IDOT contract 66R64 bid tabulation
Section (70VBR)BRR. Let by Illinois DOT on April 24, 2026, Lasalle, District 03. 3 bids received; low bid $660,277 by D. Construction, Inc..
- Owner
- Illinois DOT
- Letting
- 24 APR 2026
- Pay items
- 54
- Data through
- 18 SEP 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | D. Construction, Inc. | $660,277 | Low |
| 2 | Gillan Construction LLC | $814,379 | +23% |
| 3 | Gensini Excavating, Inc. | $919,630 | +39% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. D. Construction, Inc. | 2. Gillan Construction LLC | 3. Gensini Excavating, Inc. |
|---|---|---|---|---|---|---|
| 1 | Anti-graffiti coating (X0327999) | SF | 1,572 | $36.30 | $36.30 | $36.52 |
| 2 | Clean app slab drain (X1300003) | EACH | 6 | $400.00 | $700.00 | $553.30 |
| 3 | Floor drains cleaned (X5030539) | EACH | 8 | $300.00 | $450.00 | $553.30 |
| 4 | Struct steel remov (X5051204) | LB | 77 | $45.00 | $30.00 | $45.10 |
| 5 | Rem & RE-E EX BR rail (X5091742) | LF | 55 | $90.00 | $40.00 | $135.15 |
| 6 | Linear delin panels 4 (X6350204) | EACH | 16 | $125.00 | $50.00 | $55.33 |
| 7 | Linear delin panels 6 (X6350206) | EACH | 8 | $250.00 | $60.00 | $83.00 |
| 8 | Traf cont-prot BLR 21 (X7011800) | LS | 1 | $0.01 | $1,100.00 | $4,315.75 |
| 9 | Temp info signing (X7200061) | SF | 84 | $30.00 | $38.50 | $55.33 |
| 10 | RRPM reflector removl (X7830050) | EACH | 8 | $40.00 | $57.00 | $22.13 |
| 11 | Appr slab repair (PD) (Z0001800) | SY | 5 | $1,500.00 | $2,000.00 | $2,513.05 |
| 12 | Conc curb repair (Z0012500) | LF | 4 | $250.00 | $225.00 | $140.23 |
| 13 | Earth excavation (20200100) | CY | 100 | $50.00 | $99.00 | $99.59 |
| 14 | Sub gran mat B 6 (31101400) | SY | 529 | $14.00 | $22.00 | $22.13 |
| 15 | Bit matls tack CT (40600290) | LB | 476 | $0.01 | $1.76 | $1.77 |
| 16 | Curb rem (44000300) | LF | 319 | $10.00 | $2.15 | $2.16 |
| 17 | Paved SHLD removal (44004250) | SY | 508 | $20.00 | $14.30 | $14.39 |
| 18 | HMA shoulders 10 (48203037) | SY | 529 | $60.00 | $93.50 | $94.06 |
| 19 | Conc rem (50102400) | CY | 27.10 | $2,500.00 | $4,000.00 | $4,628.74 |
| 20 | Protective shield (50157300) | SY | 32 | $160.00 | $160.00 | $304.31 |
| 21 | Conc sup-STR (50300255) | CY | 27.10 | $2,500.00 | $4,000.00 | $5,017.95 |
| 22 | Protective coat (50300300) | SY | 77 | $1.00 | $8.00 | $50.71 |
| 23 | F & E struct steel (50500405) | LB | 121 | $55.00 | $45.00 | $67.32 |
| 24 | Reinf bars, epoxy CTD (50800205) | LB | 3,770 | $3.50 | $4.50 | $4.16 |
| 25 | Bar splicers (50800515) | EACH | 52 | $65.00 | $55.00 | $55.93 |
| 26 | Pref JT strip seal (52000110) | LF | 170 | $250.00 | $450.00 | $283.98 |
| 27 | Anchor bolts 1 (52100520) | EACH | 6 | $150.00 | $165.00 | $216.90 |
| 28 | Deck slab rep (part) (53016000) | SY | 2 | $1,750.00 | $2,500.00 | $6,672.41 |
| 29 | Deck slab rep (FD-T1) (53016001) | SY | 2 | $2,500.00 | $3,000.00 | $6,720.80 |
| 30 | STR rep con DP = < 5 (53212754) | SF | 24 | $300.00 | $400.00 | $1,645.05 |
| 31 | Epoxy crack injection (59000200) | LF | 199 | $66.00 | $60.00 | $38.73 |
| 32 | HMA SHLD curb (66101150) | LF | 319 | $40.00 | $25.00 | $49.08 |
| 33 | Mobilization (67100100) | LS | 1 | $20,800 | $45,000 | $23,660 |
| 34 | Traf cont-prot 701321 (70100405) | EACH | 2 | $28,896 | $30,000 | $29,463 |
| 35 | TR cont & prot 701801 (70102642) | EACH | 1 | $0.01 | $1,100.00 | $2,766.51 |
| 36 | Temp BR traf signals (70106500) | EACH | 2 | $40,000 | $22,440 | $24,013 |
| 37 | Temp rumble strips (70106700) | EACH | 12 | $1,100.00 | $1,100.00 | $995.94 |
| 38 | Changeable message SN (70107025) | CAL DAY | 88 | $50.00 | $85.80 | $165.99 |
| 39 | Short term pavt mking (70300100) | LF | 479 | $0.01 | $16.50 | $2.21 |
| 40 | SHRT TRM pavt MK rem (70300150) | SF | 160 | $0.01 | $22.00 | $4.98 |
| 41 | Temp conc barrier (70400100) | LF | 700 | $30.00 | $45.00 | $89.49 |
| 42 | Rel temp conc barrier (70400200) | LF | 687.50 | $15.00 | $15.00 | $45.56 |
| 43 | Imp attn temp NRN TL3 (70600251) | EACH | 4 | $7,000.00 | $5,500.00 | $3,541.13 |
| 44 | Imp attn rel NRN TL3 (70600352) | EACH | 4 | $2,500.00 | $2,750.00 | $663.96 |
| 45 | Sign panel T1 (72000100) | SF | 15 | $30.80 | $77.00 | $39.96 |
| 46 | Remov sin pan assy TA (72400100) | EACH | 2 | $104.50 | $313.00 | $96.94 |
| 47 | Rem & rel sign panel T2 (72400740) | SF | 11 | $60.50 | $71.50 | $176.25 |
| 48 | Wood sin support (73000100) | LF | 60 | $28.60 | $60.00 | $35.93 |
| 49 | Mod ureth PM line 4 (78009004) | LF | 4,092 | $2.53 | $2.53 | $2.93 |
| 50 | Mod ureth PM line 6 (78009006) | LF | 220 | $5.06 | $5.06 | $4.43 |
| 51 | Replacement reflector (78100300) | EACH | 8 | $198.00 | $88.00 | $44.26 |
| 52 | Grdrail ref type A (78200005) | EACH | 24 | $30.00 | $25.00 | $22.13 |
| 53 | Barr wall ref type C (78200011) | EACH | 21 | $30.00 | $25.00 | $11.07 |
| 54 | PVT MKG rem WTR blast (78300202) | SF | 1,473 | $3.58 | $3.40 | $4.70 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.
Every contract let that day: IDOT letting of April 24, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.