CDOT contract C27376A bid tabulation
Repairs to structure F-16-YE (Southbound Santa Fe to Eastbound C470 Flyover -The scope of work will include the installation of a temporary support system (e.g. falsework tower or corbels) and working platform at Pier 7 to support all four girders that are supported by the pier and provide a working. Let by Colorado DOT on January 30, 2026, Region 1. 3 bids received; low bid $1,251,000 by Ames Construction Incorporated, +20% against the engineer's estimate of $1,039,023.
- Owner
- Colorado DOT
- Letting
- 30 JAN 2026
- Pay items
- 14
- Data through
- 10 SEP 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Ames Construction Incorporated | $1,251,000 | Low | +20% |
| 2 | Kraemer North America, LLC | $2,787,950 | +123% | +168% |
| 3 | Kiewit Infrastructure Co. | $5,119,102 | +309% | +393% |
Engineer's estimate: $1,039,023.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Ames Construction Incorporated | 2. Kraemer North America, LLC | 3. Kiewit Infrastructure Co. |
|---|---|---|---|---|---|---|---|
| 1 | Removal of structure (202-00001) | EACH | 1 | $4,803.71 | $5,300.00 | $20,000 | $27,770 |
| 2 | Removal of guardrail type 3 (202-01130) | LF | 50 | $14.01 | $65.00 | $55.00 | $200.58 |
| 3 | Removal of guardrail type 9 (202-01190) | LF | 50 | $100.00 | $210.00 | $125.00 | $656.37 |
| 4 | Potholing (203-01597) | HR | 10 | $353.88 | $750.00 | $500.00 | $922.28 |
| 5 | Provide temporary support (509-08100) | LS | 1 | $500,000 | $840,000 | $2,100,000 | $3,896,364 |
| 6 | Sanitary facility (620-00020) | EACH | 1 | $2,669.75 | $500.00 | $1,200.00 | $1,500.00 |
| 7 | Mobilization (626-00000) | LS | 1 | $82,445 | $124,375 | $324,000 | $475,000 |
| 8 | Public information services (tier III) (626-01103) | LS | 1 | $100,000 | $12,000 | $5,000.00 | $23,544 |
| 9 | Uniformed traffic control (630-00003) | HR | 150 | $154.97 | $185.00 | $150.00 | $267.00 |
| 10 | Traffic control inspection (630-00007) | DAY | 5 | $123.73 | $185.00 | $250.00 | $355.00 |
| 11 | Traffic control management (630-00012) | DAY | 30 | $1,200.00 | $2,400.00 | $1,300.00 | $3,700.00 |
| 12 | Traffic control (special) LS (630-00016) | LS | 1 | $60,000 | $113,200 | $200,000 | $400,000 |
| 13 | Portable message sign panel (630-80355) | EACH | 6 | $20,000 | $2,200.00 | $8,500.00 | $8,720.00 |
| 14 | Night work lighting (632-00000) | LS | 1 | $100,000 | $20,500 | $10,000 | $37,708 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from CDOT's tabulation for this contract. CDOT Tabulation of Bids PDFs from its bid tab archive, May 2023 to September 2026 (each contract linked to its OnBase document), and four December 2025 lettings read by OCR. About 100 tabulations of late 2025 and 2026 are printed in a font without text and are not read yet. On A+B contracts the cost part is kept. Bids that did not match their published total are left out.
Every contract let that day: CDOT letting of January 30, 2026. Compiled by Mirage Metrics.