IDOT contract 61L45 bid tabulation
Project Number: Mcmq-032 / /, section 24-01121-00-PV. Let by Illinois DOT on August 1, 2025, Dupage, District 01. 5 bids received; low bid $495,500 by R. W. Dunteman Company.
- Owner
- Illinois DOT
- Letting
- 01 AUG 2025
- Pay items
- 43
- Data through
- 18 SEP 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | R. W. Dunteman Company | $495,500 | Low |
| 2 | Schroeder Asphalt Services, Inc. | $499,540 | +1.0% |
| 3 | K-Five Construction Corporation | $511,765 | +3.0% |
| 4 | A Lamp Concrete Contractors, Inc. | $524,988 | +6.0% |
| 5 | Builders Paving, LLC | $532,785 | +8.0% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. R. W. Dunteman Company | 2. Schroeder Asphalt Services, Inc. | 3. K-Five Construction Corporation | 4. A Lamp Concrete Contractors, Inc. | 5. Builders Paving, LLC |
|---|---|---|---|---|---|---|---|---|
| 1 | Strip ref CR con TR (LR443200) | LF | 4,307 | $7.70 | $10.00 | $2.00 | $7.70 | $2.50 |
| 2 | PCC surf rem var DP (X4400100) | SY | 7,367 | $3.85 | $3.50 | $2.42 | $4.25 | $3.00 |
| 3 | Construction layout (Z0013798) | LS | 1 | $7,500.00 | $6,000.00 | $12,600 | $2,500.00 | $10,000 |
| 4 | Earth excavation (20200100) | CY | 110 | $67.50 | $65.00 | $96.39 | $82.00 | $100.00 |
| 5 | Rem & disp uns matl (20201200) | CY | 167 | $58.00 | $65.00 | $122.00 | $30.00 | $55.00 |
| 6 | Topsoil F & P 4 (21101615) | SY | 136 | $16.25 | $18.50 | $16.25 | $9.00 | $16.25 |
| 7 | Sodding salt tolerant (25200110) | SY | 136 | $43.25 | $50.00 | $43.25 | $25.00 | $43.25 |
| 8 | Supple watering (25200200) | UNIT | 8 | $25.00 | $35.00 | $25.00 | $1.00 | $25.00 |
| 9 | Inlet filters (28000510) | EACH | 26 | $200.00 | $215.00 | $265.00 | $15.00 | $265.00 |
| 10 | Agg subgrade improve (30300001) | CY | 149 | $51.50 | $65.00 | $32.00 | $30.00 | $55.00 |
| 11 | Agg base cse B 6 (35101800) | SY | 436 | $15.75 | $12.00 | $41.00 | $15.25 | $20.00 |
| 12 | Bit matls PR CT (40600275) | LB | 189 | $0.01 | $0.01 | $0.01 | $0.01 | $0.01 |
| 13 | Bit matls tack CT (40600290) | LB | 5,511 | $0.01 | $0.01 | $0.01 | $0.01 | $0.01 |
| 14 | Long joint sealant (40600370) | LF | 2,794 | $6.50 | $6.25 | $4.97 | $5.25 | $6.00 |
| 15 | Mix CR JTS flangewys (40600400) | TON | 35 | $430.00 | $300.00 | $150.00 | $150.00 | $530.00 |
| 16 | HMA surf rem butt JT (40600982) | SY | 33 | $30.00 | $20.00 | $0.01 | $32.00 | $15.00 |
| 17 | PCC surf rem butt JT (40600985) | SY | 16 | $40.00 | $50.00 | $0.01 | $66.00 | $15.00 |
| 18 | HMA BC IL-19.0 N50 (40603080) | TON | 18 | $175.00 | $200.00 | $127.00 | $125.00 | $125.00 |
| 19 | P HMA BC IL-4.75 N50 (40603200) | TON | 254 | $110.00 | $135.00 | $166.93 | $140.00 | $102.00 |
| 20 | HMA SC IL-9.5 D N50 (40604060) | TON | 778 | $94.75 | $95.00 | $93.02 | $103.00 | $90.00 |
| 21 | Protective coat (42001300) | SY | 338 | $1.00 | $2.00 | $4.00 | $0.01 | $1.00 |
| 22 | HMA surf rem 2 1/4 (44000158) | SY | 741 | $14.50 | $5.00 | $7.50 | $5.50 | $8.00 |
| 23 | HMA surf rem 3 3/4 (44000164) | SY | 122 | $64.75 | $6.50 | $12.50 | $16.25 | $23.00 |
| 24 | Drive pavement rem (44000200) | SY | 42 | $27.50 | $25.00 | $25.00 | $19.50 | $55.00 |
| 25 | Comb curb gutter rem (44000500) | LF | 998 | $14.00 | $16.00 | $13.90 | $8.50 | $14.00 |
| 26 | CL D patch T1 7 (44201725) | SY | 90 | $87.50 | $76.00 | $60.00 | $80.00 | $70.00 |
| 27 | CL D patch T2 7 (44201729) | SY | 134 | $80.00 | $76.00 | $60.00 | $60.00 | $70.00 |
| 28 | CL D patch T3 7 (44201733) | SY | 400 | $70.00 | $73.00 | $60.00 | $51.00 | $70.00 |
| 29 | CL D patch T4 7 (44201735) | SY | 268 | $65.00 | $72.00 | $60.00 | $46.00 | $70.00 |
| 30 | Aggregate SHLDS B 6 (48101500) | SY | 220 | $32.50 | $23.00 | $30.00 | $26.50 | $40.00 |
| 31 | FR & grates adjust (60300105) | EACH | 5 | $850.00 | $950.00 | $615.00 | $725.00 | $850.00 |
| 32 | FR & grates T24 (60404950) | EACH | 5 | $685.00 | $800.00 | $550.00 | $500.00 | $685.00 |
| 33 | FR & lids T1 OL (60406000) | EACH | 3 | $485.00 | $565.00 | $550.00 | $475.00 | $485.00 |
| 34 | Comb CC&G TY B-6.24 (60605000) | LF | 998 | $50.50 | $74.00 | $47.80 | $69.00 | $67.00 |
| 35 | Mobilization (67100100) | LS | 1 | $36,875 | $20,000 | $31,000 | $31,475 | $106,018 |
| 36 | TR cont & prot 701501 (70102620) | LS | 1 | $22,643 | $15,000 | $81,636 | $90,900 | $10,000 |
| 37 | Changeable message SN (70107025) | CAL DAY | 28 | $40.00 | $50.00 | $50.00 | $30.00 | $40.00 |
| 38 | Short term pavt mking (70300100) | LF | 881 | $1.85 | $3.00 | $1.00 | $1.00 | $0.01 |
| 39 | SHRT TRM pavt MK rem (70300150) | SF | 98 | $3.50 | $5.00 | $2.00 | $2.00 | $0.01 |
| 40 | THPL PVT MK line 4 (78000200) | LF | 9,672 | $0.74 | $1.10 | $0.74 | $1.00 | $0.75 |
| 41 | THPL PVT MK line 24 (78000650) | LF | 38 | $5.25 | $9.75 | $5.25 | $15.00 | $5.25 |
| 42 | Raised refl pavt MKR (78100100) | EACH | 75 | $77.00 | $84.00 | $77.00 | $75.00 | $77.00 |
| 43 | Raised ref PVT MK rem (78300200) | EACH | 77 | $14.03 | $18.00 | $10.00 | $27.00 | $5.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.
Every contract let that day: IDOT letting of August 1, 2025. Compiled by Mirage Metrics.