CDOT contract C27393 bid tabulation
Permanent repairs to structure F-16-YE (Southbound Santa Fe to Eastbound C470 Flyover ) Site Number: 00 Days Road User Cost Per Time Unit: $ 6200. Let by Colorado DOT on February 11, 2026, Region 1. 3 bids received; low bid $1,251,000 by Ames Construction Incorporated, -40% against the engineer's estimate of $2,088,581.
- Owner
- Colorado DOT
- Letting
- 11 FEB 2026
- Pay items
- 27
- Data through
- 10 SEP 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Ames Construction Incorporated | $1,251,000 | Low | -40% |
| 2 | Kraemer North America, LLC | $1,849,215 | +48% | -11% |
| 3 | Kiewit Infrastructure Co. | $2,845,303 | +127% | +36% |
Engineer's estimate: $2,088,581.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Ames Construction Incorporated | 2. Kraemer North America, LLC | 3. Kiewit Infrastructure Co. |
|---|---|---|---|---|---|---|---|
| 1 | Removal of portions of present structure (202-00495) | LS | 1 | $700,000 | $255,000 | $500,000 | $377,706 |
| 2 | Potholing (203-01597) | HR | 10 | $353.88 | $400.00 | $500.00 | $922.28 |
| 3 | Reset fence (210-01000) | LF | 20 | $59.96 | $235.00 | $100.00 | $245.25 |
| 4 | Wildlife biologist (240-00000) | HR | 40 | $196.75 | $220.00 | $200.00 | $190.75 |
| 5 | Removal of nests (240-00010) | HR | 40 | $300.00 | $220.00 | $200.00 | $160.00 |
| 6 | Hot mix asphalt (patching) (asphalt) (403-00720) | TON | 20 | $468.07 | $435.00 | $400.00 | $436.00 |
| 7 | Temporary bridge deck (509-08120) | SF | 120 | $1,200.00 | $175.00 | $400.00 | $1,400.00 |
| 8 | Bearing device (type III) (512-00103) | EACH | 4 | $10,301 | $18,000 | $45,000 | $33,900 |
| 9 | Bridge drain (special) (install only) (513-00691) | EACH | 1 | $2,000.00 | $4,260.00 | $15,000 | $37,619 |
| 10 | Bridge expansion device (0-4 inch) (518-01004) | LF | 60 | $580.73 | $510.00 | $1,800.00 | $1,881.05 |
| 11 | Concrete class DF (601-03056) | CY | 19 | $2,208.86 | $2,960.00 | $7,500.00 | $5,858.37 |
| 12 | Concrete class S35 (601-05035) | CY | 37 | $3,000.00 | $2,825.00 | $7,500.00 | $9,669.36 |
| 13 | Structural concrete coating (601-40300) | SY | 67 | $34.24 | $140.00 | $22.00 | $13.08 |
| 14 | Reinforcing steel (epoxy coated) (602-00020) | LB | 17,728 | $3.21 | $3.00 | $3.25 | $1.99 |
| 15 | Guardrail type 3 (31 inch midwest guardrail system) (606-00302) | LF | 50 | $68.07 | $108.00 | $100.00 | $708.50 |
| 16 | Guardrail type 9 (style CA) (606-00910) | LF | 50 | $500.00 | $305.00 | $750.00 | $933.01 |
| 17 | Bridge rail type 7 (special) (606-10705) | LF | 8 | $563.06 | $2,100.00 | $1,000.00 | $4,331.87 |
| 18 | Prestressing steel bar (618-00000) | LB | 3,525 | $40.00 | $33.00 | $15.00 | $30.28 |
| 19 | Sanitary facility (620-00020) | EACH | 1 | $2,669.75 | $1,000.00 | $2,000.00 | $1,500.00 |
| 20 | Mobilization (626-00000) | LS | 1 | $82,445 | $123,216 | $70,000 | $300,000 |
| 21 | Public information services (tier III) (626-01103) | LS | 1 | $100,000 | $6,000.00 | $4,500.00 | $17,658 |
| 22 | Uniformed traffic control (630-00003) | HR | 300 | $154.97 | $185.00 | $150.00 | $267.05 |
| 23 | Traffic control inspection (630-00007) | DAY | 75 | $123.73 | $385.00 | $250.00 | $354.25 |
| 24 | Traffic control management (630-00012) | DAY | 45 | $569.59 | $1,875.00 | $1,300.00 | $3,760.49 |
| 25 | Traffic control (special) LS (630-00016) | LS | 1 | $60,000 | $76,350 | $110,000 | $500,000 |
| 26 | Portable message sign panel (630-80355) | EACH | 6 | $20,000 | $7,120.00 | $8,500.00 | $8,719.98 |
| 27 | Night work lighting (632-00000) | LS | 1 | $300,000 | $38,000 | $25,000 | $100,556 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from CDOT's tabulation for this contract. CDOT Tabulation of Bids PDFs from its bid tab archive, May 2023 to September 2026 (each contract linked to its OnBase document), and four December 2025 lettings read by OCR. About 100 tabulations of late 2025 and 2026 are printed in a font without text and are not read yet. On A+B contracts the cost part is kept. Bids that did not match their published total are left out.
Every contract let that day: CDOT letting of February 11, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.