CDOT contract C27057 bid tabulation
CO 60 (MP 9-10). Let by Colorado DOT on June 18, 2025, Region 4. 2 bids received; low bid $488,198 by Connell Resources Incorporated, +10% against the engineer's estimate of $442,734.
- Owner
- Colorado DOT
- Letting
- 18 JUN 2025
- Pay items
- 20
- Data through
- 10 SEP 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Connell Resources Incorporated | $488,198 | Low | +10% |
| 2 | Kraemer North America, LLC | $810,845 | +66% | +83% |
Engineer's estimate: $442,734.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Connell Resources Incorporated | 2. Kraemer North America, LLC |
|---|---|---|---|---|---|---|
| 1 | Removal of pipe (202-00035) | LF | 350 | $38.52 | $22.70 | $70.00 |
| 2 | Removal of asphalt mat (202-00220) | SY | 1,750 | $25.00 | $13.50 | $18.00 |
| 3 | Unclassified excavation (203-00000) | CY | 555 | $90.00 | $43.00 | $85.00 |
| 4 | Embankment material (complete in place) (203-00060) | CY | 117 | $99.60 | $60.00 | $250.00 |
| 5 | Structure backfill (flow-fill) (206-00065) | CY | 123 | $110.00 | $205.00 | $300.00 |
| 6 | Structure backfill (class 1) (206-00100) | CY | 123 | $94.26 | $67.00 | $125.00 |
| 7 | Aggregate base course (class 6) (304-06007) | CY | 292 | $99.54 | $78.50 | $110.00 |
| 8 | Hot mix asphalt (grading SX) (75) (PG 76- 28) (403-34771) | TON | 784 | $190.00 | $170.00 | $275.00 |
| 9 | 18 inch plastic pipe (603-50018) | LF | 310 | $175.00 | $132.00 | $240.00 |
| 10 | 18 inch culvert siphon pipe (616-29180) | LF | 40 | $85.00 | $183.00 | $240.00 |
| 11 | 24 inch welded steel pipe (jacked) (619-10247) | LF | 20 | $316.80 | $4,540.00 | $6,500.00 |
| 12 | Mobilization (626-00000) | LS | 1 | $26,000 | $72,500 | $141,000 |
| 13 | Modified epoxy pavement marking (627-00008) | GAL | 10 | $697.12 | $550.00 | $250.00 |
| 14 | Flagging (630-00000) | HR | 150 | $40.65 | $50.00 | $45.00 |
| 15 | Traffic control management (630-00012) | DAY | 7 | $538.27 | $1,100.00 | $850.00 |
| 16 | Barricade (type 3 M-A) (temporary) (630-80335) | EACH | 3 | $113.25 | $60.00 | $75.00 |
| 17 | Construction traffic sign (panel size A) (630-80341) | EACH | 45 | $49.30 | $17.00 | $50.00 |
| 18 | Vertical panel (630-80350) | EACH | 20 | $33.31 | $17.00 | $25.00 |
| 19 | Portable message sign panel (630-80355) | EACH | 2 | $5,117.37 | $1,130.00 | $2,000.00 |
| 20 | Traffic cone (630-80380) | EACH | 50 | $9.35 | $6.00 | $25.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from CDOT's tabulation for this contract. CDOT Tabulation of Bids PDFs from its bid tab archive, May 2023 to September 2026 (each contract linked to its OnBase document), and four December 2025 lettings read by OCR. About 100 tabulations of late 2025 and 2026 are printed in a font without text and are not read yet. On A+B contracts the cost part is kept. Bids that did not match their published total are left out.
Every contract let that day: CDOT letting of June 18, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.