CDOT contract C27057 bid tabulation

CO 60 (MP 9-10). Let by Colorado DOT on June 18, 2025, Region 4. 2 bids received; low bid $488,198 by Connell Resources Incorporated, +10% against the engineer's estimate of $442,734.

Owner
Colorado DOT
Letting
18 JUN 2025
Pay items
20
Data through
10 SEP 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Connell Resources Incorporated$488,198Low+10%
2Kraemer North America, LLC$810,845+66%+83%
CDOT contract C27057: bids by rank

Engineer's estimate: $442,734.

Bid tabulation

LinePay itemUnitQuantityEstimate1. Connell Resources Incorporated2. Kraemer North America, LLC
1Removal of pipe (202-00035)LF350$38.52$22.70$70.00
2Removal of asphalt mat (202-00220)SY1,750$25.00$13.50$18.00
3Unclassified excavation (203-00000)CY555$90.00$43.00$85.00
4Embankment material (complete in place) (203-00060)CY117$99.60$60.00$250.00
5Structure backfill (flow-fill) (206-00065)CY123$110.00$205.00$300.00
6Structure backfill (class 1) (206-00100)CY123$94.26$67.00$125.00
7Aggregate base course (class 6) (304-06007)CY292$99.54$78.50$110.00
8Hot mix asphalt (grading SX) (75) (PG 76- 28) (403-34771)TON784$190.00$170.00$275.00
918 inch plastic pipe (603-50018)LF310$175.00$132.00$240.00
1018 inch culvert siphon pipe (616-29180)LF40$85.00$183.00$240.00
1124 inch welded steel pipe (jacked) (619-10247)LF20$316.80$4,540.00$6,500.00
12Mobilization (626-00000)LS1$26,000$72,500$141,000
13Modified epoxy pavement marking (627-00008)GAL10$697.12$550.00$250.00
14Flagging (630-00000)HR150$40.65$50.00$45.00
15Traffic control management (630-00012)DAY7$538.27$1,100.00$850.00
16Barricade (type 3 M-A) (temporary) (630-80335)EACH3$113.25$60.00$75.00
17Construction traffic sign (panel size A) (630-80341)EACH45$49.30$17.00$50.00
18Vertical panel (630-80350)EACH20$33.31$17.00$25.00
19Portable message sign panel (630-80355)EACH2$5,117.37$1,130.00$2,000.00
20Traffic cone (630-80380)EACH50$9.35$6.00$25.00
CDOT contract C27057: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from CDOT's tabulation for this contract. CDOT Tabulation of Bids PDFs from its bid tab archive, May 2023 to September 2026 (each contract linked to its OnBase document), and four December 2025 lettings read by OCR. About 100 tabulations of late 2025 and 2026 are printed in a font without text and are not read yet. On A+B contracts the cost part is kept. Bids that did not match their published total are left out.

Every contract let that day: CDOT letting of June 18, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy