IDOT contract 62V52 bid tabulation
Section FAP. Let by Illinois DOT on June 13, 2025, Mchenry, District 01. 2 bids received; low bid $2,389,468 by Curran Contracting Company.
- Owner
- Illinois DOT
- Letting
- 13 JUN 2025
- Pay items
- 88
- Data through
- 18 SEP 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Curran Contracting Company | $2,389,468 | Low |
| 2 | Peter Baker & Son Co. | $2,655,193 | +11% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Curran Contracting Company | 2. Peter Baker & Son Co. |
|---|---|---|---|---|---|
| 1 | Constructn layout SPL (X0320050) | LS | 1 | $15,000 | $2,500.00 |
| 2 | Ped signal post 5 FT (X1400378) | EACH | 2 | $1,490.60 | $1,490.60 |
| 3 | Grading & shap SHLDRS (X2020110) | UNIT | 162 | $60.00 | $160.00 |
| 4 | CC&G RMVL repl < = 10 (X4400501) | LF | 75 | $71.55 | $95.00 |
| 5 | CC&G RMVL repl > 10FT (X4400503) | LF | 385 | $68.70 | $95.00 |
| 6 | FR & lids adjust SPL (X6030310) | EACH | 9 | $2,500.00 | $1,500.00 |
| 7 | Engrs FLD ofc TY A D1 (X6700407) | CAL MO | 12 | $4,000.00 | $1,000.00 |
| 8 | Temp info signing (X7200061) | SF | 51.40 | $16.00 | $25.00 |
| 9 | Accessible ped signal (X8760200) | EACH | 4 | $2,695.35 | $2,695.35 |
| 10 | Conc FDN TY A 12D (X8780012) | LF | 8 | $421.88 | $421.88 |
| 11 | Det loop repl (X8860105) | LF | 961 | $25.80 | $25.80 |
| 12 | RE-optimize TR sig sys 1 (Z0033044) | EACH | 1 | $682.50 | $682.50 |
| 13 | Earth excavation (20200100) | CY | 3,315 | $25.00 | $74.00 |
| 14 | Rem & disp uns matl (20201200) | CY | 325 | $30.00 | $80.00 |
| 15 | Geotech fab F/GR stab (21001000) | SY | 975 | $2.13 | $4.50 |
| 16 | Topsoil F & P 4 (21101615) | SY | 70 | $10.00 | $10.00 |
| 17 | Sodding salt tolerant (25200110) | SY | 70 | $60.00 | $60.00 |
| 18 | Supple watering (25200200) | UNIT | 0.40 | $0.01 | $1.00 |
| 19 | Agg subgrade improve (30300001) | CY | 325 | $65.00 | $130.00 |
| 20 | Agg subgrade impr 12 (30300112) | SY | 4,872 | $28.00 | $40.00 |
| 21 | HMA base cse 8 (35501316) | SY | 12 | $115.00 | $135.60 |
| 22 | HMA BC wid 8 (35600708) | SY | 4,872 | $46.00 | $45.50 |
| 23 | Bit matls PR CT (40600275) | LB | 2,195 | $1.35 | $0.01 |
| 24 | Bit matls tack CT (40600290) | LB | 26,287 | $0.01 | $0.01 |
| 25 | Long joint sealant (40600370) | LF | 19,277 | $2.80 | $3.80 |
| 26 | Mix CR JTS flangewys (40600400) | TON | 147 | $200.00 | $75.00 |
| 27 | HMA surf rem butt JT (40600982) | SY | 364 | $25.00 | $1.00 |
| 28 | P HMA BC IL-4.75 N50 (40603200) | TON | 794 | $110.00 | $113.00 |
| 29 | HMA SC IL-9.5 D N50 (40604060) | TON | 2 | $400.00 | $250.00 |
| 30 | HMA SC IL-9.5 D N70 (40604062) | TON | 4,098 | $87.00 | $87.00 |
| 31 | Protective coat (42001300) | SY | 249 | $0.01 | $3.00 |
| 32 | PCC driveway pavt 8 (42300400) | SY | 9 | $184.25 | $300.00 |
| 33 | PC conc sidewalk 5 (42400200) | SF | 900 | $16.50 | $15.00 |
| 34 | Detectable warnings (42400800) | SF | 74 | $40.00 | $60.00 |
| 35 | Pavement rem (44000100) | SY | 4,872 | $32.00 | $22.00 |
| 36 | HMA surf rem 1 1/2 (44000155) | SY | 29,544 | $2.25 | $1.99 |
| 37 | HMA surf rem 2 1/4 (44000158) | SY | 19,347 | $2.60 | $2.99 |
| 38 | Drive pavement rem (44000200) | SY | 20 | $24.00 | $105.00 |
| 39 | Sidewalk rem (44000600) | SF | 350 | $4.94 | $5.00 |
| 40 | CL D patch T1 15 (44201823) | SY | 85 | $300.00 | $85.00 |
| 41 | CL D patch T2 15 (44201827) | SY | 512 | $200.00 | $85.00 |
| 42 | CL D patch T3 15 (44201831) | SY | 598 | $150.00 | $85.00 |
| 43 | CL D patch T4 15 (44201833) | SY | 512 | $120.00 | $85.00 |
| 44 | Saw cuts (44213200) | LF | 12,361 | $1.00 | $3.75 |
| 45 | Agg wedge SHLD type B (48102100) | TON | 274 | $50.00 | $55.00 |
| 46 | Man reconst (60257900) | EACH | 2 | $3,000.00 | $4,500.00 |
| 47 | FR & lids T1 CL (60406100) | EACH | 2 | $1,000.00 | $800.00 |
| 48 | Pipe culv cleaned 12 (60920012) | LF | 150 | $18.00 | $18.00 |
| 49 | Non SPL waste disposl (66900200) | CY | 3,315 | $60.00 | $80.00 |
| 50 | Soil disposal analy (66900530) | EACH | 1 | $1,400.00 | $1,800.00 |
| 51 | Reg sub P-const plan (66901001) | LS | 1 | $3,900.00 | $3,500.00 |
| 52 | Reg sub F con report (66901003) | LS | 1 | $500.00 | $500.00 |
| 53 | Reg sub mon (66901006) | CAL DAY | 20 | $700.00 | $725.00 |
| 54 | Mobilization (67100100) | LS | 1 | $150,000 | $268,094 |
| 55 | Traf cont-prot 701201 (70100450) | LS | 1 | $125.00 | $100.00 |
| 56 | Traf cont-prot 701206 (70100455) | LS | 1 | $1.00 | $100.00 |
| 57 | Traf cont-prot 701306 (70100460) | LS | 1 | $125.00 | $100.00 |
| 58 | Traf cont-prot 701336 (70100600) | LS | 1 | $25,000 | $100.00 |
| 59 | TR cont & prot 701501 (70102620) | LS | 1 | $25,000 | $118,410 |
| 60 | TR cont & prot 701502 (70102622) | LS | 1 | $1.00 | $100.00 |
| 61 | TR cont & prot 701801 (70102640) | LS | 1 | $1.00 | $100.00 |
| 62 | Short term pavt mking (70300100) | LF | 38,078 | $0.01 | $0.01 |
| 63 | SHRT TRM pavt MK rem (70300150) | SF | 12,693 | $0.01 | $0.01 |
| 64 | Temp PVT MK LTR & sym paint (70300211) | SF | 1,977 | $1.00 | $0.01 |
| 65 | Temp PVT MK line 4 - paint (70300221) | LF | 125,745 | $0.40 | $0.01 |
| 66 | Temp PVT MK line 6 - paint (70300241) | LF | 9,849 | $0.45 | $0.01 |
| 67 | Temp PVT MK line 8 - paint (70300251) | LF | 750 | $0.80 | $0.01 |
| 68 | Temp PVT MK line 12 - paint (70300261) | LF | 1,746 | $1.00 | $0.01 |
| 69 | Temp PVT MK line 24 - paint (70300281) | LF | 765 | $1.25 | $0.01 |
| 70 | Temp PVT MK L4 T4 tape (70307120) | LF | 25,131 | $1.00 | $0.01 |
| 71 | THPL PVT MK LTR & sym (78000100) | SF | 659 | $4.20 | $4.00 |
| 72 | THPL PVT MK line 4 (78000200) | LF | 41,915 | $0.70 | $0.79 |
| 73 | THPL PVT MK line 6 (78000400) | LF | 3,283 | $1.05 | $1.22 |
| 74 | THPL PVT MK line 8 (78000500) | LF | 250 | $1.40 | $1.63 |
| 75 | THPL PVT MK line 12 (78000600) | LF | 582 | $2.10 | $2.45 |
| 76 | THPL PVT MK line 24 (78000650) | LF | 255 | $4.20 | $4.90 |
| 77 | Raised refl pavt MKR (78100100) | EACH | 655 | $36.00 | $46.90 |
| 78 | Raised ref PVT MK rem (78300200) | EACH | 524 | $13.79 | $19.00 |
| 79 | PVT MKG rem WTR blast (78300202) | SF | 52,593 | $0.02 | $0.05 |
| 80 | Undrgrd C galvs 2 (81028200) | LF | 72 | $41.65 | $41.65 |
| 81 | Main EX TR sig instal (85000200) | EACH | 1 | $2,000.00 | $2,000.00 |
| 82 | Elcbl C signal 14 2C (87301215) | LF | 418 | $1.29 | $1.29 |
| 83 | Elcbl C egrdc 6 1C (87301900) | LF | 33 | $2.21 | $2.21 |
| 84 | Drill EX handhole (87900200) | EACH | 3 | $845.00 | $845.00 |
| 85 | Rem elcbl FR con (89502300) | LF | 434 | $0.73 | $0.73 |
| 86 | Remov EX TS equip (89502375) | EACH | 1 | $630.00 | $630.00 |
| 87 | Rebuild EX handhole (89502376) | EACH | 1 | $1,297.50 | $1,297.50 |
| 88 | Remov EX handhole (89502380) | EACH | 1 | $785.00 | $785.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.
Every contract let that day: IDOT letting of June 13, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.