IDOT contract 62V86 bid tabulation
Section FAP. Let by Illinois DOT on April 25, 2025, Dupage, District 01. 3 bids received; low bid $2,285,003 by K-Five Construction Corporation.
- Owner
- Illinois DOT
- Letting
- 25 APR 2025
- Pay items
- 98
- Data through
- 18 SEP 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | K-Five Construction Corporation | $2,285,003 | Low |
| 2 | Builders Paving, LLC | $2,440,970 | +7.0% |
| 3 | R. W. Dunteman Company | $2,546,859 | +11% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. K-Five Construction Corporation | 2. Builders Paving, LLC | 3. R. W. Dunteman Company |
|---|---|---|---|---|---|---|
| 1 | Constructn layout SPL (X0320050) | LS | 1 | $3,100.00 | $8,000.00 | $7,500.00 |
| 2 | Serv instl GR MT MTR (X1400150) | EACH | 1 | $3,778.43 | $4,000.00 | $3,778.43 |
| 3 | Ped signal post 10 FT (X1400367) | EACH | 3 | $1,128.69 | $1,150.00 | $1,128.69 |
| 4 | Ped signal post 5 FT (X1400378) | EACH | 3 | $960.22 | $980.00 | $960.22 |
| 5 | CC&G RMVL repl < = 10 (X4400501) | LF | 300 | $58.00 | $70.00 | $75.90 |
| 6 | CC&G RMVL repl > 10FT (X4400503) | LF | 520 | $58.00 | $68.00 | $69.96 |
| 7 | SS cleaned 12 (X5537800) | LF | 375 | $1.00 | $1.00 | $1.00 |
| 8 | Pro man/CB con OV SS (X6025604) | EACH | 1 | $3,950.00 | $8,700.00 | $6,985.00 |
| 9 | FR & lids adjust SPL (X6030310) | EACH | 30 | $1,520.00 | $1,325.00 | $1,250.00 |
| 10 | Engrs FLD ofc TY A D1 (X6700407) | CAL MO | 12 | $3,300.00 | $3,300.00 | $4,500.00 |
| 11 | Temp info signing (X7200061) | SF | 308.40 | $17.00 | $17.00 | $17.00 |
| 12 | Fac T5 cab SPL (X8570231) | EACH | 1 | $31,676 | $32,000 | $31,677 |
| 13 | Uninter PS cab SPL (X8620250) | EACH | 1 | $7,890.00 | $8,000.00 | $7,890.24 |
| 14 | Accessible ped signal (X8760200) | EACH | 12 | $2,473.20 | $2,500.00 | $2,473.20 |
| 15 | Conc FDN TY A 12D (X8780012) | LF | 28 | $337.84 | $345.00 | $337.84 |
| 16 | Vid veh det sys SN AP (X8891009) | EACH | 1 | $12,691 | $13,000 | $12,691 |
| 17 | Drainage STR cleaned (Z0018500) | EACH | 25 | $320.00 | $325.00 | $320.00 |
| 18 | RE-optimize TR sig sys 1 (Z0033044) | EACH | 3 | $720.00 | $730.00 | $720.00 |
| 19 | Earth excavation (20200100) | CY | 55 | $100.00 | $65.00 | $60.31 |
| 20 | Topsoil F & P 4 (21101615) | SY | 180 | $18.00 | $6.00 | $18.00 |
| 21 | Sodding salt tolerant (25200110) | SY | 180 | $30.00 | $66.00 | $30.00 |
| 22 | Supple watering (25200200) | UNIT | 1 | $25.00 | $1.00 | $25.00 |
| 23 | HMA base cse 6 (35501308) | SY | 54 | $25.00 | $100.00 | $87.62 |
| 24 | Bit matls tack CT (40600290) | LB | 35,010 | $0.01 | $0.01 | $0.66 |
| 25 | Long joint sealant (40600370) | LF | 30,150 | $2.56 | $2.80 | $2.48 |
| 26 | Mix CR JTS flangewys (40600400) | TON | 105 | $50.00 | $520.00 | $383.25 |
| 27 | HMA surf rem butt JT (40600982) | SY | 410 | $1.00 | $15.00 | $29.17 |
| 28 | HMA SC IL-9.5 D N50 (40604060) | TON | 633 | $96.00 | $87.00 | $109.55 |
| 29 | P HMA SC SMA 9.5 F N80 (40605026) | TON | 6,848 | $120.00 | $115.00 | $108.38 |
| 30 | Protective coat (42001300) | SY | 465 | $0.01 | $3.00 | $0.01 |
| 31 | PCC driveway pavt 8 (42300400) | SY | 7 | $200.00 | $270.00 | $170.84 |
| 32 | PC conc sidewalk 5 (42400200) | SF | 2,446 | $13.75 | $15.50 | $8.90 |
| 33 | Detectable warnings (42400800) | SF | 270 | $34.00 | $56.00 | $33.74 |
| 34 | HMA surf rem 1 1/2 (44000155) | SY | 7,460 | $2.50 | $6.00 | $2.97 |
| 35 | HMA surf rem 1 3/4 (44000156) | SY | 69,870 | $3.00 | $3.60 | $2.74 |
| 36 | Drive pavement rem (44000200) | SY | 60 | $30.00 | $35.00 | $59.90 |
| 37 | Sidewalk rem (44000600) | SF | 2,466 | $3.50 | $5.20 | $2.91 |
| 38 | CL D patch T2 14 (44201815) | SY | 210 | $42.00 | $95.00 | $182.65 |
| 39 | CL D patch T3 14 (44201819) | SY | 1,155 | $42.00 | $85.00 | $165.67 |
| 40 | CL D patch T4 14 (44201821) | SY | 693 | $42.00 | $80.00 | $151.09 |
| 41 | Temp soil reten systm (52200020) | SF | 350 | $80.00 | $100.00 | $115.00 |
| 42 | Storm sew CL A 1 12 (550A0050) | LF | 5 | $575.00 | $260.00 | $255.00 |
| 43 | CB TA 4 dia T24F&G (60201340) | EACH | 1 | $6,800.00 | $9,000.00 | $11,855 |
| 44 | Man TA 4 dia T1F CL (60218400) | EACH | 1 | $18,500 | $10,000 | $23,855 |
| 45 | Man adjust (60255500) | EACH | 2 | $950.00 | $1,050.00 | $550.00 |
| 46 | FR & grates adjust (60300105) | EACH | 3 | $950.00 | $1,050.00 | $450.00 |
| 47 | FR & lids adjust (60300305) | EACH | 20 | $950.00 | $1,050.00 | $550.00 |
| 48 | Comb CC&G TB6.12 (60603800) | LF | 29 | $54.00 | $74.00 | $47.00 |
| 49 | Comb CC&G TY B-6.24 (60605000) | LF | 235 | $54.00 | $82.00 | $50.78 |
| 50 | Non SPL waste disposl (66900200) | CY | 55 | $100.00 | $100.00 | $117.04 |
| 51 | Soil disposal analy (66900530) | EACH | 1 | $1,630.00 | $1,630.00 | $1,630.00 |
| 52 | Reg sub P-const plan (66901001) | LS | 1 | $3,400.00 | $3,800.00 | $3,400.00 |
| 53 | Reg sub F con report (66901003) | LS | 1 | $500.00 | $500.00 | $500.00 |
| 54 | Reg sub mon (66901006) | CAL DAY | 11 | $700.00 | $720.00 | $700.00 |
| 55 | Mobilization (67100100) | LS | 1 | $140,948 | $143,000 | $153,277 |
| 56 | TR cont & prot 701501 (70102620) | LS | 1 | $1.00 | $100.00 | $85,391 |
| 57 | TR cont & prot 701601 (70102630) | LS | 1 | $97,800 | $10,000 | $9,000.00 |
| 58 | TR cont & prot 701602 (70102632) | LS | 1 | $5,500.00 | $7,000.00 | $5,500.00 |
| 59 | TR cont & prot 701701 (70102635) | LS | 1 | $5,500.00 | $7,000.00 | $5,500.00 |
| 60 | TR cont & prot 701801 (70102640) | LS | 1 | $500.00 | $600.00 | $1,376.66 |
| 61 | Short term pavt mking (70300100) | LF | 15,030 | $1.00 | $1.30 | $1.18 |
| 62 | SHRT TRM pavt MK rem (70300150) | SF | 7,910 | $2.00 | $0.40 | $0.94 |
| 63 | Temp PVT MK LTR & sym paint (70300211) | SF | 3,903 | $1.25 | $1.25 | $1.25 |
| 64 | Temp PVT MK line 4 - paint (70300221) | LF | 73,980 | $0.25 | $0.30 | $0.25 |
| 65 | Temp PVT MK line 6 - paint (70300241) | LF | 15,675 | $0.38 | $0.40 | $0.38 |
| 66 | Temp PVT MK line 8 - paint (70300251) | LF | 315 | $0.50 | $0.50 | $0.50 |
| 67 | Temp PVT MK line 12 - paint (70300261) | LF | 4,200 | $0.75 | $0.80 | $0.75 |
| 68 | Temp PVT MK line 24 - paint (70300281) | LF | 2,565 | $1.25 | $1.30 | $1.25 |
| 69 | THPL PVT MK LTR & sym (78000100) | SF | 1,301 | $5.25 | $5.25 | $5.25 |
| 70 | THPL PVT MK line 4 (78000200) | LF | 24,660 | $0.75 | $0.75 | $0.70 |
| 71 | THPL PVT MK line 6 (78000400) | LF | 5,225 | $0.95 | $1.30 | $1.30 |
| 72 | THPL PVT MK line 8 (78000500) | LF | 105 | $1.10 | $1.75 | $1.75 |
| 73 | THPL PVT MK line 12 (78000600) | LF | 1,400 | $2.60 | $2.60 | $2.60 |
| 74 | THPL PVT MK line 24 (78000650) | LF | 855 | $5.25 | $5.25 | $5.25 |
| 75 | Raised refl pavt MKR (78100100) | EACH | 692 | $31.50 | $35.00 | $35.00 |
| 76 | Raised ref PVT MK rem (78300200) | EACH | 692 | $9.61 | $18.00 | $9.59 |
| 77 | PVT MKG rem WTR blast (78300202) | SF | 15,155 | $1.00 | $1.00 | $1.00 |
| 78 | Undrgrd C galvs 2 (81028200) | LF | 168 | $74.82 | $76.00 | $74.82 |
| 79 | Undrgrd C galvs 3 (81028220) | LF | 15 | $81.97 | $83.00 | $81.97 |
| 80 | Undrgrd C galvs 4 (81028240) | LF | 60 | $83.00 | $84.00 | $83.00 |
| 81 | Main EX TR sig instal (85000200) | EACH | 5 | $1,635.19 | $1,700.00 | $1,635.19 |
| 82 | Elcbl C signal 14 2C (87301215) | LF | 968 | $6.48 | $6.60 | $6.48 |
| 83 | Elcbl C signal 14 3C (87301225) | LF | 632 | $6.65 | $6.90 | $6.65 |
| 84 | Elcbl C signal 14 7C (87301255) | LF | 135 | $7.36 | $7.60 | $7.36 |
| 85 | Elcbl C lead 14 1PR (87301305) | LF | 678 | $6.62 | $6.90 | $6.62 |
| 86 | Elcbl C serv 6 2C (87301805) | LF | 27 | $8.23 | $8.40 | $8.23 |
| 87 | Elcbl C egrdc 6 1C (87301900) | LF | 62 | $7.12 | $7.40 | $7.12 |
| 88 | Conc FDN TY A (87800100) | LF | 4 | $404.78 | $420.00 | $404.78 |
| 89 | Drill EX handhole (87900200) | EACH | 11 | $438.78 | $460.00 | $438.78 |
| 90 | Ped SH LED 1F BM CDT (88102717) | EACH | 4 | $687.17 | $710.00 | $687.17 |
| 91 | Inductive loop detect (88500100) | EACH | 9 | $222.43 | $230.00 | $222.43 |
| 92 | Det loop T1 (88600100) | LF | 3,935 | $24.59 | $26.00 | $24.59 |
| 93 | Reloc EX ped sig head (89500200) | EACH | 1 | $312.80 | $350.00 | $312.80 |
| 94 | Reloc EX TS equip (89501250) | EACH | 1 | $704.93 | $770.00 | $704.93 |
| 95 | Rem elcbl FR con (89502300) | LF | 558 | $6.01 | $6.20 | $6.01 |
| 96 | Rem & RE elcbl FR con (89502350) | LF | 146 | $6.01 | $6.20 | $6.01 |
| 97 | Remov EX TS equip (89502375) | EACH | 2 | $644.11 | $660.00 | $644.11 |
| 98 | Rebuild EX handhole (89502376) | EACH | 3 | $2,443.98 | $2,600.00 | $2,443.98 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.
Every contract let that day: IDOT letting of April 25, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.