IDOT contract 62V54 bid tabulation
Section FAP. Let by Illinois DOT on April 25, 2025, Cook, District 01. 3 bids received; low bid $1,679,248 by Builders Paving, LLC.
- Owner
- Illinois DOT
- Letting
- 25 APR 2025
- Pay items
- 94
- Data through
- 18 SEP 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Builders Paving, LLC | $1,679,248 | Low |
| 2 | Peter Baker & Son Co. | $1,701,876 | +1.0% |
| 3 | Schroeder Asphalt Services, Inc. | $1,920,167 | +14% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Builders Paving, LLC | 2. Peter Baker & Son Co. | 3. Schroeder Asphalt Services, Inc. |
|---|---|---|---|---|---|---|
| 1 | Constructn layout SPL (X0320050) | LS | 1 | $4,900.00 | $4,900.00 | $25,000 |
| 2 | Rod and clean EX cond (X0324599) | LF | 3,330 | $0.20 | $0.20 | $0.25 |
| 3 | Rem & rein bric paver (X0327611) | SF | 20 | $50.00 | $50.00 | $55.00 |
| 4 | Ped signal post 10 FT (X1400367) | EACH | 11 | $2,660.00 | $2,660.00 | $2,850.00 |
| 5 | CC&G RMVL repl < = 10 (X4400501) | LF | 240 | $88.00 | $88.00 | $95.00 |
| 6 | CC&G RMVL repl > 10FT (X4400503) | LF | 862 | $88.00 | $88.00 | $95.00 |
| 7 | HMA surf rem var DP (X4401198) | SY | 83 | $30.00 | $25.00 | $5.00 |
| 8 | SS cleaned 12 (X5537800) | LF | 340 | $5.00 | $4.50 | $6.00 |
| 9 | FR & lids adjust SPL (X6030310) | EACH | 29 | $1,250.00 | $1,410.00 | $1,350.00 |
| 10 | Engrs FLD ofc TY A D1 (X6700407) | CAL MO | 6 | $3,300.00 | $2,000.00 | $3,000.00 |
| 11 | Temp info signing (X7200061) | SF | 283 | $20.00 | $20.00 | $18.00 |
| 12 | Accessible ped signal (X8760200) | EACH | 20 | $3,068.00 | $3,068.00 | $3,275.00 |
| 13 | Conc FDN TY A 12D (X8780012) | LF | 48 | $729.00 | $729.00 | $780.00 |
| 14 | Vid veh det sys complete (X8891007) | EACH | 2 | $15,630 | $15,630 | $16,750 |
| 15 | Drainage STR cleaned (Z0018500) | EACH | 63 | $350.00 | $280.00 | $375.00 |
| 16 | RE-optimize TR sig sys 1 (Z0033044) | EACH | 4 | $1,953.00 | $1,953.00 | $2,100.00 |
| 17 | Supple watering (20101700) | UNIT | 1 | $1.00 | $1.00 | $5.00 |
| 18 | Earth excavation (20200100) | CY | 32 | $40.00 | $40.00 | $50.00 |
| 19 | Topsoil F & P 4 (21101615) | SY | 36 | $20.00 | $20.00 | $25.00 |
| 20 | Sodding salt tolerant (25200110) | SY | 36 | $85.00 | $85.00 | $100.00 |
| 21 | HMA base cse 8 (35501316) | SY | 20 | $128.00 | $105.00 | $400.00 |
| 22 | Bit matls tack CT (40600290) | LB | 13,037 | $0.01 | $0.01 | $0.01 |
| 23 | Long joint sealant (40600370) | LF | 15,780 | $2.97 | $3.65 | $3.25 |
| 24 | Mix CR JTS flangewys (40600400) | TON | 44 | $555.00 | $150.00 | $300.00 |
| 25 | HMA surf rem butt JT (40600982) | SY | 313 | $15.00 | $2.00 | $7.00 |
| 26 | HMA SC IL-9.5 D N50 (40604060) | TON | 20 | $155.00 | $100.00 | $100.00 |
| 27 | P HMA SC SMA 9.5 F N80 (40605026) | TON | 2,835 | $118.00 | $128.00 | $159.00 |
| 28 | Protective coat (42001300) | SY | 287 | $1.00 | $1.00 | $2.00 |
| 29 | PCC driveway pavt 8 (42300400) | SY | 1 | $500.00 | $500.00 | $535.00 |
| 30 | PC conc sidewalk 5 (42400200) | SF | 2,636 | $10.00 | $10.00 | $10.75 |
| 31 | Detectable warnings (42400800) | SF | 254 | $42.00 | $42.00 | $45.00 |
| 32 | HMA surf rem 1 3/4 (44000156) | SY | 28,921 | $4.00 | $3.95 | $3.50 |
| 33 | Drive pavement rem (44000200) | SY | 2 | $100.00 | $100.00 | $105.00 |
| 34 | Curb rem (44000300) | LF | 225 | $15.00 | $15.00 | $16.00 |
| 35 | Sidewalk rem (44000600) | SF | 2,926 | $4.00 | $4.00 | $4.25 |
| 36 | Median removal (PD) (44003510) | SF | 1,500 | $3.37 | $2.00 | $7.00 |
| 37 | CL D patch T2 13 (44201803) | SY | 220 | $150.00 | $220.00 | $189.00 |
| 38 | CL D patch T3 13 (44201807) | SY | 115 | $150.00 | $200.00 | $179.00 |
| 39 | CL D patch T4 13 (44201809) | SY | 115 | $150.00 | $170.00 | $169.00 |
| 40 | CL D patch T2 18 (44201863) | SY | 50 | $198.00 | $305.00 | $290.00 |
| 41 | CL D patch T3 18 (44201867) | SY | 25 | $198.00 | $275.00 | $280.00 |
| 42 | CL D patch T4 18 (44201869) | SY | 25 | $198.00 | $235.00 | $270.00 |
| 43 | Water valves adjust (56109210) | EACH | 2 | $385.00 | $665.00 | $413.00 |
| 44 | CB reconst (60252800) | EACH | 1 | $1,450.00 | $1,875.00 | $1,550.00 |
| 45 | Man reconst (60257900) | EACH | 1 | $1,850.00 | $2,600.00 | $2,000.00 |
| 46 | Inlets adjust (60260100) | EACH | 5 | $485.00 | $550.00 | $520.00 |
| 47 | FR & grates adjust (60300105) | EACH | 11 | $485.00 | $600.00 | $520.00 |
| 48 | FR & lids adjust (60300305) | EACH | 5 | $625.00 | $600.00 | $675.00 |
| 49 | FR & grates T24 (60404950) | EACH | 2 | $585.00 | $425.00 | $620.00 |
| 50 | FR & lids T1 CL (60406100) | EACH | 3 | $455.00 | $400.00 | $475.00 |
| 51 | Comb CC&G TB6.06 (60603500) | LF | 100 | $50.00 | $50.00 | $53.00 |
| 52 | Conc median surf 4 (60618300) | SF | 1,500 | $10.00 | $10.00 | $10.75 |
| 53 | Non SPL waste disposl (66900200) | CY | 32 | $100.00 | $100.00 | $105.00 |
| 54 | Soil disposal analy (66900530) | EACH | 2 | $900.00 | $900.00 | $1,000.00 |
| 55 | Reg sub P-const plan (66901001) | LS | 1 | $4,800.00 | $4,800.00 | $5,100.00 |
| 56 | Reg sub F con report (66901003) | LS | 1 | $500.00 | $500.00 | $1,000.00 |
| 57 | Reg sub mon (66901006) | CAL DAY | 2 | $700.00 | $700.00 | $1,000.00 |
| 58 | Mobilization (67100100) | LS | 1 | $146,170 | $132,805 | $70,000 |
| 59 | TR cont & prot 701601 (70102630) | LS | 1 | $15,000 | $5,000.00 | $70,000 |
| 60 | TR cont & prot 701701 (70102635) | LS | 1 | $1.00 | $2.00 | $2.00 |
| 61 | TR cont & prot 701801 (70102640) | LS | 1 | $5,350.00 | $5,350.00 | $2.00 |
| 62 | Night work zone light (70200100) | LS | 1 | $1,000.00 | $5,200.00 | $1,000.00 |
| 63 | Short term pavt mking (70300100) | LF | 11,311 | $0.01 | $0.01 | $2.00 |
| 64 | SHRT TRM pavt MK rem (70300150) | SF | 3,771 | $0.01 | $0.01 | $4.00 |
| 65 | Temp PVT MK LTR & sym paint (70300211) | SF | 592 | $2.85 | $2.85 | $1.30 |
| 66 | Temp PVT MK line 4 - paint (70300221) | LF | 2,259 | $0.30 | $0.30 | $0.40 |
| 67 | Temp PVT MK line 6 - paint (70300241) | LF | 2,191 | $0.40 | $0.40 | $0.55 |
| 68 | Temp PVT MK line 8 - paint (70300251) | LF | 960 | $0.60 | $0.60 | $0.75 |
| 69 | Temp PVT MK line 12 - paint (70300261) | LF | 2,709 | $1.00 | $1.00 | $1.25 |
| 70 | Temp PVT MK line 24 - paint (70300281) | LF | 570 | $2.00 | $2.00 | $1.75 |
| 71 | Temp PVT MK L4 T4 tape (70307120) | LF | 5,656 | $0.01 | $0.01 | $1.40 |
| 72 | THPL PVT MK LTR & sym (78000100) | SF | 592 | $5.00 | $5.00 | $6.25 |
| 73 | THPL PVT MK line 4 (78000200) | LF | 2,259 | $0.69 | $1.05 | $1.00 |
| 74 | THPL PVT MK line 6 (78000400) | LF | 2,191 | $1.00 | $1.00 | $1.25 |
| 75 | THPL PVT MK line 8 (78000500) | LF | 960 | $1.35 | $2.00 | $2.25 |
| 76 | THPL PVT MK line 12 (78000600) | LF | 2,709 | $2.00 | $1.80 | $3.75 |
| 77 | THPL PVT MK line 24 (78000650) | LF | 590 | $5.00 | $5.00 | $6.50 |
| 78 | Raised refl pavt MKR (78100100) | EACH | 284 | $45.00 | $45.00 | $40.00 |
| 79 | Raised ref PVT MK rem (78300200) | EACH | 284 | $10.00 | $19.00 | $19.00 |
| 80 | PVT MKG rem WTR blast (78300202) | SF | 8,814 | $0.01 | $0.01 | $1.50 |
| 81 | Undrgrd C galvs 2 (81028200) | LF | 220 | $103.90 | $103.90 | $111.00 |
| 82 | Main EX TR sig instal (85000200) | EACH | 4 | $13,200 | $13,200 | $14,000 |
| 83 | Elcbl C signal 14 2C (87301215) | LF | 3,832 | $5.50 | $5.50 | $5.75 |
| 84 | Elcbl C signal 14 3C (87301225) | LF | 4,397 | $5.60 | $5.60 | $5.75 |
| 85 | Elcbl C lead 14 1PR (87301305) | LF | 5,439 | $5.70 | $5.70 | $6.00 |
| 86 | Elcbl C egrdc 6 1C (87301900) | LF | 589 | $6.00 | $6.00 | $7.00 |
| 87 | Drill EX handhole (87900200) | EACH | 12 | $897.00 | $897.00 | $950.00 |
| 88 | Ped SH LED 1F BM CDT (88102717) | EACH | 20 | $1,594.00 | $1,594.00 | $1,700.00 |
| 89 | Inductive loop detect (88500100) | EACH | 19 | $209.00 | $209.00 | $225.00 |
| 90 | Det loop T1 (88600100) | LF | 2,882 | $40.20 | $40.20 | $43.00 |
| 91 | Rem elcbl FR con (89502300) | LF | 7,804 | $0.90 | $0.90 | $1.00 |
| 92 | Remov EX TS equip (89502375) | EACH | 4 | $7,920.00 | $7,920.00 | $8,500.00 |
| 93 | Rebuild EX handhole (89502376) | EACH | 3 | $8,507.00 | $8,507.00 | $9,100.00 |
| 94 | Remov EX conc FDN (89502385) | EACH | 1 | $1,320.00 | $1,320.00 | $1,400.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.
Every contract let that day: IDOT letting of April 25, 2025. Compiled by Mirage Metrics.