IDOT contract 66P33 bid tabulation
Section (06-2HB-4)BRR. Let by Illinois DOT on January 17, 2025, Bureau, District 03. 2 bids received; low bid $439,369 by D. Construction, Inc..
- Owner
- Illinois DOT
- Letting
- 17 JAN 2025
- Pay items
- 46
- Data through
- 18 SEP 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | D. Construction, Inc. | $439,369 | Low |
| 2 | Civil Constructors, Inc. d/b/a/ Helm Civil | $596,679 | +36% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. D. Construction, Inc. | 2. Civil Constructors, Inc. d/b/a/ Helm Civil |
|---|---|---|---|---|---|
| 1 | CLN & PT exp RE-bar (X5060704) | SF | 56 | $60.00 | $324.00 |
| 2 | STR rep con DP = < 5 (Z0012754) | SF | 10 | $450.00 | $875.00 |
| 3 | Deck slab rep (FD-T2) (Z0016002) | SY | 26 | $1,300.00 | $1,500.00 |
| 4 | Deck slab rep (part) (Z0016200) | SY | 2 | $1,500.00 | $1,500.00 |
| 5 | Reloc name plates (Z0049790) | EACH | 1 | $2,000.00 | $586.00 |
| 6 | Stone riprap CL A4 (28100107) | SY | 18 | $200.00 | $903.00 |
| 7 | Filter fabric (28200200) | SY | 18 | $15.00 | $10.60 |
| 8 | Bit matls tack CT (40600290) | LB | 340 | $0.01 | $3.00 |
| 9 | Long joint sealant (40600370) | LF | 398 | $26.36 | $21.24 |
| 10 | Temporary ramp (40600990) | SY | 94 | $0.01 | $15.00 |
| 11 | HMA BC IL-9.5 N70 (40602985) | TON | 36 | $250.00 | $650.00 |
| 12 | P HMA SC IL-9.5 D N70 (40604162) | TON | 31 | $250.00 | $750.00 |
| 13 | HMA surf rem 3 1/4 (44000162) | SY | 578 | $16.00 | $50.00 |
| 14 | CL B patch T2 14 (44201019) | SY | 32 | $350.00 | $760.00 |
| 15 | Dowel bars 1 1/2 (44201299) | EACH | 80 | $27.50 | $47.20 |
| 16 | Saw cuts (44213200) | LF | 224 | $7.50 | $17.10 |
| 17 | Agg wedge SHLD type B (48102100) | TON | 10 | $85.00 | $164.00 |
| 18 | HMA shoulders 3 1/4 (48203010) | SY | 224 | $43.00 | $115.00 |
| 19 | Conc rem (50102400) | CY | 15.30 | $2,750.00 | $3,760.00 |
| 20 | Protective shield (50157300) | SY | 272 | $85.00 | $96.30 |
| 21 | Conc sup-STR (50300255) | CY | 15.30 | $3,000.00 | $3,690.00 |
| 22 | Protective coat (50300300) | SY | 42 | $2.50 | $21.80 |
| 23 | Reinf bars, epoxy CTD (50800205) | LB | 2,420 | $4.25 | $3.85 |
| 24 | Bar splicers (50800515) | EACH | 24 | $67.84 | $83.30 |
| 25 | Pref JT strip seal (52000110) | LF | 111 | $260.00 | $403.00 |
| 26 | Granular backfill STR (58600101) | CY | 3 | $250.00 | $1,820.00 |
| 27 | Contr low-streng matl (59300100) | CY | 1.80 | $1,000.00 | $1,890.00 |
| 28 | Shoulder rum strip 16 (64200116) | LF | 267 | $59.60 | $57.80 |
| 29 | Mobilization (67100100) | LS | 1 | $26,350 | $40,000 |
| 30 | Traf cont-prot 701401 (70100205) | EACH | 1 | $0.01 | $14,675 |
| 31 | Traf cont-prot 701402 (70100207) | EACH | 1 | $65,350 | $14,675 |
| 32 | TR cont surveillance (70103815) | CAL DAY | 60 | $0.01 | $0.10 |
| 33 | Changeable message SN (70107025) | CAL DAY | 60 | $62.50 | $20.00 |
| 34 | Short term pavt mking (70300100) | LF | 8,599 | $0.01 | $1.35 |
| 35 | SHRT TRM pavt MK rem (70300150) | SF | 2,868 | $0.01 | $1.20 |
| 36 | Temp conc barrier (70400100) | LF | 612.50 | $37.50 | $45.00 |
| 37 | Rel temp conc barrier (70400200) | LF | 550 | $17.50 | $10.00 |
| 38 | Imp attn temp NRN TL3 (70600251) | EACH | 1 | $6,500.00 | $3,500.00 |
| 39 | Imp attn rel NRN TL3 (70600352) | EACH | 1 | $2,250.00 | $750.00 |
| 40 | Pref PL PM TD STD L 9 (78004645) | LF | 316 | $9.90 | $13.95 |
| 41 | Mod ureth PM line 4 (78009004) | LF | 2,974 | $1.65 | $2.25 |
| 42 | GRV RCSD PVT MRKG 5 (78011025) | LF | 1,488 | $2.20 | $1.05 |
| 43 | GRV RCSD PVT MRKG 10 (78011050) | LF | 316 | $2.20 | $2.65 |
| 44 | Raised refl pavt MKR (78100100) | EACH | 2 | $825.00 | $1,500.00 |
| 45 | Raised ref PVT MK rem (78300200) | EACH | 2 | $10.00 | $104.00 |
| 46 | PVT MKG rem WTR blast (78300202) | SF | 655 | $8.80 | $6.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.
Every contract let that day: IDOT letting of January 17, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.