FDOT contract T3A08 bid tabulation

SR 2 FROM SPRING BRANCH TO E OF COWARTS CREEK BRIDGE. Let by Florida DOT on October 28, 2026, Jackson, District 3. 5 bids received; low bid $1,651,142 by Anderson Columbia Co., Inc..

Owner
Florida DOT
Letting
28 OCT 2026
Pay items
28
Data through
28 OCT 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Anderson Columbia Co., Inc.$1,651,142Low
2Southeast Construction Company LLC$1,845,126+12%
3Lagniappe Contracting and Paving LLC$2,110,454+28%
4C.W. Roberts Contracting, Inc.$2,266,595+37%
5Gulf Coast Utility Contractors, LLC$3,647,847+121%
FDOT contract T3A08: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Anderson Columbia Co., Inc.2. Southeast Construction Company LLC3. Lagniappe Contracting and Paving LLC4. C.W. Roberts Contracting, Inc.5. Gulf Coast Utility Contractors, LLC
0005Mobilization (0101-1)LS1$87,620$35,000$62,465$115,000$225,000
0010Maintenance of traffic (0102-1)DA1$54,167$22,250$46,200$56,880$125,000
0015Work zone sign (0102-60)ED3,436$1.12$1.15$1.29$1.20$3.00
0020Channelizing device- types I, II, VP, drum, or LCD (0102-74-1)ED41,272$0.01$0.06$0.06$0.05$1.50
0025Temporary raised/retroreflective pavement marker, type B (0102-78-2)EACH891$5.31$5.75$4.50$5.70$11.00
0030Portable changeable message sign, temporary (0102-99)ED508$21.25$23.00$24.75$24.00$40.00
0035Temporary raised rumble per day, includes all sets and relocations (0102-909)DA120$5.00$40.00$41.89$40.00$100.00
0040Litter removal (0107-1)ACRE143.32$53.11$50.00$50.00$57.00$250.00
0045Mowing (0107-2)ACRE143.32$53.11$50.00$40.00$57.00$250.00
0050Clearing & grubbing (0110-1-1)ACRE1$5,131.01$24,500$35,000$6,003.00$79,000
0055Milling existing asphalt pavement, 2" avg depth (0327-70-5)SY57,014$0.50$2.75$3.46$3.35$13.75
0060Milling existing asphalt pavement, 1 1/2" avg depth (0327-70-6)SY17,757$0.50$2.50$3.46$3.05$12.95
0065Superpave asphaltic concrete, traffic B, PG76-22 (0334-1-52)TN333.20$157.76$179.50$165.00$210.00$210.00
0070Asphalt concrete friction course,traffic B, FC-12.5, PG (0337-7-81)TN7,902.80$137.30$148.00$165.00$177.87$210.00
0075Performance turf, sod (0570-1-2)SY12,632$3.03$4.50$3.40$6.10$4.00
0080Painted pavement markings, standard, yellow, solid, 6" (0710-11201)GM3.13$1,434.08$1,600.00$2,016.00$1,700.00$1,650.00
0085Painted pavement markings, standard, yellow, skip, 6" (0710-11231)GM3.24$902.94$800.00$1,386.00$860.00$825.00
0090Initial contingency amount, DO not bid (0999-25)LS1$50,000$50,000$50,000$50,000$50,000
0095Ground-in rumble strips, 8" sinusoidal (0546-72-3)GM12.03$3,557.20$3,000.00$4,051.69$3,675.00$3,500.00
0100Single column ground sign assembly, F&I ground mount, than 12 SF (0700-1111)EACH19$531.14$550.00$643.74$570.00$600.00
0105Raised pavement marker, type B (0706-1-3)EACH891$5.31$5.50$4.50$5.70$6.00
0110Painted pavement markings, surface (0710-90)LS1$36,755$25,875$10,836$26,000$24,500
0115Thermoplastic, standard-other surfaces, white, solid, 6" (0711-16101)GM8.00$5,630.11$5,500.00$6,930.00$5,500.00$5,250.00
0120Thermoplastic, standard-other surfaces, yellow, solid, 6" (0711-16201)GM3.13$5,630.11$5,495.00$6,930.00$5,500.00$5,250.00
0125Thermoplastic, standard-other surfaces, yellow, skip, 6" (0711-16231)GM3.24$2,549.48$2,350.00$3,150.00$2,600.00$2,500.00
0130Permanent tape, white, solid, 6" for concrete bridges (0713-103101)GM0.67$37,180$31,500$44,100$34,000$32,750
0135Permanent tape, yellow, solid, for concrete bridges (0713-103201)GM0.11$37,180$31,500$44,100$35,000$32,750
0140Permanent tape, yellow, 10-30 skip, 6" wide, for concrete surfaces (0713-103281)GM0.34$10,623$15,500$18,900$17,000$16,500
FDOT contract T3A08: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from FDOT's tabulation for this contract. FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.

Every contract let that day: FDOT letting of October 28, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy