aggregate in achm surface course (1/2") (407162) | TON | 658 | $88.83 | $149.60 | $150.85 |
| 0004 | Asphalt binder (PG 64-22) in achm surface course (1/2") (minimum bid $120.00) (407432) | TON | 42 | $650.00 | $149.60 | $120.00 |
| 0005 | Achm patching of existing roadway (415011) | TON | 30 | $200.00 | $200.00 | $335.37 |
| 0006 | Maintenance of traffic (603009) | LS | 1 | $8,500.00 | $2,500.00 | $7,660.43 |
| 0007 | Signs (604003) | SF | 96 | $55.00 | $13.75 | $13.20 |
| 0008 | Reflectorized paint pavement marking yellow (4") (718101) | LF | 5,068 | $1.00 | $0.42 | $0.66 |
| 0009 | Mobilization (unit bid amount may not exceed 5% of subtotal) (601001) | LS | 1 | $5,200.00 | $3,755.00 | $5,000.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ARDOT's tabulation for this contract. ARDOT monthly bid tab PDFs (morning and afternoon sessions), January 2022 to November 2026. Base bids are printed in whole dollars; on A+B and A+C jobs the base bid is kept, and the published rank follows the award amount.
Every contract let that day: ARDOT letting of September 17, 2025. Compiled by Mirage Metrics.