CDOT contract C27376A bid tabulation

Repairs to structure F-16-YE (Southbound Santa Fe to Eastbound C470 Flyover -The scope of work will include the installation of a temporary support system (e.g. falsework tower or corbels) and working platform at Pier 7 to support all four girders that are supported by the pier and provide a working. Let by Colorado DOT on January 30, 2026, Region 1. 3 bids received; low bid $1,251,000 by Ames Construction Incorporated, +20% against the engineer's estimate of $1,039,023.

Owner
Colorado DOT
Letting
30 JAN 2026
Pay items
14
Data through
10 SEP 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Ames Construction Incorporated$1,251,000Low+20%
2Kraemer North America, LLC$2,787,950+123%+168%
3Kiewit Infrastructure Co.$5,119,102+309%+393%
CDOT contract C27376A: bids by rank

Engineer's estimate: $1,039,023.

Bid tabulation

LinePay itemUnitQuantityEstimate1. Ames Construction Incorporated2. Kraemer North America, LLC3. Kiewit Infrastructure Co.
1Removal of structure (202-00001)EACH1$4,803.71$5,300.00$20,000$27,770
2Removal of guardrail type 3 (202-01130)LF50$14.01$65.00$55.00$200.58
3Removal of guardrail type 9 (202-01190)LF50$100.00$210.00$125.00$656.37
4Potholing (203-01597)HR10$353.88$750.00$500.00$922.28
5Provide temporary support (509-08100)LS1$500,000$840,000$2,100,000$3,896,364
6Sanitary facility (620-00020)EACH1$2,669.75$500.00$1,200.00$1,500.00
7Mobilization (626-00000)LS1$82,445$124,375$324,000$475,000
8Public information services (tier III) (626-01103)LS1$100,000$12,000$5,000.00$23,544
9Uniformed traffic control (630-00003)HR150$154.97$185.00$150.00$267.00
10Traffic control inspection (630-00007)DAY5$123.73$185.00$250.00$355.00
11Traffic control management (630-00012)DAY30$1,200.00$2,400.00$1,300.00$3,700.00
12Traffic control (special) LS (630-00016)LS1$60,000$113,200$200,000$400,000
13Portable message sign panel (630-80355)EACH6$20,000$2,200.00$8,500.00$8,720.00
14Night work lighting (632-00000)LS1$100,000$20,500$10,000$37,708
CDOT contract C27376A: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from CDOT's tabulation for this contract. CDOT Tabulation of Bids PDFs from its bid tab archive, May 2023 to September 2026 (each contract linked to its OnBase document), and four December 2025 lettings read by OCR. About 100 tabulations of late 2025 and 2026 are printed in a font without text and are not read yet. On A+B contracts the cost part is kept. Bids that did not match their published total are left out.

Every contract let that day: CDOT letting of January 30, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy