IDOT contract 68C93 bid tabulation

Section 72[6RS;(6-1)RS-1]. Let by Illinois DOT on June 12, 2026, Peoria, District 04. 2 bids received; low bid $10,996,119 by Advanced Asphalt Company.

Owner
Illinois DOT
Letting
12 JUN 2026
Pay items
62
Data through
18 SEP 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Advanced Asphalt Company$10,996,119Low
2R. A. Cullinan and Son, a div of UCM, Inc.$11,150,809+1.0%
IDOT contract 68C93: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Advanced Asphalt Company2. R. A. Cullinan and Son, a div of UCM, Inc.
1Constr sta layout (XZ013798)LS1$15,000$6,388.85
2Recoverable delineatr (X2600002)EACH233$65.00$155.00
3HMA surf rem SPL (X4400196)SY7,411$16.50$33.99
4CL A patch T4 10 SPL (X4420559)SY1,026.50$255.00$255.00
5Linear delin panels 4 (X6350204)EACH156$40.00$40.00
6Conc bar wall R&R L1 (X6370101)LS1$17,250$14,718
7Traf cont & prot SPL (X7010216)LS1$77,000$104,869
8GDRL agg eros cont (Z0001002)TON2,418$115.00$110.34
9Drainage STR removed (Z0018700)EACH14$2,300.00$1,914.62
10Erosion cont curb rem (Z0020805)LF7,168.70$10.00$5.01
11Trainees (Z0076600)HR5,000$0.80$0.80
12Trainees TPG (Z0076604)HR5,000$15.00$15.00
13Earth exc wid (20200500)CY55.40$125.00$104.74
14Mowing (25000750)ACRE40$120.00$120.00
15Sub gran mat A (31100100)TON95.20$87.50$110.38
16HMA base cse 4 1/4 (35501301)SY54,954$29.50$28.61
17HMA base cse 10 (35501324)SY952.10$70.00$104.90
18P bit matls tack CT (40600295)LB208,905$0.90$1.08
19Matl transfer device (40600405)TON31,292$4.65$3.07
20HMA surf rem butt JT (40600982)SY1,158.10$33.50$15.37
21PCC surf rem butt JT (40600985)SY875$41.50$22.37
22Temporary ramp (40600990)SY1,344.40$15.00$5.85
23P HMA BC IL-9.5 N70 (40603208)TON8,927$130.00$138.35
24HMA SC IL-9.5FG D N50 (40604010)TON6,594$120.00$160.22
25P SC SMA 12.5 E N80 (40605034)TON10,202$155.00$183.33
26Incidental HMA surf (40800050)TON142.40$250.00$285.00
27HMA surf rem 3/4 (44000152)SY1,577$5.00$8.48
28HMA surf rem 3 3/4 (44000164)SY3,518.30$6.10$7.88
29HMA surf rem 4 1/4 (44000166)SY52,685$7.45$5.83
30Paved SHLD removal (44004250)SY785.50$22.00$21.62
31CL A patch T2 10 (44200553)SY88$300.00$300.00
32CL A patch T3 10 (44200557)SY80$300.00$300.00
33CL A patch T4 10 (44200559)SY3,096.90$250.00$250.00
34CL A patch T4 12 (44200583)SY186.67$260.00$260.00
35Patch reinforcement (44213000)SY4,478.10$95.00$95.00
36Saw cuts (44213200)LF5,735.60$2.00$2.00
37Tie bars 3/4 (44213204)EACH1,638$5.00$5.00
38Aggregate SHLDS B (48101200)TON1,706$37.75$66.44
39HMA shoulders (48203100)TON5,769$120.00$141.17
40Conc struct (50300225)CY14$1,196.85$1,875.00
41Reinf bars, epoxy CTD (50800205)LB1,110$4.72$6.50
42SPBGR TY A 6FT posts (63000001)LF11,925$33.00$33.00
43SPGR att to culvert (63000030)LF68.75$275.00$275.00
44Traf bar term T2 (63100045)EACH13$2,200.00$2,200.00
45Traf bar term T6 (63100085)EACH2$4,425.00$4,425.00
46TR bar TRM T1 SPL tan (63100167)EACH13$3,700.00$3,700.00
47Guardrail remov (63200310)LF12,360$6.25$6.25
48Shoulder rum strip 8 (64200108)LF51,331$0.35$0.25
49Imp atten FRD nar TL3 (64300260)EACH1$23,975$23,975
50Mobilization (67100100)LS1$625,000$32,350
51Changeable message SN (70107025)CAL DAY720$25.00$75.00
52Short term pavt mking (70300100)LF5,415$2.00$2.37
53SHRT TRM pavt MK rem (70300150)SF1,805$2.50$9.18
54Temp PVT MK line 6 - paint (70300241)LF73,845$0.01$0.25
55Temp PVT MK line 8 - paint (70300251)LF549.24$0.01$0.35
56Terminal marker - DA (72501000)EACH28$42.00$42.00
57Pref PL PM TD STD L 6 (78004630)LF73,845$5.80$4.55
58Pref PL PM TD STD L 8 (78004640)LF549.24$12.50$19.00
59GRV RCSD PVT MRKG 7 (78011035)LF73,845$0.60$0.45
60GRV RCSD PVT MRKG 9 (78011045)LF549.24$1.00$0.65
61Raised refl pavt MKR (78100100)EACH323$53.00$47.00
62Raised ref PVT MK rem (78300200)EACH323$14.00$31.53
IDOT contract 68C93: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.

Every contract let that day: IDOT letting of June 12, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy