IDOT contract 46943 bid tabulation

Section ILLINOIS. Let by Illinois DOT on January 16, 2026, Lake, District 01. 5 bids received; low bid $578,450 by Alliance Contractors, Inc..

Owner
Illinois DOT
Letting
16 JAN 2026
Pay items
37
Data through
18 SEP 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Alliance Contractors, Inc.$578,450Low
2Foundation Mechanics$589,847+2.0%
3Lorig Construction Company$677,264+17%
4MYS, Incorporated$778,960+35%
5Michels Construction, Inc.$977,997+69%
IDOT contract 46943: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Alliance Contractors, Inc.2. Foundation Mechanics3. Lorig Construction Company4. MYS, Incorporated5. Michels Construction, Inc.
1Seeding SPL (K1005421)ACRE0.18$14,520$5,000.00$15,000$11,769$14,391
2Washout basin (X0326806)LS1$750.00$500.00$250.00$2,183.51$328.85
3Eros cont blanket SPL (X2511630)SY745$10.50$2.00$11.00$2.80$3.43
4Traf bar term TY 1 (X6310164)EACH4$2,600.00$2,600.00$2,600.00$2,822.28$3,563.49
5CH LK fence remov (X6640300)LF200$15.00$4.50$10.00$13.91$13.71
6Traf cont & prot SPL (X7010216)LS1$4,925.00$2,500.00$22,000$8,939.56$6,852.86
7Wood pole removal (X8301801)EACH2$500.00$500.00$1,500.00$674.12$685.29
8Construction layout (Z0013798)LS1$9,500.00$5,000.00$20,000$10,648$16,790
9Tree remov 6-15 (20100110)UNIT75$32.00$32.00$32.00$35.87$43.86
10Tree remov over 15 (20100210)UNIT102$42.00$42.00$42.00$53.80$57.56
11Earth excavation (20200100)CY178$10.00$100.00$60.00$113.42$500.00
12Channel excavation (20300100)CY117$15.00$100.00$105.00$123.35$270.20
13Porous gran embank (20700110)TON41.10$210.00$100.00$165.00$105.33$434.00
14Topsoil F & P 4 (21101615)SY745$0.10$10.00$0.10$11.77$50.06
15Perimeter eros bar (28000400)LF860$3.50$1.00$3.50$4.76$13.43
16Stone dump rip CL A4 (28100807)TON182$175.00$100.00$190.00$92.15$275.51
17Filter fabric (28200200)SY263$1.00$2.00$5.00$5.24$28.05
18Agg base cse A 12 (35101100)SY610$55.00$30.00$46.00$37.42$80.44
19Bit matls PR CT (40600275)LB1,419$0.01$2.00$0.01$0.19$0.14
20Bit matls tack CT (40600290)LB548$0.01$2.00$0.01$0.19$0.14
21HMA surf rem butt JT (40600982)SY19$195.00$50.00$200.00$183.56$130.20
22HMA BC IL-9.5 N50 (40602978)TON47$180.00$200.00$275.00$376.78$267.26
23HMA SC IL-9.5FG C N50 (40604000)TON49$181.00$200.00$190.00$376.78$267.26
24Rem exist struct (50100100)EACH1$28,000$78,850$125,000$68,607$80,963
25Structure excavation (50200100)CY68$15.00$100.00$75.00$243.76$388.22
26Conc struct (50300225)CY21$3,855.00$2,000.00$3,700.00$6,164.65$3,330.72
27Concrete encasement (50300280)CY4.40$1,500.00$500.00$1,000.00$2,465.86$2,898.15
28P P conc DK BM 21 DP (50400405)SF1,069$144.00$174.00$150.00$157.93$160.00
29Reinf bars, epoxy CTD (50800205)LB3,570$2.85$3.00$4.25$7.76$2.57
30Steel railing TY S1 (50900205)LF92$205.00$205.00$210.00$210.28$280.97
31Fur M S pile 14X0.250 (51200958)LF117$725.00$500.00$155.00$52.16$61.50
32Driving piles (51202305)LF117$1.00$1.00$1.00$637.57$250.00
33Test pile met shells (51203200)EACH2$750.00$2,500.00$7,000.00$10,433$47,748
34Name plates (51500100)EACH1$1,000.00$5,000.00$1,100.00$950.98$1,486.92
35SPBGR TY A 6FT posts (63000001)LF100$28.00$28.00$28.00$38.24$38.38
36Traf bar term T5A (63100075)EACH4$1,400.00$1,400.00$1,500.00$1,531.08$1,918.80
37Mobilization (67100100)LS1$34,400$35,000$30,000$42,737$58,000
IDOT contract 46943: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.

Every contract let that day: IDOT letting of January 16, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy