CDOT contract C26874 bid tabulation
REGION 3 STENCIL PROJECT ON HIGHWAYS 40, 394,13. This Project will consist of refreshing existing crosswalks, stop bars and pavement markings with inlaid preformed thermoplastic material on the following Highways: 040A 130.29, 394A . 24-.71, 013A 0 - 64.16. Project Engineer: Kaleb Baugh 970-683-7530. Let by Colorado DOT on July 3, 2025, Region 3. 2 bids received; low bid $448,563 by Roadsafe Traffic Systems, Inc, -10% against the engineer's estimate of $499,196.
- Owner
- Colorado DOT
- Letting
- 03 JUL 2025
- Pay items
- 10
- Data through
- 10 SEP 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Roadsafe Traffic Systems, Inc | $448,563 | Low | -10% |
| 2 | Branson Traffic Control Company, Inc | $458,738 | +2.0% | -8.0% |
Engineer's estimate: $499,196.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Roadsafe Traffic Systems, Inc | 2. Branson Traffic Control Company, Inc |
|---|---|---|---|---|---|---|
| 1 | Removal of pavement marking (202-00250) | SF | 27,454.80 | $2.00 | $1.75 | $2.00 |
| 2 | Mobilization (626-00000) | LS | 1 | $35,000 | $25,000 | $20,000 |
| 3 | Preformed thermoplastic pavement marking (word-symbol) (special) (627-30407) | SF | 7,123.40 | $16.50 | $16.75 | $17.25 |
| 4 | Preformed thermoplastic pavement marking (xwalk-stop line) (special) (627-30411) | SF | 19,900 | $13.00 | $12.25 | $12.50 |
| 5 | Flagging (630-00000) | HR | 300 | $14.00 | $13.00 | $5.00 |
| 6 | Traffic control management (630-00012) | DAY | 45 | $500.00 | $125.00 | $200.00 |
| 7 | Construction traffic sign (panel size A) (630-80341) | EACH | 21 | $50.00 | $25.00 | $25.00 |
| 8 | Construction traffic sign (panel size B) (630-80342) | EACH | 15 | $60.00 | $25.00 | $25.00 |
| 9 | Advance warning flashing or sequencing arrow panel (C type) (630-80358) | EACH | 2 | $1,200.00 | $500.00 | $300.00 |
| 10 | Traffic cone (630-80380) | EACH | 200 | $10.00 | $5.00 | $1.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from CDOT's tabulation for this contract. CDOT Tabulation of Bids PDFs from its bid tab archive, May 2023 to September 2026 (each contract linked to its OnBase document), and four December 2025 lettings read by OCR. About 100 tabulations of late 2025 and 2026 are printed in a font without text and are not read yet. On A+B contracts the cost part is kept. Bids that did not match their published total are left out.
Every contract let that day: CDOT letting of July 3, 2025. Compiled by Mirage Metrics.